Northern Clearing, Inc. v. Larson-Juhl, Inc.

688 N.W.2d 783
CourtCourt of Appeals of Wisconsin
DecidedSeptember 21, 2004
Docket04-0010
StatusPublished

This text of 688 N.W.2d 783 (Northern Clearing, Inc. v. Larson-Juhl, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Clearing, Inc. v. Larson-Juhl, Inc., 688 N.W.2d 783 (Wis. Ct. App. 2004).

Opinion

Northern Clearing, Inc., Plaintiff-Respondent,
v.
Larson-Juhl, Inc., Defendant-Appellant.

No. 04-0010.

Court of Appeals of Wisconsin.

Opinion Filed: September 21, 2004.

Before Cane, C.J., Hoover, P.J., and Peterson, J.

¶1 PER CURIAM.

Larson-Juhl, Inc., appeals a judgment awarding $211,037.66 damages, plus costs and prejudgment interest, to Northern Clearing, Inc. Larson-Juhl argues: (1) Northern's subcontract prohibited damages for delay; (2) the trial court erroneously awarded Northern damages on a theory of quantum meruit; (3) the court applied an erroneous measure of damages and miscalculated damages; and (4) Northern is not entitled to prejudgment interest. We affirm the judgment.

Standard of Review

¶2 Quantum meruit is an equitable remedy. Baierl v. McTaggart, 2001 WI 107, 245 Wis. 2d 632, 635 n.1, 629 N.W.2d 277. The decision to grant equitable relief is addressed to trial court discretion. Zinda v. Krause, 191 Wis. 2d 154, 175, 528 N.W.2d 55 (Ct. App. 1995). "Because the exercise of discretion is so essential to the trial court's functioning, we generally look for reasons to sustain discretionary decisions." Schneller v. St. Mary's Hosp. Med. Ctr., 155 Wis. 2d 365, 374, 455 N.W.2d 250 (Ct. App. 1990), aff'd, 162 Wis. 2d 296, 470 N.W.2d 873 (1991). Therefore, we must look to the record to determine whether the trial court undertook a reasonable inquiry and examination of the facts, and whether the record discloses a reasonable basis for the trial court's decision. Hedtcke v. Sentry Ins. Co., 109 Wis. 2d 461, 471, 326 N.W.2d 727 (1982). In the exercise of discretion, a trial judge may reach a conclusion which another judge or court may not reach. Hartung v. Hartung, 102 Wis. 2d 58, 66, 306 N.W.2d 16 (1981).

¶3 When reviewing the facts the trial court relied upon in reaching its discretionary decision, we do not overturn the facts found unless clearly erroneous. Michael A.P. v. Solsrud, 178 Wis. 2d 137, 153, 502 N.W.2d 918 (Ct. App. 1993). Our role is to search the record for evidence to support the findings the trial court made, not for evidence to support findings the court could have but did not make. In re Estate of Dejmal, 95 Wis. 2d 141, 154, 289 N.W.2d 813 (1980). When the trial judge is the finder of fact and there is conflicting testimony, the trial judge is the ultimate arbiter of the credibility. Gehr v. Sheboygan, 81 Wis. 2d 117, 122, 260 N.W.2d 30 (1977).

Facts

¶4 With these standards in mind, we turn to the facts of record supporting the trial court's determination. Larson-Juhl retained Nelson Surveying to provide surveying services for the construction of a new manufacturing facility. Larson-Juhl also contracted with C.E. Doyle, LLC, a general contractor, to build the facility. Doyle subcontracted with Northern to do excavation, clearing and grading.

¶5 At the commencement of the project, Nelson placed the grading stakes in a manner that later was determined to be erroneous. The first day that Northern was on the job, Northern's project manager, Dale Brevak, asked Michael Pero of Nelson to check his stakes because they did not look right. Pero checked them, but said that they were placed correctly. Brevak continued to voice his concern to Ed Schueler, Doyle's project supervisor, and Phil Wisner, the plant manager of Larson-Juhl. Finally, Schueler halted the project to re-survey it. Schueler gave Brevak a corrected plan and asked Brevak to work on it as soon as possible.

¶6 Phil Wisner testified that after the excavation had started, he had addressed the grade problems with Brevak, who advised he was following the surveyor's stakes. To resolve the issue, Wisner drove out to the site to halt the excavation until the problem could be identified. At the site, he met with Brevak, Nelson, and Schueler, who had already decided that the project needed to be halted to determine the cause of what was determined to be a grade discrepancy.

¶7 Schueler testified at trial,

A lot of times there is a situation comes on a job and you have to take care of it immediately. And in the area you're working in, it needs to be cut out right away, the equipment is there, it's the most reasonable way to do it is right away.
....
If you set it aside and come back to it, it usually cost more. And most people understand that. So that's why sometimes a verbal thing to proceed is necessary.

