Edward E. Gillen Company, a Wisconsin Corporation v. City of Lake Forest

3 F.3d 192, 1993 U.S. App. LEXIS 20980, 1993 WL 311938
CourtCourt of Appeals for the Seventh Circuit
DecidedAugust 17, 1993
Docket92-2206
StatusPublished
Cited by42 cases

This text of 3 F.3d 192 (Edward E. Gillen Company, a Wisconsin Corporation v. City of Lake Forest) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward E. Gillen Company, a Wisconsin Corporation v. City of Lake Forest, 3 F.3d 192, 1993 U.S. App. LEXIS 20980, 1993 WL 311938 (7th Cir. 1993).

Opinion

ILANA DIAMOND ROVNER, Circuit Judge.

Edward E. Gillen Company (“Gillen”) brought this diversity suit against the City of Lake Forest, Illinois (“Lake Forest”) after Lake Forest refused to pay for unanticipated expenses Gillen had incurred in constructing off-shore breakwaters for a municipal marina. Claiming damages in excess of $850,000, Gillen sought recovery under theories of express and implied warranty, mistake, equita *193 ble reformation, negligent misrepresentation, quantum meruit, contract, and quasi-contract. The district court dismissed several'of these claims, including the claim for equitable reformation of Gillen’s contract with Lake Forest. The court later granted Lake Forest’s motion for partial summary judgment as to damages, holding that most of the monetary relief Gillen sought was precluded by the contract’s “no damages for delay” clause. Gillen challenges both of these rulings on appeal. We affirm.

I. FACTS

In 1986, Gillen was awarded a contract to construct off-shore breakwaters in Lake Michigan for the Lake Forest marina. A portion of the project involved the construction of “Breakwater II,” which was designed to serve as both a breakwater and a walkway for strolling and fishing. The dual purpose of this breakwater required that it be built of large stones that fit closely together. Accordingly, the manual setting forth Lake Forest’s specifications for the project (and that served as the basis for Gillen’s bid) dictated the use of cubic “AIII” stone with a uniform dimension of approximately 4.5 feet. The project manual also required that this stone be procured solely from Valders Stone and Marble, Inc. (“Valders”).

After Lake Forest awarded the construction contract to Gillen, it contracted with Valders to supply the AIII stone. An addendum to Lake Forest’s agreement with Vald-ers required that the stone conform to the requirements of the project manual. Valders supplied the first shipment of AIII stone in September 1986. Although the stone was inspected and approved by a Lake Forest agent, it did not meet the project manual’s specifications, particularly in terms of its dimensions and shape. Gillen complained to Lake Forest’s site engineer, but the engineer instructed Gillen to select the better pieces of stone and try to “jigsaw” them together. Gillen incurred additional costs in doing so.

A second shipment of stone was delivered in October 1986, and it had the same problems as the first. Lake Forest again directed Gillen to jigsaw the stone into place. However, when Gillen was approximately halfway through installing this shipment, Lake Forest’s engineer agreed that the stone was inadequate and halted construction. Shortly thereafter, Lake Forest issued Change Order No. 5, which altered the specifications for the breakwater, shortening the portion to be constructed of AIII stone and dictating a different type of construction for the remainder. The change order also extended the completion date for Breakwater II from January 1, 1987 to May 22, 1987. Gillen proceeded in accordance with the new specifications until mid-December 1986, when construction was halted for the winter.

In January 1987, Gillen submitted a claim to Lake Forest for the additional costs it had incurred as a result of the non-conforming AIII stone. Lake Forest denied the claim.

Ón March 27, 1987, Lake Forest issued Change Order No. 6, which required Gillen to reconstruct a 75-foot portion of the breakwater, replacing the AIII stone with pre-cast concrete units. Gillen refused to sign the order because it did not provide for any additional compensation. But when Lake Forest threatened to replace Gillen and sue for damages, Gillen proceeded as ordered. Gillen completed work on Breakwater II in May 1987. Gillen filed this action in January 1991. 1

The district court dismissed Gillen’s equitable reformation claim because Gillen had not alleged that its written contract with Lake Forest departed from the parties’ mutual understanding of their agreement. In the court’s view, Gillen’s allegation that it had entered into the contract expecting that Valders would supply appropriate stone supported a claim for breach of warranty or contract (which Gillen had asserted separately), but not one for equitable reformation.' *194 Edward E. Gillen Co. v. City of Lake Forest, No. 91 C 0183, 1991 WL 171945, at *5-6, 1991 U.S.Dist. Lexis 12274, at *14-15 (N.D.Ill. Sept. 3, 1991).

The court subsequently granted Lake Forest’s motion for partial summary judgment as to damages, concluding that most of the damages Gillen sought were barred by Supplemental Condition SC-12.5 of the contract, which provided:

The CONTRACTOR agrees that in the event of delay for any reason caused by any party or person, it will be fully compensated for the delay by an extension of time to complete the Contract and will not seek additional compensation.

Edward E. Gillen Co. v. City of Lake Forest, No. 91 C 0183, 1992 WL 29995, 1992 U.S.Dist. Lexis 1438 (N.D.Ill. Feb. 12, 1992). Gillen filed a motion to reconsider, arguing that a substantial portion of its damages resulted from additional costs that were unrelated to delay. The district court denied the motion, observing that Gillen had never before quarreled with the proposition that the majority of its damages were delay-related. The court further concluded that despite Gillen’s belated attempt to re-characterize its damages, most of the costs for which it sought compensation had in fact been caused by delay. Edward E. Gillen Co. v. City of Lake Forest, No. 91 C 0183, Minute Order (N.D.Ill. