U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc.

480 S.E.2d 447, 325 S.C. 129, 1997 S.C. LEXIS 15
CourtSupreme Court of South Carolina
DecidedJanuary 20, 1997
Docket24551
StatusPublished
Cited by24 cases

This text of 480 S.E.2d 447 (U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc., 480 S.E.2d 447, 325 S.C. 129, 1997 S.C. LEXIS 15 (S.C. 1997).

Opinion

WALLER, Justice:

The following question has been certified to this Court by the United States District Court for the District of South Carolina:

Under the facts of this case, what exceptions, if any, to an unambiguous no-damages-for-delay clause in a construction contract would the South Carolina Supreme Court recognize?

*132 FACTS

Metric, general contractor for construction of a new federal prison in Estill, S.C., hired Williams Electric Company as the major electrical subcontractor. The contract, written by Metric, contains the following no-damages-for-delay clause:

7. Extensions of Time_ In the event the Subcontractor’s performance of this Subcontract is delayed or interfered with by acts or omissions of the Owner, Contractor or other subcontractors, Subcontractor may request an extension of time for the performance of this Subcontract as hereinabove provided, but shall not be entitled to any increase in the subcontract Price or to damages or additional compensation as a consequence of such delays or interference except to the extent that the Contract entitles Contractor to compensation therefor and then only to the extent of any amounts that Contractor, on behalf of Subcontractor, recovers from Owner for such delays or interference.

During construction of the prison, Williams suffered delays caused primarily by Metric’s failure to properly coordinate and manage the subcontractors. As a result, Williams incurred more labor and material costs than anticipated and was required to remain on the project for months after its scheduled completion date. Subsequent to completion of the prison, Williams brought this action in the Federal District Court under the Miller Act 1 for additional expenses caused by the delays. Metric answered and sought summary judgment, contending it is not liable by virtue of the no-damages-for-delay clause.

DISCUSSION

Generally, no-damage-for-delay provisions are valid and enforceable so long as they meet ordinary rules governing the validity of contracts. See Annot, Validity and Construction of “No Damage Clause with Respect to Delay in Building or Construction Contract, 74 A.L.R.3d 187, § 2[a] (1976). A majority of jurisdictions, however, recognize certain exceptions to such clauses. Id. Among the recognized exceptions *133 are (a) delay caused by fraud, misrepresentation, or other bad faith; (b) delay caused by active interference; (c) delay which has extended such an unreasonable length of time that the party delayed would have been justified in abandoning the contract; (d) delay that was not contemplated by the parties; and (e) delay caused by gross negligence.

We premise our discussion by recognizing that, in South Carolina, there exists in every contract an implied obligation of good faith and fair dealing. Adams v. Creel, 320 S.C. 274, 465 S.E.2d 84 (1995); Parker v. Byrd, 309 S.C. 189, 420 S.E.2d 850 (1992); Tharpe v. G.E. Moore, 254 S.C. 196, 174 S.E.2d 397 (1970). Accordingly, to the extent these exceptions give rise to a violation of this obligation, we find them to be a logical extension of South Carolina law. We address the exceptions seriatim.

a. Delay caused by fraud, misrepresentation, or other bad faith.

The most widely recognized exception to the enforceability of a no-damage-for delay clause is fraud, misrepresentation or bad faith. 74 A.L.R.3d at 215-216, § 7(b). Of those cases addressing this exception, it appears to have been adopted in all but one jurisdiction. See Owen Constr. Co. v. Iowa State Dept. of Transp., 274 N.W.2d 304 (Iowa 1979); Jensen Constr. Co. v. Dallas County, 920 S.W.2d 761 (Tex. App.1996); Newberry Square Development Corp. v. Southern Landmark, Inc., 578 So.2d 750 (Fla.1991); J & B Steel Contractors, Inc. v. Iber & Sons, 162 Ill.2d 265, 205 Ill.Dec. 98, 642 N.E.2d 1215 (1994); White Oak Coloration v. Department of Transportation, 217 Conn. 281, 585 A.2d 1199 (Conn. 1991); State Highway Admin. v. Greiner, 83 Md.App. 621, 577 A.2d 363 (1990) (all recognizing exception for fraud or bad faith). But see Marsch v. Southern N.E.R. Corp, 230 Mass. 483, 120 N.E. 120 (1918) (declining to adopt fraud exception).

Clearly, fraud, misrepresentation and bad faith in performance of one’s contractual duties would give rise to a violation of the implied obligation of good faith and fair dealing. See O’Quinn v. Beach Associates, 272 S.C. 95, 249 S.E.2d 734 (1978) (recognizing that a contract may be avoided on grounds of fraud). Accordingly, we find that adoption of this exception

*134 is a logical extension of South Carolina law and join the majority of jurisdictions in adopting this exception.

b. Delay caused by active interference

A majority of courts also adopt an exception to a no-damage-for-delay clause in cases of direct, active, willful interference with the work of the contractor. 74 A.L.R.3d at 219-221, § 7(e). See also Newberry Square Development v. Southern Landmark, supra; Owen Constr. Co. v. Iowa State Dept. of Transp., supra; Green Plumbing & Heating Co. v. Turner Constr. Co., 500 F.Supp. 910 (E.D.Mich.1980) (applying Mich, law); Christiansen Bros., Inc. v. State, 90 Wash.2d 872, 586 P.2d 840 (1978). This Court has recognized that where performance of a contract by the vendor is prevented by the vendee, the vendee may not take advantage of the delay. 2 See Shannon v. Freeman, 117 S.C. 480,109 S.E. 406 (1921). Such active interference effectually violates the implied obligation of fair dealing. Accordingly, we find this exception to be a logical extension of South Carolina law. 3

c. Unreasonable delay justifying abandonment of the contract

A number of courts recognize an exception to a no-damage clause where delays are so unreasonable in length or

*135 duration that they amount to an abandonment of the contract, or would justify the contractor’s abandonment. 74 A.L.R.3d at 226-230, § 7(i).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Travelers Casualty & Surety Co. of America
55 F. Supp. 3d 852 (N.D. West Virginia, 2014)
C & H Electric, Inc. v. Bethel
Supreme Court of Connecticut, 2014
Tricon Kent Co. v. Lafarge North America, Inc.
186 P.3d 155 (Colorado Court of Appeals, 2008)
Tupelo Redevelopment Agency v. Gray Corp.
972 So. 2d 495 (Mississippi Supreme Court, 2007)
J.A. Jones Construction Co. v. Lehrer McGovern Bovis, Inc.
89 P.3d 1009 (Nevada Supreme Court, 2004)
Blake Construction Co. v. Upper Occoquan Sewage Authority
587 S.E.2d 711 (Supreme Court of Virginia, 2003)
Volvo Trademark Holding Aktiebolaget v. CLM EQUIP. COMPANY, INC.
236 F. Supp. 2d 536 (W.D. North Carolina, 2002)
Triple R Paving, Inc. v. Broward County
774 So. 2d 50 (District Court of Appeal of Florida, 2000)
Osprey, Inc. v. Cabana Ltd. Partnership
532 S.E.2d 269 (Supreme Court of South Carolina, 2000)
Miss. Transp. Com'n v. Ronald Adams Cont.
753 So. 2d 1077 (Mississippi Supreme Court, 2000)
Mississippi Transp. Com'n v. SCI, INC.
717 So. 2d 332 (Mississippi Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
480 S.E.2d 447, 325 S.C. 129, 1997 S.C. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-fuba-williams-electric-co-v-metric-constructors-inc-sc-1997.