Environmental Solutions International, Inc. v. J.C. Construction, Inc.

CourtCourt of Appeals of South Carolina
DecidedJune 2, 2008
Docket2008-UP-282
StatusUnpublished

This text of Environmental Solutions International, Inc. v. J.C. Construction, Inc. (Environmental Solutions International, Inc. v. J.C. Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Solutions International, Inc. v. J.C. Construction, Inc., (S.C. Ct. App. 2008).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA

In The Court of Appeals


Environmental Solutions International, Inc., Appellant,

v.

J.C. Construction, Inc., Wolfe Creek Construction, Inc., and Woolpert L.L.P.,

of whom:

J.C. Construction, Inc. is Respondent.


Appeal from Colleton County
Jackson V. Gregory, Circuit Court Judge


Unpublished Opinion No. 2008-UP-282
Submitted June 1, 2008 – Filed June 2, 2008


AFFIRMED


R. Clenton Campbell and Grahame E. Holmes, both of Walterboro, for Appellant.

Amanda A. Bailey and M. Mark McAdams, both of Myrtle Beach, for Respondent.


PER CURIAM:  Environmental Solutions International, Inc. appeals the trial judge’s grant of summary judgment, contending the trial judge committed error in finding no issue of material fact as to whether ESI was compensated for services rendered to J.C. Construction, Inc., thus barring claims under quantum meruit and breach of contract.  We affirm.[1]

FACTS

In May 2003, Respondent J.C. Construction, Inc. (JCC), a general construction company, successfully submitted a bid for a project to refurbish a waste water treatment facility for the Town of St. Matthews, South Carolina.  One aspect of the workload required JCC to remove and dispose of sludge from the treatment facility’s basins.  To effectuate the sludge removal, JCC solicited bids for this portion of the work and subcontracted with Appellant Environmental Solutions International, Inc. (ESI) in November 2003.  ESI agreed to payment of $108.00 per ton of sludge removed.  The scope of the sludge removal was based on an estimate by Woolpert, L.L.P. (Woolpert), an engineering consultant hired by the town, and was limited by the terms of the contract.  Under the subcontract, ESI was required to:

Remove, solidify, transport and dispose of approximately 350 tons of waste treatment sludge.  Payment to be determined by measure of sludge hauled to the landfill.  The unit cost rate of $108.00 per ton hauled shall apply (as per the project bid form).  Approximate total commitment for accounting purposes only is $37,800.00.

After contracting with JCC, ESI hired Wolfe Creek Construction, Inc. (Wolfe Creek) to perform the actual removal.  In December 2003, ESI and Wolfe Creek began the removal process.  A number of delays plagued the project from the beginning resulting from leakage in sludge dewatering containers, inclement weather, and the lengthy process required to dry the sludge.  Additionally, the total amount of sludge requiring removal greatly exceeded the scope originally estimated by Woolpert.  In response to this discovery, ESI submitted a change order to JCC, increasing the scope of removal from 350 tons to 5,000 tons to reflect Woolpert’s error in the original estimate.

In April 2004, ESI quit work and left the jobsite, leaving behind a partially-filled dewatering bag of sludge, various equipment, and sawdust used in solidifying the sludge.  In May 2004, ESI faxed JCC a new agreement demanding a price increase from $108.00 per ton to $220.00 per ton for the sludge removal.  ESI alleged the price increase was in line with the increased costs associated with the larger workload which would require more personnel and different equipment in order to meet the project deadlines.  JCC never accepted this agreement and solicited new bids in order to facilitate the removal.  Wolfe Creek offered to complete the project, subcontracted with JCC, and completed all remaining sludge removal.  Wolfe Creek compensated ESI for the materials left behind at the jobsite by giving ESI a $10,350.00 credit.  The credit memo sent to ESI by Wolfe Creek noted the credit was for time, materials, and labor exhausted in filling the remaining bag and for three loads of ESI’s sawdust. 

Thereafter, ESI filed suit against several parties including JCC over the subcontract for sludge removal.  ESI alleged JCC was liable for breach of contract, quantum meruit, conversion, and intentional interference with contractual relations.  JCC moved for summary judgment on all causes of action.  At the hearing, ESI withdrew its claim of conversion.  Subsequently, the trial judge granted JCC’s Motion for Summary Judgment as to all of ESI’s claims. 

DISCUSSION

ESI alleges there are genuine issues of material fact as to whether it was paid under the contract for (1) the total amount of sludge hauled to the landfill and (2) for the sludge pumped into dewatering bags but left at the jobsite, and therefore, the grant of summary judgment was inappropriate as to the claims for quantum meruit and breach of contract.  We disagree. 

