Malcolm International LLC v. Fisher Sand & Gravel-New Mexico, Inc.

CourtDistrict Court, D. New Mexico
DecidedJune 26, 2025
Docket1:23-cv-00188
StatusUnknown

This text of Malcolm International LLC v. Fisher Sand & Gravel-New Mexico, Inc. (Malcolm International LLC v. Fisher Sand & Gravel-New Mexico, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Malcolm International LLC v. Fisher Sand & Gravel-New Mexico, Inc., (D.N.M. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW MEXICO

MALCOLM INTERNATIONAL, LLC, Plaintiff, v. No. 1:23-CV-00188-SMD-JMR FISHER SAND & GRAVEL-NEW MEXICO, INC., Defendant, FISHER SAND & GRAVEL-NEW MEXICO, INC. Counter-Plaintiff, v. MALCOLM INTERNATIONAL, LLC, Counter-Defendant.

OMNIBUS OPINION AND ORDER GRANTING DEFENDANT’S MOTION FOR SUMMARY JUDGMENT AND DENYING DEFENDANT’S MOTION FOR DECLARATORY JUDGMENT

THIS MATTER is before the Court on Defendant Fisher Sand & Gravel’s (“Fisher’s”) motion for summary judgment. Doc. 49 (“Def.’s SJ Mot.”). Plaintiff Malcolm International, LLC (“Malcolm”) filed its response, and Defendant filed its reply. Doc. 51 (“Pl.’s SJ Resp.”); Doc. 52 (“Def.’s Reply”). FACTUAL BACKGROUND This case arises from a contractual dispute between Fisher and Malcolm. Doc. 1 (“Compl.”). In March of 2018, the New Mexico Department of Transportation (“NMDOT”) selected Fisher as the primary contractor for construction of a bridge in Quay County, New Mexico. Compl. ¶¶ 9–10. Fisher then subcontracted Malcolm to complete the cast-in-place piers and other bridge components (“the Project”). Id. ¶ 11. Prior to the Project’s start, Fisher and NMDOT concluded that raising the piers an extra five feet out of the water would make the bridge more environmentally sound. Id. ¶ 12. Fisher informed Malcolm of this design change and Malcolm subsequently submitted an estimate of the associated costs of redesigning the piers. Id. ¶¶ 16–17. In October of 2018, Fisher and NMDOT executed Change Order Six, approving the

new plan and granting a forty-five-day extension to Fisher. Id. ¶ 19. Malcolm was not a party to the Change Order. Id. ¶ 14. Fisher agreed to absorb the cost of the revised design, but did not guarantee that Malcolm would be compensated for costs associated with the Project’s new schedule. Id. ¶¶ 13, 18. The pier redesign did not alter the scope of the work that Malcolm was hired to complete (one bridge, two abutments, two piers, and two disc bearings). Id. ¶ 15. It did, however, delay Malcolm’s start date and increase the quantity of rebar and concrete needed to complete the piers. Id. Fisher paid Malcolm for the additional materials, but not for the extra labor or other costs related to the delay. Id. ¶ 30. Malcolm and Fisher pursued administrative remedies to recover

these costs from NMDOT. Id. ¶ 23. NMDOT denied Malcolm’s claim. Id. Malcolm, Fisher, and NMDOT then participated in an unsuccessful Public Works mediation. Id. ¶ 24. Following these efforts, Fisher did not file a summons and complaint against NMDOT on Malcolm’s behalf. Id. ¶ 25. Malcolm asked Fisher to do so. Id. ¶ 26. Fisher replied that it was only willing to file on Malcolm’s behalf if Malcolm agreed to release Fisher of any liability for damages. Id. Malcolm refused and Fisher never filed the complaint. Id. PROCEDURAL BACKGROUND Malcolm sued Fisher on March 6, 2023, in the United States District Court for the District of New Mexico, invoking the court’s diversity jurisdiction. Compl. at 1. See 28 U.S.C. § 1332. The complaint alleges three counts: breach of contract, unjust enrichment, and breach of the duty of good faith and fair dealing. Id. at 4–6. In April of 2023, Fisher moved to dismiss all three claims. Doc. 5 (“Def.’s Mot. to Dismiss.”). The court dismissed Malcolm’s claims for unjust enrichment and breach of the duty of good faith and fair dealing. Doc. 13 (“Order on Def.’s Mot. to Dismiss”) at 7. The remaining claim for breach of contract was permitted to proceed on either

of two theories: that Fisher breached the contract by failing to preserve Malcolm’s claim against NMDOT for compensation or that Fisher breached by failing to compensate Malcolm for increased costs that Malcolm suffered because of delays in the project. Id. at 7–8. The Parties proceeded with discovery. Doc. 40. Fisher now seeks summary judgment on Malcolm’s breach of contract claim and brings a crossclaim for declaratory judgment, requesting that the Court award Fisher costs and attorneys’ fees associated with the litigation. Def.’s SJ Mot. at 13. LEGAL STANDARD Summary judgment is warranted “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P.

