Quality Concrete Products, Inc. v. Thomason

172 S.E.2d 297, 253 S.C. 579, 1970 S.C. LEXIS 291
CourtSupreme Court of South Carolina
DecidedFebruary 6, 1970
Docket19015
StatusPublished
Cited by11 cases

This text of 172 S.E.2d 297 (Quality Concrete Products, Inc. v. Thomason) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quality Concrete Products, Inc. v. Thomason, 172 S.E.2d 297, 253 S.C. 579, 1970 S.C. LEXIS 291 (S.C. 1970).

Opinion

Moss, Chief Justice.

It appears from the record that C. Y. Thomason, a corporation, the appellant herein, contracted with Self Memorial Hospital for the construction of a nursing personnel residence, and Quality Concrete Products, Inc., the respondent herein, was a subcontractor and agreed to manufacture and install precast-prestressed concrete materials in said nursing personnel residence during the course of construction. When the nursing personnel residence was completed, Self Memorial Hospital withheld payments due the appellant, claiming deductions for defective work. Thomason refused to pay Quality for the concrete materials furnished and installed by it, asserting that the materials furnished were inferior and were not properly installed.

The present action is one on contract brought for the purpose of determining what amounts, if any, were due the respondent by the appellant by virtue of two contracts, whereby Quality was to provide and install precast-prestressed concrete materials for the construction of the Self Memorial Hospital nursing personnel residence. The first was a written contract by which Quality agreed to furnish all labor, materials and equipment necessary to complete all precast-prestressed concrete work on the personnel residence, for which work the appellant agreed to pay the sum of $4,560.00. The respondent then alleges that it fully performed the said contract, according to its terms, and that the appellant failed to pay the amount due it under the said written contract.

Quality also alleges that it entered into an oral contract with Thomason whereby it agreed to furnish all labor, materials and equipment necessary to complete all precast *583 concrete fascia work on the personnel residence for the sum of $7,474.00. The respondent then alleges that it fully performed the said contract, according to its terms, and that the appellant failed to pay the amount due it under the said oral contract.

Thomason, by answer, denied that it was indebted to Quality because the materials provided by Quality were inferior and not acceptable to Self Memorial Hospital and were rejected by it; that Quality abandoned the project and authorized Thomason to correct and complete the work at its own expense and deduct this amount from the contract price, and, that said costs exceeded the amount alleged to be due Quality. These defenses, inter alia, were pled as to each of the two causes of action. In addition, Thomason claimed a setoff in a sum equal to any amounts allegedly due Quality and counterclaimed alleging that it expended $7,-693.10 in the correction of Quality’s materials and workmanship, thus causing Quality to be indebted to Thomason in the sum of $1,126.60 in excess of the claim of Quality on the oral contract and demanded judgment for the total cost of the corrective work.

This case came on for trial before The Honorable Robert W. Hayes, Presiding Judge, and a jury, at the 1968 September Term of the Court of Common Pleas for Greenwood County and resulted in a verdict in favor of Quality in the sum of $10,199.70. This sum represented the total of the two contract prices, as Quality admitted to certain back charges during the course of the trial. Before the case went to the jury, the trial judge held that the respondent was entitled to recover as a minimum the sum of $3,530.90, and a maximum amount, under the two contracts, of $10,199.70. Thomason agreed to the maximum figure from which its proven deductions, if any, were to be made. Thomason contended that Quality did provide certain fascia materials and services in the installation thereof but asserted that it expended $6,668.80 correcting their defective materials and *584 workmanship and was entitled to a setoff against the maximum amount recoverable under the two contracts.

It is the position of Thomason that the court erred in failing to grant its motions for a directed verdict and for judgment non obstcmte veredicto, in the sum of $6,668.80, on the ground that the only reasonable inference to be drawn from all of the evidence was that said amount was a proper offset against the alleged contract price for materials and services rendered to it by Quality.

It appears from the testimony in behalf of Quality that when Thomason obtained the contract to build the personnel residence at Self Memorial Hospital, that it submitted bids to Thomason for the precast-prestressed concrete materials and also for the fascia. The bid for the fascia was in the amount of $7,474.00. A written contract was made, as is heretofore stated, concerning the precast-prestressed concrete materials but no contract was entered into by the parties for the fascia. Almost a year later Thomason did send a contract for rubbed finished fascia to Quality but such was not signed by it because Quality could not perform it within the time provided thereby. Thereafter, the project manager who was in charge of the construction of the personnel residence for Thomason, went to the plant of Quality in Greenville and stated because he had to meet a certain schedule he thought he could live with fascia with a form finish, which took much less time to produce than the rubbed finished fascia. A witness for Quality testified that the proposed contract price for rubbed finished fascia was $7,474.00 but after the project manager for Thomason agreed to a form finish fascia, the alleged contract price was reduced by $907.50.

As to the type of fascia to be furnished by Quality to Thomason under the contract, it was testified by a representative of the respondent, as follows:

“We agree to furnish them a panel with a form finish, just as it came out of the form, that they would put whatever finish the architect ultimately decided to accept, and that any work between the form finish and what it takes to receive *585 the finish the architect agreed to take they would do themselves.” >

This witness testified that a panel with a form finish is just as it comes out of the mold or form, with no touch up work done to its surface whatsoever and whatever appearance is built into it from the form remains there. Such panel would show the wood marks and steel joint marks on it and there would be considerable imperfection in the finish, including any ripples that were in the form in which the said panel had been molded.

As to the performance of the contract by Quality, we quote from the testimony of a witness for Quality as follows :

“Q. Did you supply the type of fascia panels that was ordered from you by C. Y. Thomason Company?
“A. Yes, sir.
“Q. Did you supply the fascia panels with the finish on them ordered by C. Y. Thomason Construction Company?
“A. We did supply a a form finish, as agreed, yes, sir.
“Q. That was the type ordered from C. Y. Thomason Company?
“A. Yes, sir.
“Q. All right, sir. Have you been paid by C. Y. Thomason Construction Company for these fascia panels ?
“A. Not one dime.”
;Ji ;}c >]c

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parker v. Shecut
531 S.E.2d 546 (Court of Appeals of South Carolina, 2000)
U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc.
480 S.E.2d 447 (Supreme Court of South Carolina, 1997)
Ro-Lo Enterprises v. Hicks Enterprises, Inc.
362 S.E.2d 888 (Court of Appeals of South Carolina, 1987)
Johnston v. Brown
357 S.E.2d 450 (Supreme Court of South Carolina, 1987)
J. J. Lawter Plumbing v. Wen Chow International Trade & Investment, Inc.
331 S.E.2d 789 (Court of Appeals of South Carolina, 1985)
Madden v. Cox
328 S.E.2d 108 (Court of Appeals of South Carolina, 1985)
Hall v. Palmetto Enterprises II, Inc.
317 S.E.2d 140 (Court of Appeals of South Carolina, 1984)
Hall v. PALMETTO ENTR. II, INC., OF CLINTON
317 S.E.2d 140 (Court of Appeals of South Carolina, 1984)
Baker v. Weaver
309 S.E.2d 770 (Court of Appeals of South Carolina, 1983)
Speizman Knitting MacHines Corp. v. Fretwell
213 S.E.2d 586 (Supreme Court of South Carolina, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
172 S.E.2d 297, 253 S.C. 579, 1970 S.C. LEXIS 291, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quality-concrete-products-inc-v-thomason-sc-1970.