THIS
OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS
PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.
THE STATE OF SOUTH CAROLINA
In The Court of
Appeals
Environmental Solutions International, Inc., Appellant,
v.
J.C. Construction, Inc., Wolfe Creek Construction, Inc., and
Woolpert L.L.P.,
of whom:
J.C. Construction, Inc. is Respondent.
Appeal from Colleton County
Jackson V. Gregory, Circuit
Court Judge
Unpublished
Opinion No. 2008-UP-282
Submitted June
1, 2008 Filed June 2, 2008
AFFIRMED
R. Clenton Campbell and Grahame E.
Holmes, both of Walterboro, for Appellant.
Amanda A. Bailey and M. Mark McAdams, both
of Myrtle Beach, for Respondent.
PER CURIAM: Environmental
Solutions International, Inc. appeals the trial judges grant of summary
judgment, contending the trial judge committed error in finding no issue of
material fact as to whether ESI was compensated for services rendered to J.C.
Construction, Inc., thus barring claims under quantum meruit and breach of
contract. We affirm.[1]
FACTS
In
May 2003, Respondent J.C. Construction, Inc. (JCC), a general construction
company, successfully submitted a bid for a project to refurbish a waste water
treatment facility for the Town of St. Matthews, South Carolina. One aspect of
the workload required JCC to remove and dispose of sludge from the treatment facilitys
basins. To effectuate the sludge removal, JCC solicited bids for this portion
of the work and subcontracted with Appellant Environmental Solutions
International, Inc. (ESI) in November 2003. ESI agreed to payment of $108.00
per ton of sludge removed. The scope of the sludge removal was based on an
estimate by Woolpert, L.L.P. (Woolpert), an engineering consultant hired by the
town, and was limited by the terms of the contract. Under the subcontract, ESI
was required to:
Remove, solidify, transport and dispose
of approximately 350 tons of waste treatment sludge. Payment to be determined
by measure of sludge hauled to the landfill. The unit cost rate of $108.00 per
ton hauled shall apply (as per the project bid form). Approximate total
commitment for accounting purposes only is $37,800.00.
After
contracting with JCC, ESI hired Wolfe Creek Construction, Inc. (Wolfe Creek) to
perform the actual removal. In December 2003, ESI and Wolfe Creek began the
removal process. A number of delays plagued the project from the beginning
resulting from leakage in sludge dewatering containers, inclement weather, and
the lengthy process required to dry the sludge. Additionally, the total amount
of sludge requiring removal greatly exceeded the scope originally estimated by
Woolpert. In response to this discovery, ESI submitted a change order to JCC,
increasing the scope of removal from 350 tons to 5,000 tons to reflect
Woolperts error in the original estimate.
In
April 2004, ESI quit work and left the jobsite, leaving behind a
partially-filled dewatering bag of sludge, various equipment, and sawdust used
in solidifying the sludge. In May 2004, ESI faxed JCC a new agreement demanding
a price increase from $108.00 per ton to $220.00 per ton for the sludge removal.
ESI alleged the price increase was in line with the increased costs associated
with the larger workload which would require more personnel and different
equipment in order to meet the project deadlines. JCC never accepted this
agreement and solicited new bids in order to facilitate the removal. Wolfe
Creek offered to complete the project, subcontracted with JCC, and completed
all remaining sludge removal. Wolfe Creek compensated ESI for the materials
left behind at the jobsite by giving ESI a $10,350.00 credit. The credit memo
sent to ESI by Wolfe Creek noted the credit was for time, materials, and labor
exhausted in filling the remaining bag and for three loads of ESIs sawdust.
Thereafter,
ESI filed suit against several parties including JCC over the subcontract for
sludge removal. ESI alleged JCC was liable for breach of contract, quantum
meruit, conversion, and intentional interference with contractual relations.
JCC moved for summary judgment on all causes of action. At the hearing, ESI
withdrew its claim of conversion. Subsequently, the trial judge granted JCCs
Motion for Summary Judgment as to all of ESIs claims.
DISCUSSION
ESI alleges there are genuine issues of
material fact as to whether it was paid under the contract for (1) the total amount
of sludge hauled to the landfill and (2) for the sludge pumped into dewatering
bags but left at the jobsite, and therefore, the grant of summary judgment was
inappropriate as to the claims for quantum meruit and breach of contract. We
disagree.