56(a); see Butler v. Daimler Trucks N. Am., LLC, 74 F.4th 1131, 1140 (10th Cir. 2023). The moving party bears the burden of “informing the district court of the basis for its motion, and identifying those portions of [the record] which it believes demonstrate the absence of a material fact.” Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). Once this requirement is met, the non-movant can defeat summary judgment by showing that there is a genuine dispute of material facts. Id. The non-movant’s response must “set forth specific facts by reference to affidavits, deposition transcripts, or other exhibits to support the claim.” Serna v. Colo. Dep’t of Corr., 455 F.3d 1146, 1151 (10th Cir. 2006). The court then reviews the proffered evidence and, drawing all reasonable inferences in favor of the nonmoving party, determines whether the facts “establish, at a minimum, an inference of the presence of each element essential to the case.” Bausman v. Interstate Brands Corp., 252 F.3d 1111, 1115 (10th Cir. 2001). DISCUSSION A. Undisputed Material Facts The Court begins with the Parties’ statements of undisputed material facts (“UMFs”) and

construes any disputed fact in the light most favorable to Malcolm as the non-moving party. Scott v. Harris, 550 U.S. 372, 378 (2007). Local Rule 56.1 instructs that each disputed fact “must be numbered, must refer with particularity to those portions of the record upon which the non-movant relies, and must state the number of the movant’s fact that is disputed.” D.N.M.LR-Civ. 56.1(b). If the non-movant fails to controvert a material fact with a citation to the record, it is deemed undisputed. Id.; see, e.g., Martin v. City of Albuquerque, 147 F. Supp. 3d 1298, 1336 n.3 (D.N.M. 2015). Malcolm’s statement of materials facts does not comply with the Local Rules; its response to Fisher’s UMF is unnumbered, at times lacking citation to the record, and its additional material

facts, which should be lettered, are instead numbered. Pl.’s SJ Resp. at 3–6 (“Pl.’s UMF”). However, because these errors are largely issues of formatting, the Court will consider the facts properly disputed where Malcolm has included citations to the record. Cf. Skowron v. C.H. Robinson Co., 651 F. Supp. 3d 401, 404 (D. Mass. 2023) (finding facts properly disputed, even where they did not comply with local rules, because the plaintiff include citations to the record). The following recitation of facts thus draws from Fisher’s initial UMF, Malcolm’s response, and Fisher’s reply. 1 Def.’s SJ Mot. at 5–9 (“Def.’s UMF”); Pl.’s UMF at 3–6; Def.’s Reply at 2–4 (“Def.’s Resp. to Pl.’s UMF”). On January 11, 2018, Fisher entered into a subcontract with Malcolm for the Project. Def.’s UMF ¶ 1; Pl.’s UMF at 3; Def.’s SJ Mot., Ex. A (“the Contract”) at 1. Two months later, Fisher submitted a request to NMDOT to redesign the pier footings to make them more structurally sound.

Def.’s UMF ¶ 2; Pl.’s UMF at 2. Fisher informed Malcolm of the need to raise the piers and Malcolm understood that this alteration would delay its start date. 2 Def.’s UMF ¶ 3; Pl.’s UMF ¶ 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Bausman v. Interstate Brands Corp.
252 F.3d 1111 (Tenth Circuit, 2001)
Glasscock v. McCotter
56 F. App'x 452 (Tenth Circuit, 2003)
Chavez v. State of New Mexico
397 F.3d 826 (Tenth Circuit, 2005)
Serna v. Colorado Department of Corrections
455 F.3d 1146 (Tenth Circuit, 2006)
Wade v. Emcasco Insurance
483 F.3d 657 (Tenth Circuit, 2007)
Parker v. Town of Chelsea
275 F. App'x 769 (Tenth Circuit, 2008)
Coleman v. Blue Cross Blue Shield of Kansas, Inc.
287 F. App'x 631 (Tenth Circuit, 2008)
SUREFOOT LC v. Sure Foot Corp.
531 F.3d 1236 (Tenth Circuit, 2008)
Marlin Oil Corporation v. Lurie
417 F. App'x 740 (Tenth Circuit, 2011)
Conaway v. Smith
853 F.2d 789 (Tenth Circuit, 1988)
Taylor v. Allegretto
816 P.2d 479 (New Mexico Supreme Court, 1991)
Chavez v. Manville Products Corp.
777 P.2d 371 (New Mexico Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Malcolm International LLC v. Fisher Sand & Gravel-New Mexico, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/malcolm-international-llc-v-fisher-sand-gravel-new-mexico-inc-nmd-2025.