In order for a motion of summary judgment to warrant denial, a triable issue must exist.  Worsley Cos., Inc. v. Town of Mount Pleasant, 339 S.C. 51, 55, 528 S.E.2d 657, 660 (2000).  “A court considering summary judgment neither makes factual determinations nor considers the merits of competing testimony; however, summary judgment is completely appropriate when a properly supported motion sets forth facts that remain undisputed or are contested in a deficient manner.”  David v. McLeod Reg’l Med. Ctr., 367 S.C. 242, 250, 626 S.E.2d 1, 5 (2006).    

In the case at bar, ESI has failed to raise a genuine issue of material fact it was not compensated for services provided to JCC.  The record is barren of evidence to support this contention.  Therefore, the trial judge’s grant of summary judgment was appropriate. 

ESI alleges it was not paid for the amount of sludge it disposed of according to the terms of the contract and for the amount of sludge it pumped into dewatering bags and left at the jobsite.  However, ESI did not properly support these claims to the extent necessary to raise a genuine issue of material fact.  As in this case, summary judgment is completely appropriate when facts are contested in a deficient manner.  See David, 367 S.C. at 250, 626 S.E.2d at 5.

1.  Sludge Removal Fully Performed under the Terms of the Contract

ESI alleges that it was not paid for the 350 tons of sludge removed, transported, and disposed of at the dump.  Based on our review of the record, this issue is not preserved.  Even if preserved, the issue fails on the merits. 

This sludge removal was specifically covered by the terms of the contract.  ESI performed under the contract by disposing of approximately 350 tons of sludge and would have a cause of action for breach of contract against JCC if JCC failed to pay for these services.  However, sufficient evidence is not contained in the record to support this contention. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pitcher v. Lauritzen
423 P.2d 491 (Utah Supreme Court, 1967)
David v. McLeod Regional Medical Center
626 S.E.2d 1 (Supreme Court of South Carolina, 2006)
Swanson v. Stratos
564 S.E.2d 117 (Court of Appeals of South Carolina, 2002)
First-Citizens Bank & Trust Co. v. Conway National Bank
317 S.E.2d 776 (Court of Appeals of South Carolina, 1984)
Ro-Lo Enterprises v. Hicks Enterprises, Inc.
362 S.E.2d 888 (Court of Appeals of South Carolina, 1987)
Texcon, Inc. v. Anderson Aviation, Inc.
326 S.E.2d 168 (Supreme Court of South Carolina, 1985)
Daniel v. Georgia Railroad Bank & Trust Co.
334 S.E.2d 659 (Supreme Court of Georgia, 1985)
Regions Bank v. Schmauch
582 S.E.2d 432 (Court of Appeals of South Carolina, 2003)
Worsley Companies v. Town of Mount Pleasant
528 S.E.2d 657 (Supreme Court of South Carolina, 2000)
U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc.
480 S.E.2d 447 (Supreme Court of South Carolina, 1997)
Columbia Wholesale Co. v. Scudder May N.V.
440 S.E.2d 129 (Supreme Court of South Carolina, 1994)
Fuller v. Eastern Fire & Casualty Insurance
124 S.E.2d 602 (Supreme Court of South Carolina, 1962)
HK New Plan Exchange Property Owner I, LLC v. Coker
649 S.E.2d 181 (Court of Appeals of South Carolina, 2007)
Quality Concrete Products, Inc. v. Thomason
172 S.E.2d 297 (Supreme Court of South Carolina, 1970)
Soil Remediation Co. v. Nu-Way Environmental, Inc.
482 S.E.2d 554 (Supreme Court of South Carolina, 1997)
Myrtle Beach Hospital, Inc. v. City of Myrtle Beach
532 S.E.2d 868 (Supreme Court of South Carolina, 2000)
LANDBANK FUND VII, LLC v. Dickerson
632 S.E.2d 882 (Court of Appeals of South Carolina, 2006)
Bishop v. Benson
374 S.E.2d 517 (Court of Appeals of South Carolina, 1988)
Moses v. Commonwealth
600 S.E.2d 162 (Court of Appeals of Virginia, 2004)
QHG of Lake City, Inc. v. McCutcheon
600 S.E.2d 105 (Court of Appeals of South Carolina, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Environmental Solutions International, Inc. v. J.C. Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-solutions-international-inc-v-jc-construction-inc-scctapp-2008.