In order for a motion of summary
judgment to warrant denial, a triable issue must exist. Worsley Cos., Inc.
v. Town of Mount Pleasant, 339 S.C. 51, 55, 528 S.E.2d 657, 660 (2000). A
court considering summary judgment neither makes factual determinations nor
considers the merits of competing testimony; however, summary judgment is
completely appropriate when a properly supported motion sets forth facts that
remain undisputed or are contested in a deficient manner. David v. McLeod
Regl Med. Ctr., 367 S.C. 242, 250, 626 S.E.2d 1, 5 (2006).
In
the case at bar, ESI has failed to raise a genuine issue of material fact it
was not compensated for services provided to JCC. The record is barren of
evidence to support this contention. Therefore, the trial judges grant of
summary judgment was appropriate.
ESI
alleges it was not paid for the amount of sludge it disposed of according to
the terms of the contract and for the amount of sludge it pumped into
dewatering bags and left at the jobsite. However, ESI did not properly support
these claims to the extent necessary to raise a genuine issue of material
fact. As in this case, summary judgment is completely appropriate when facts
are contested in a deficient manner. See David, 367 S.C. at 250,
626 S.E.2d at 5.
1.
Sludge Removal Fully Performed under the Terms of the Contract
ESI alleges that it was not paid for the
350 tons of sludge removed, transported, and disposed of at the dump. Based on
our review of the record, this issue is not preserved. Even if preserved, the
issue fails on the merits.
This sludge removal was specifically
covered by the terms of the contract. ESI performed under the contract by
disposing of approximately 350 tons of sludge and would have a cause of action
for breach of contract against JCC if JCC failed to pay for these services. However,
sufficient evidence is not contained in the record to support this contention.
The cause of action for breach of
contract requires the plaintiff to establish the following elements: (1) the
existence of a contract, (2) a breach of the contract, and (3) damages to the
plaintiff proximately resulting from the breach. Fuller v. Eastern Fire
& Cas. Ins. Co., 240 S.C. 75, 89, 124 S.E.2d 602, 610 (1962). A breach
occurs when a party to the contract fails to carry out a term, promise, or
condition of the contract. See Freeman Dodge, Inc. v. Fin. Servs.,
Inc., 272 S.C. 164, 249 S.E.2d 897 (1978) (finding finance companys
failure to offer car back to dealership as required by the terms of the
contract was breach).
ESI has failed to produce evidence
supporting the elements required for a breach of contract action. Looking to
the pleadings, depositions, answers to interrogatories, and admissions on
file, together with the affidavits in the record, ESI did not present
sufficient evidence of a breach by JCC to create an issue for trial. See Rule 56(c), SCRCP.
It
is undisputed JCC and ESI entered into a mutual contract. By the terms of the
contract, ESI was required to [r]emove, solidify, transport and dispose of
approximately 350 tons of waste treatment sludge. After disposal of the
sludge, JCC was required to pay ESI according to the measure of sludge hauled
to the landfill. To establish a breach, ESI was required to prove JCC did not
pay for sludge removal complying with the terms of the agreement. However, there
is no evidence in the record suggesting JCC failed to compensate ESI for the
work it performed. The only evidence offering insight into JCCs payment for ESIs
services is the deposition of Brian Larry Penfield, Jr. (Penfield), the
president and owner of ESI. In his deposition, Penfield testified:
Q: Okay. And do you know how much
money J.C. Construction paid you?
A: Without pulling it out I do not
know, sir.
Q: So you have no idea as you sit here
today whether they paid you the entire $38,000, do you?
A: Not right this moment I do not.
Q: All right. As we sit here today can
you tell me what services or materials that you provided to my client, J.C.
Construction that you were not compensated for?
A: Well, the contract for the first 350
tons and first $37,800 I would say that that there was falling in line with the
$108 a ton and then due to circumstances either caused by delays, change orders
and other nature like that, that the materials that was in the bag on the
bottom of the hill and the prevention of moving further with the job since we
were basically . . . when we put a work stoppage in to try and get things
hashed out it prevented us from making up the rest of the money, particularly
time, the cost of the bags. We had multitude of down days to where we drove up
there and we couldnt do anything, some of which may have been in our error but
some of which were not, so those are the things that I think that should be
calculated in regard to that.
In the appellants brief, ESIs counsel
concedes this testimony confirms ESI was paid for the first 350 tons of sludge
removal but argues that Penfields testimony was erroneous and inaccurate.
While counsel maintains that Penfield was mistaken and ESI was not paid for the
sludge removal fully performed, no additional evidence is offered anywhere in
the record to support this contention.