¶8 At a meeting, Chuck Doyle indicated that he was "willing to go along with whatever it was going to take to get the job done.... They encouraged us to keep on going because there was some possible liability down the road with other subcontractors that may be delayed by us not completing our part of the job." Brevak did not recall discussions regarding quantities of material or prices. He explained that typically, however, extra work due to unforeseen conditions was done on a time and material basis. Brevak believed that C.E. Doyle, LLC, would obtain a change order from Larson-Juhl to compensate Northern.

¶9 Wayne Cameron, an engineer at Larson-Juhl, testified that he brought the problem of the grade discrepancy to Brevak's attention. He stated that the amount of fill was too large in comparison to the amount of cutting that was needed. He stated that he "continued to question" Brevak. He testified that he met with Schueler and determined that "something was really wrong based on how much fill has been taken off the site ...."

¶10 Doyle testified, "The agreement was that he would proceed and at some time, when it was documented or when it was realized what really the extent of the job would be, he would at that time submit a change order." No change order was presented at that time, because there "was no damage amounts at that time." He explained: "If he didn't provide those services then there probably would be other damages that we would have to address and that's about all we knew at that point."

¶11 Although Richard Vernon, the president of Northern, had asked for assurance of payment for the extra work, Doyle "couldn't authorize any written authorization for the work that was done wrong because at the time that it was done wrong I wasn't even sure what parties were guilty of what." He later learned that Northern had nothing to do with the staking error. Doyle further testified "the problem seems to be that Nelson's survey didn't take that into account when they staked the project, that we were using the old DOT number that they provided to us."

¶12 The entire site consisted of approximately seventeen acres that had to be cleared, stripped of topsoil, regraded and reshaped. The footprint of the building itself was approximately three to four acres. Due to the staking error, the site was re-staked and approximately seventy percent of the seventeen-acre site needed to be re-filled to raise the elevation by two feet.

¶13 The trial court found that the general contractor, C.E. Doyle LLC, entered into a subcontract with Northern to perform excavating and grading service for $134,500.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Terpstra v. Soiltest, Inc.
218 N.W.2d 129 (Wisconsin Supreme Court, 1974)
Charolais Breeding Ranches, Ltd. v. FPC Securities Corp.
279 N.W.2d 493 (Court of Appeals of Wisconsin, 1979)
Schneller v. St. Mary's Hospital Medical Center
470 N.W.2d 873 (Wisconsin Supreme Court, 1991)
John E. Gregory & Son, Inc. v. A. Guenther & Sons Co.
432 N.W.2d 584 (Wisconsin Supreme Court, 1988)
Schneller Ex Rel. Schneller v. St. Mary's Hospital Medical Center
455 N.W.2d 250 (Court of Appeals of Wisconsin, 1990)
In Matter of Estate of Dejmal
289 N.W.2d 813 (Wisconsin Supreme Court, 1980)
Gename v. Benson
153 N.W.2d 571 (Wisconsin Supreme Court, 1967)
Ramsey v. Ellis
484 N.W.2d 331 (Wisconsin Supreme Court, 1992)
Hedtcke v. Sentry Insurance
326 N.W.2d 727 (Wisconsin Supreme Court, 1982)
Stack Construction Co. v. Chenenoff
137 N.W.2d 66 (Wisconsin Supreme Court, 1965)
Michael A.P. v. Solsrud
502 N.W.2d 918 (Court of Appeals of Wisconsin, 1993)
Wm. Beaudoin & Sons, Inc. v. Milwaukee County
217 N.W.2d 373 (Wisconsin Supreme Court, 1974)
Baierl v. McTaggart
2001 WI 107 (Wisconsin Supreme Court, 2001)
State v. Caban
563 N.W.2d 501 (Wisconsin Supreme Court, 1997)
Fieldhouse Landscape, Inc. v. Gentile
107 N.W.2d 491 (Wisconsin Supreme Court, 1961)
Zinda v. Krause
528 N.W.2d 55 (Court of Appeals of Wisconsin, 1995)
Hartung v. Hartung
306 N.W.2d 16 (Wisconsin Supreme Court, 1981)
Theuerkauf v. Sutton
306 N.W.2d 651 (Wisconsin Supreme Court, 1981)
State v. Echols
499 N.W.2d 631 (Wisconsin Supreme Court, 1993)
Mead v. Ringling
64 N.W.2d 222 (Wisconsin Supreme Court, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
688 N.W.2d 783, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-clearing-inc-v-larson-juhl-inc-wisctapp-2004.