Taylor v. Allegretto

816 P.2d 479, 112 N.M. 410
CourtNew Mexico Supreme Court
DecidedJuly 29, 1991
Docket19112
StatusPublished
Cited by4 cases

This text of 816 P.2d 479 (Taylor v. Allegretto) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor v. Allegretto, 816 P.2d 479, 112 N.M. 410 (N.M. 1991).

Opinion

OPINION

MONTGOMERY, Justice.

Plaintiffs seek review of the trial court’s interpretation of a written contract between the parties and its rejection of their tender of parol evidence regarding alleged agreements collateral to the contract. Finding error in the court’s rulings, we reverse.

I.

Defendant Allegretto entered into a contract with plaintiff Taylor, a licensed architect and contractor and owner of plaintiff Taylor Resources Corp., a construction company, to prepare plans and specifications for a three-unit medical office building in Las Cruces, New Mexico. (Taylor and his corporation are referred to collectively in this opinion as “Taylor.”) The parties met frequently during preparation of the plans and discussed the possibility of building a second three-unit complex on adjacent property also owned by Allegretto. It apparently was agreed during this time that in the initial phase of construction the shell of the first three-unit building, referred to as the 1240 Telshor property, would be constructed and that the interior of one of the units, Unit 2, would be completely finished. Allegretto would use Unit 2 as the office for his dental practice and as a model unit to show prospective buyers of the other units.

Almost one year after the parties entered into the contract for preparation of the plans for the first building, the parties agreed to execute a second contract, using a standard American Institute of Architects Abbreviated Form Agreement (“AIA agreement”), for construction of “Unit # 2 — As per plans and specifications.” The contract sum was listed as $126,000. The form was prepared and signed by Taylor and sent to Allegretto.

Taylor began construction on the 1240 Telshor building in September 1985. By January 1986, he had built the shell for the entire building and had completed the interior of Unit 2. In addition, he had performed work which was not included in the plans and specifications. These items included, among other things, an 80-square-foot loft, plumbing and electrical additions, built-in furniture and other fixtures, work on common areas, and site work on the adjacent lot.

For tax reasons, Allegretto moved into Unit 2 at the end of 1985, before construction was completed. Following completion of the work in January 1986, Allegretto sold Units 1 and 3 to third parties as unfinished units and sold the adjacent lot as vacant land.

Taylor maintains that he and Allegretto had entered into an oral joint-venture agreement, in which Allegretto guaranteed that Taylor would be the exclusive contractor for completion of Units 1 and 3 and construction of the second office complex. Asserting that Allegretto’s sale of Units 1 and 3 as unfinished units and his sale of the adjacent lot as vacant land violated this agreement, Taylor filed suit in district court in November 1986, alleging breach of the agreement and stating claims based on quantum meruit, constructive fraud, and misrepresentation. Taylor also alleged that other agreements relating to the work to be performed and the compensation therefor governed the parties’ relationship, rather than the AIA agreement, which Taylor argued was executed solely to obtain financing. Additionally, Taylor sought recovery for extra work which he alleged the parties had agreed to during construction but for which he had not been paid.

The trial court ruled against Taylor on all counts. The court found that the AIA agreement and the contract for preparation of plans were the only agreements between the parties and refused to consider evi- . dence tendered by Taylor about the alleged oral agreements. The court also found that Allegretto had paid for the added cost of changes or additions which he had asked Taylor to perform.

Taylor abandoned his claims based on fraud and misrepresentation. On appeal, he maintains initially that the trial court erred in giving effect to the AIA agreement, asserting that the contract was prepared solely for the purpose of enabling Allegretto to obtain a loan, and that there was thus no mutual assent that the contract would govern the parties’ relations. Rather, Taylor contends, the parties’ relationship was governed by a series of oral agreements. He claims that he agreed to draft the plans and specifications at a fraction of his usual cost based upon Allegretto’s assurances that, if he prepared satisfactory plans and the two worked well together, he would be the exclusive contractor for both building projects. Taylor maintains that Allegretto informed him that he had available $130,000 to begin the initial phase of construction and that they both agreed that Allegretto would pay Taylor this sum as a “start-up” figure, not tied to any specific amount of work. Taylor agreed to this, he says, based on Allegretto’s assurances that his profit would come at the “back end of the deal” as the exclusive contractor for the building and from a portion of the profit from the sale of all units. Allegretto denies all of these alleged agreements.

In the alternative, Taylor argues that if the contract is found operative, by its own terms it covered only the construction of “Unit #2” — the completed dental office unit — and not construction of the building shell. It also omitted any agreements about profits for work on the project as a whole at the “back end of the deal.” Taylor also asserts that during construction the parties entered into numerous agreements regarding extra work not contemplated in the contract plans and that he has not been compensated for this work.

Allegretto disputes each of Taylor’s contentions, maintaining that the AIA agreement was the sole operative contract between the parties and that it covered all construction performed on the project, including the shell of the 1240 Telshor building and completion of the interior of Unit 2. There were no additional oral agreements between the parties, according to Allegretto, except for certain extra work for which he insists Taylor has been paid.

At trial, the court permitted Taylor to introduce testimony regarding the alleged oral agreements as outlined above, subject to the condition that at the end of the trial the court would accept or reject the testimony depending upon whether the evidence demonstrated that the oral agreements were collateral to, or instead merged into, the AIA agreement. Allegretto entered a continuing objection to the introduction of the testimony. The court concluded in separate conclusions of law that there was “no evidence of a previous stipulation or agreement between the parties that is collateral to the written contracts of the parties” and that Taylor’s evidence of an alleged parol agreement was not “clear, positive and above suspicion.” The court ruled that the parol evidence was therefore inadmissible. The court thus implicitly found the parties intended the AIA agreement to be operative and specifically found it covered construction of the shell of the entire building as well as the interior of Unit 2. The court also found that Allegretto had paid for the extra cost of changes or additions which he had asked Taylor to perform.

II.

As noted, one of Taylor’s principal contentions at trial was that the AIA agreement was executed solely to facilitate obtaining a loan and was not intended to govern the parties’ legal relationship with respect to the building project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trek Leasing, Inc. v. United States
62 Fed. Cl. 673 (Federal Claims, 2004)
Catholic University of America v. Bragunier Masonry Contractors, Inc.
775 A.2d 458 (Court of Special Appeals of Maryland, 2001)
Taylor v. Allegretto
879 P.2d 86 (New Mexico Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
816 P.2d 479, 112 N.M. 410, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-v-allegretto-nm-1991.