Given Penfields uncertain testimony and
the lack of other supporting evidence, this court does not find a genuine issue
of material fact as to whether ESI was paid under the contract. Although
Penfield appears to be unsure as to what amount he received from JCC at the
time of the deposition, the testimony establishes ESI was paid. When asked
what services ESI was not compensated for, Penfield seems to suggest ESI wants
payment for the sludge pumped into the dewatering bags and left at the jobsite
and the costs associated with delays as opposed to the money due under the
original terms of the contract. His response to the question is ambiguous at
best. This ambiguity is not sufficient to raise a genuine issue of material
fact sufficient for trial on the claim ESI was not paid for work fully
performed under the contract. Facts contested in a deficient manner cannot
overcome a properly supported motion for summary judgment.
After JCC established a lack of
evidentiary support for the case, the burden shifted to ESI to prove the
existence of a genuine issue of material fact. See Regions Bank v.
Schmauch, 354 S.C. 648, 660, 582 S.E.2d 432, 438 (Ct. App. 2003). A party
opposing a motion for summary judgment must allege facts clearly showing a
material issue for trial and cannot rely on a mere scintilla of evidence to
overcome the motion. See Thomas v. Waters, 315 S.C. 524, 526,
334 S.E.2d 659, 661 (2001). ESI failed to meet this burden. Looking to Rule
56(c), SCRCP, we are limited to examining the pleadings, depositions, answers
to interrogatories, admissions on file, and affidavits to find a genuine issue
of material fact warranting a denial of a grant of summary judgment. Based on
the record in this case, no such factual dispute exists to support the claim
ESI was not compensated for the sludge removal fully performed under the
contract. Therefore, the grant of summary judgment was proper in regards to
this claim.
2.
Excess Sludge Pumped into Dewatering Bags without Disposal
Additionally, ESI is seeking recovery
for sludge removed in excess of the terms of the contract and left in
dewatering bags at the jobsite without proper disposal. ESI alleges it is
entitled to recover for this work under a theory of quantum meruit, or in the
alternative, under a claim for breach of contract.
Quantum meruit is an equitable remedy. Columbia Wholesale v. Scudder May N.V., 312 S.C. 259, 261, 440 S.E.2d 129,
130 (1994); Landbank Fund VII, LLC v. Dickerson, 369 S.C. 621, 630, 632
S.E.2d 882, 887 (Ct. App. 2006). In a law action, the measure of damages is
determined by the parties agreement, while in equity, the measure of the
recovery is the extent of the duty or obligation imposed by law, and is
expressed by the amount which the court considers the defendant has been
unjustly enriched at the expense of the plaintiff. QHG of Lake City,
Inc. v. McCutcheon, 360 S.C. 196, 203, 600 S.E.2d 165, 108 (Ct. App. 2004)
(quoting Myrtle Beach Hosp. v. City of Myrtle Beach, 341 S.C. 1, 8, 532
S.E.2d 868, 872 (2000) (quoting United States Rubber Prods., Inc. v. Town of
Batesburg, 183 S.C. 49, 55, 190 S.E. 120, 126 (1937))).
To prevail on a quantum meruit claim,
the following elements must be established: (1) the plaintiff conferred a
benefit to the defendant; (2) the defendant realized the benefit; and (3) the
defendant retained the benefit under circumstances making it inequitable for
the defendant to retain the benefit without paying its value. Myrtle Beach Hosp., 341 S.C. at 8-9, 532 S.E.2d at 872; Landbank, 369 S.C. at
630, 632 S.E.2d at 888; QHG of Lake City, 360 S.C. at 203-204, 600
S.E.2d at 108; Swanson v. Stratos, 350 S.C. 116, 121, 564 S.E.2d 117,
119 (Ct. App. 2002). However, [i]f the tasks the plaintiff is seeking
compensation for under a quantum meruit theory are encompassed within the terms
of an express contract which has not been abandoned or rescinded, the plaintiff
may not recover under quantum meruit. Swanson, 350 S.C. at 122, 564
S.E.2d at 120 (citing 66 Am.Jur.2d Restitution and Implied Contracts §
81 (2001) ([I]t is a defense to an action in quantum meruit that there is an
express contract covering the issue of compensation for services or materials
furnished.)); see also Texcon, Inc. v. Anderson Aviation, Inc.,
284 S.C. 307, 326 S.E.2d 168 (Ct. App. 1985) (finding master erred in allowing
recovery in quantum meruit where express contract existed).
In Ro-Lo Enterprises v. Hicks Enterprises, Inc., 294 S.C. 111, 113-114, 362
S.E.2d 888, 889 (Ct. App. 1987), this Court addressed what constitutes
abandonment of a contract:
Abandonment of contract by one
party is the giving up of the right to a benefit due from the other party. Pitcher
v. Lauritzen, 18 Utah 2d 368, 423 P.2d 491 (1967). A contract will be
treated as abandoned when the acts of one party inconsistent with its existence
are acquiesced in by the other party. Sauder v. Dittmar, 118 F.2d 524 (10th
Cir. 1941); 17 Am.Jur.2d Contracts Section 484 (1964). To constitute
abandonment of contract by conduct, the actions relied upon must be positive,
unequivocal, and inconsistent with the existence of a contract. Mood v.
Methodist Episcopal Church South, 289 S.W. 461 (Tex. Civ. App. 1926).
The
abandonment of a contract is a matter of intention to be ascertained from the
facts and circumstances surrounding the transaction from which the abandonment
is claimed to have resulted. Quality Concrete Products, Inc. v. Thomason,
253 S.C. 579, 589, 172 S.E.2d 297, 302 (1970). An abandonment of a contract
need not be express but may be inferred from the conduct of the parties and the
attendant circumstances. Id. [A]n abandonment of the contract involves
a breach of the implied obligation of good faith and fair dealing. U.S. ex. rel. William Elec. Co., Inc. v. Metric Constructors, Inc., 325 S.C.
129, 135, 480 S.E.2d 447, 450 (1997).
ESI
cannot recover under a theory of quantum meruit if the work they are seeking
compensation for is covered under the terms of an express contract. However, if
the express contract has been abandoned, recovery under quantum meruit may be
possible. In this case, an express contract covered the task for which ESI is
seeking recovery, but ESI abandoned the contract when it unilaterally decided
to quit the project. This abandonment cannot allow ESI to recover under
quantum meruit. ESI left the jobsite, demanded an increase in price, and
refused to perform any further work until JCC consented. ESI sent a new
service agreement to JCC stating, along with a price increase to $220.00 per
ton removed:
This cost will include all of the
changes and the clarifications that Woolpert Engineering has imposed for this
project. No trucks can be loaded until there is an agreement signed and
returned. ESI will still need to obtain a new purchase order for the
remaining sludge to reflect the cost changes as well as change orders signed
and placed by Woolpert to insure it is done by the new specifications.
(emphasis added).
In
response to this demand, JCC hired another company to complete the remaining
tasks. ESIs abandonment was a breach of contract and does not open the door
to a claim under quantum meruit. Therefore, ESI was barred from recovery.
Furthermore,
ESI is not entitled to recover for breach of contract until it fully performs
under the terms of the contract. By failing to properly transport and dispose
of the sludge pumped into the dewatering bags, ESI did not complete performance.
Due to this failure, ESI was not yet entitled to compensation under the terms
of the contract and cannot recover for breach of contract.
3.
Ambiguity in the Contract
Additionally,
ESI argues the contract was ambiguous by stating approximately 350 tons of
waste treatment sludge. Because approximately could be subject to conflicting
interpretation, the question of whether the additional sludge removed is
covered by the terms of an express contract is disputed. If the additional
sludge removal was not covered by an express contract, recovery under quantum
meruit may be allowed.
In HK New Plan Exch. Prop. Owner I, LLC v. Coker, 375 S.C. 18, 23, 649
S.E.2d 181, 184 (Ct. App. 2007), we discussed the effect of an ambiguous contract
on a motion for summary judgment:
Generally, the
construction of a contract is a question of law for the court. Soil
Remediation Co. v. Nu-Way Envtl., Inc., 325 S.C. 231, 234, 482 S.E.2d 554,
555 (1997). Where a motion for summary judgment presents a question as to the
construction of a written contract, if the language employed by the agreement
is plain and unambiguous, the question is one of law. First-Citizens Bank
Trust Co. v. Conway Nat'l Bank, 282 S.C. 303, 305, 317 S.E.2d 776,
777 (Ct. App. 1984). In such a case, summary judgment is proper and a trial
unnecessary where the intention of the parties as to the legal effect of the
contract may be gathered from the four corners of the instrument itself. Id.
However, summary
judgment is improper where the motion presents a question as to the
construction of a written contract, and the contract is ambiguous because the
intent of the parties can not be gathered from the four corners of the
instrument. Bishop v. Benson, 297 S.C. 14, 17, 374 S.E.2d 517,
518-19 (Ct. App. 1988). Where a contract is unclear, or is ambiguous and
capable of more than one construction, the parties' intentions are matters of
fact to be submitted to a jury. Wheeler v. Globe Rutgers Fire Ins. Co. of
City of N.Y., 125 S.C. 320, 325, 118 S.E. 609, 610 (1923).
