John E. Gregory & Son, Inc. v. A. Guenther & Sons Co.

432 N.W.2d 584, 147 Wis. 2d 298, 1988 Wisc. LEXIS 106
CourtWisconsin Supreme Court
DecidedDecember 22, 1988
Docket87-0437
StatusPublished
Cited by12 cases

This text of 432 N.W.2d 584 (John E. Gregory & Son, Inc. v. A. Guenther & Sons Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John E. Gregory & Son, Inc. v. A. Guenther & Sons Co., 432 N.W.2d 584, 147 Wis. 2d 298, 1988 Wisc. LEXIS 106 (Wis. 1988).

Opinion

WILLIAM G. CALLOW, J.

This is a review of an unpublished order of the court of appeals reversing a judgment of the circuit court for Milwaukee county, Judge Michael P. Sullivan, which granted damages to John E. Gregory & Son, Inc., in the amounts of $9,068.15 from Milwaukee County and $1,641.07 from A. Guenther & Sons Co., Inc. Milwaukee county appealed the judgment entered against it. Guenther did not appeal the judgment entered against it.

The issue before this court is whether the circuit court erred by including a question in its special verdict which allowed a jury to find Milwaukee county liable for damages resulting from delay in the performance of a construction contract when the cause of the delay was not contemplated by the parties at the time they entered into the contract. We conclude that the circuit court erred, and we modify and affirm the court of appeals’ order. We find that this case need not be remanded for a new trial. ■

On March 12, 1980, John E. Gregory & Son, Inc., (Gregory) entered into a contract with A. Guenther & *300 Sons Co., Inc., (Guenther) agreeing to perform furring, lathing, plastering, and drywall work as part of a remodeling project at the sixth floor of Milwaukee County General Hospital. The contract provided that Gregory would perform the work "per plans, specifications, and addendums 1 and 2 including all taxes all for the sum of $150,000.00.” In addition, there were five change orders which increased the contract price by $13,551.

The specifications for the project included the following provisions:

GC-53 SUBCONTRACTING
The Contractor agrees to bind every Subcontractor (and every Subcontractor of a Subcontractor) and every Subcontractor agrees to be bound by the terms of the Instructions to Bidders, Contract Agreement, Specifications, General Conditions, Drawings, and the Proposal, as far as applicable to his work.
SC-7
15. DELAYS AND EXTENSION OF TIME
1. Owner shall not be liable to the contractor and/or any subcontractor for claims or damages or monetary claims of any nature caused by or arising out of delays. The sole remedy against Owner for delays shall be the allowance to claimant of additional time for completion of work, the amount thereof to be determined by the Architect in accor *301 dance with the foregoing provisions of above subparagraphs.

We recognize that the defense contained in this provision is only available to Milwaukee county. It is not available to Guenther.

In addition, the specifications included SC-7 Item No. 16. A. 1, which provides that "Time is [of] the essence of this contract.”

The court of appeals rendered its order on the factual record set forth in affidavits and exhibits. A transcript of the trial was not furnished. We set forth Gregory’s complaints concerning Guenther’s performance on this project because Gregory contends that the county was in a position to direct Guenther’s activities. In its affidavit, Gregory contends that Guenther caused several delays during the performance of the contract. Gregory insists, first, that Guenther’s delay in readying the premises interfered with Gregory’s ability to begin work on the project promptly. According to Gregory, Guenther told Gregory that the project would start in late March or early April of 1980 and would be completed in 300 days. Before Gregory could begin work, Guenther was required to demolish the existing sixth floor improvements. However, Guenther did not complete demolition until late May of 1980. Because Gregory could not start at the scheduled time, it lost two months of working time at labor rates existing prior to a carpenter’s strike. The strike halted construction between June and September 11, 1980.

Gregory also contends that Guenther’s poor scheduling of the work of its employees and other contractors interfered with Gregory’s ability to perform the contract efficiently and productively. Grego *302 ry claims that the contract provided that Gregory start the south wing construction approximately seven days after completion of the north wing. Gregory declares that, although it substantially completed the work on the north wing on February 26, 1981, due to Guenther’s delay, the work on the south wing did not begin until August 3, 1981, more than five months later. Gregory claims that Guenther caused many other delays which prevented Gregory from working efficiently and productively.

Gregory ceased performance on December 7, 1981. This was 465 days after the job had begun (not including the strike period). On June 30,1983, Gregory filed suit against Guenther. On August 23, 1984, Gregory amended the complaint making Milwaukee county (County) an additional defendant. The amended complaint alleged that Gregory entered the March 12,1980, contract in reliance upon representations by Guenther and the County that the project would be completed in 300 days. Gregory claims that Guenther and the County impeded Gregory’s performance of the contract, causing Gregory to suffer damages totaling $66,514.05. The amended complaint on which the case was tried specifically alleges the County delayed the progress of construction and failed to supervise and manage the work of Guenther and other contractors. The amended complaint alleges that this resulted in unexpected delays.

On July 29, 1985, the County filed a motion for summary judgment. The circuit court denied this motion on November 5, 1985. It noted that First Savings & Trust Co. v. Milwaukee County, 158 Wis. 207, 240, 148 N.W. 22, 148 N.W. 1093 (1914), set forth several exceptions to the general rule that "no damage for delay” clauses are to be enforced. The case *303 held that the exceptions are fraud, bad faith, and unnecessary orders which were the result of inexcusable ignorance or incompetence. Id. The circuit court held that the existence of these exceptions was a question of fact to be decided by a jury.

At the close of the trial the circuit court submitted a special verdict to the jury. The special verdict contained no questions regarding fraud or bad faith, as both parties agreed that there was no evidence in the record to support such a finding. The jury was asked whether delay was due to unnecessary orders by the County. It answered, "No.” Over the objection of defense counsel, Question No. 3 was included in the special verdict:

"Were the kinds of the delays encountered on the County Hospital remodeling job of a type not reasonably to be expected by the parties at the time they entered into the contracts?”

The counsel for the County objected to the inclusion of this question contending that a delay "not reasonably to be expected” was not one of the exception to the enforcement of "no damage for delay” clauses set forth in First Savings, supra. The objection was overruled, and the jury answered this question, "Yes.” It found that Gregory suffered $9,622 in damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Markwed Excavating, Inc. v. City of Mandan
2010 ND 220 (North Dakota Supreme Court, 2010)
Law Co., Inc. v. Mohawk Const. & Supply Co.
702 F. Supp. 2d 1304 (D. Kansas, 2010)
Northern Clearing, Inc. v. Larson-Juhl, Inc.
688 N.W.2d 783 (Court of Appeals of Wisconsin, 2004)
J.A. Jones Construction Co. v. Lehrer McGovern Bovis, Inc.
89 P.3d 1009 (Nevada Supreme Court, 2004)
U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc.
480 S.E.2d 447 (Supreme Court of South Carolina, 1997)
Roy A. Elam Masonry, Inc. v. Fru-Con Construction Corp.
922 S.W.2d 783 (Missouri Court of Appeals, 1996)
State Highway Administration v. Greiner Engineering Sciences, Inc.
577 A.2d 363 (Court of Special Appeals of Maryland, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
432 N.W.2d 584, 147 Wis. 2d 298, 1988 Wisc. LEXIS 106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-e-gregory-son-inc-v-a-guenther-sons-co-wis-1988.