Typically, when a contract is ambiguous
and a question of fact is raised to its interpretation, summary judgment would
not be appropriate. However, in this case, regardless of the interpretation of
the contract, ESI would not be entitled to recover.
If an express contract covered the excess
sludge removed, then ESI would be limited to a recovery in breach of contract.
However, due to the fact ESI breached the contract and did not fully perform,
it would be unable to recover.
If the additional sludge removal was not
covered by the contract because of the ambiguity of the term approximately,
ESI would still be unable to recover under a theory of quantum meruit. Before
recovery is allowed, quantum meruit requires the defendant to retain a benefit
under circumstances that make it inequitable for the defendant to do so without
paying value. In this case, it would not be inequitable for JCC to retain the
benefit of ESIs work because there was no inequitable conduct on the part of
JCC leading to the removal. ESI submitted a change order requesting an
increase in tonnage removed to 5000 tons. However, ESI failed to present any
evidence JCC agreed to this increase. Because it proceeded without a valid
agreement, ESI bore the risk of not receiving a benefit for its services.
Therefore, recovery for the excess sludge removal is inappropriate under a
theory of quantum meruit.
In his deposition, Penfield testified to
his understanding of the parties agreement regarding the disposal of
additional sludge:
Q: Okay. You would agree with me that
this contract doesnt give you any more rights than to basically haul away 350
tons of sludge?
. . .
A: I think there was also a change
order sent in part to remove it . . . turn it to, I think 1,800 tons or so.
Q: Was that change order ever signed by
my client?
A: That I dont know, sir.
Q: Well, Ill show it to you. Im
going to hand you what has been marked as Exhibit Number Four to your
deposition.
Q: What is that, for the record,
please?
A: That is a change in calculation
after we tried to meet every one of the change orders that had been placed upon
us.
Q: And in that you raised the price,
you basically gave a quote that sais (sic), Hey, well do this for 200 bucks a
ton, is that correct?
A: Thats correct.
Q: In the second paragraph it says, No
trucks can be loaded until there is an agreement signed and returned.
Q: Okay. So what youre doing is
youre saying my company will do this if we enter into an agreement for this
price to be $220, is that correct?
A: Yes, sir.
Q: Well, they didnt agree to this did
they, to Exhibit Number Four? They didnt agree to pay two and a half times .
. .
A: No, sir, they never signed it and
sent it back.
Q: Right so you didnt have an
agreement to do any more work out there, did you?
A: In the terms that youre putting it,
no sir.
Q: Well, you put it right here that you
werent going to load any trucks until they signed the agreement, didnt you?
The
deposition of Laverne Anderson (Anderson) establishes JCCs understanding of
the agreement regarding any additional sludge removal beyond the terms of the
contract. Anderson explained:
[W]e had ESI under contract, which is
drawn up to meet our needs, and we had won the contract to remove 350 tons and
thats it. And then if we chose to do so, to continue working with him, we
could issue him a change order at the same unit rate he gave us to complete the
job. But he left the job because he hadnt paid his suppliers, he pulled off,
he couldnt remove the sludge.
Nothing
in the record establishes any agreement between JCC and ESI for the removal of
sludge beyond the terms of the original contract. If the original contract had
expired, ESI pumped the additional sludge without an agreement with JCC. ESI
cannot perform work without any agreement in place and then argue it is
entitled to compensation. Without evidence indicating it would be inequitable
for JCC to retain this benefit, ESI is not entitled to recover under quantum
meruit.
Furthermore, we note ESI received a
credit from its subcontractor, Wolfe Creek, for time, materials, and labor
exhausted in filling the remaining bag and for three loads of ESIs sawdust. This
credit compensated ESI for expenses it incurred in pumping the excess sludge
into the dewatering bags before ESI abandoned the jobsite. Even though ESI did
not receive as much as it desired for the excess removal, the credit ensured
that ESI was repaid for the incurred costs. Therefore, equity does not require
JCC to further compensate ESI for this work.
CONCLUSION
ESI has not presented a theory of
recovery for which it is entitled to prevail based on the evidence contained in
the record. Regardless of whether the contract is ambiguous, the grant of
summary judgment is appropriate. Accordingly, the grant of summary judgment is
AFFIRMED.
ANDERSON, HUFF, and KITTREDGE, JJ.,
concur.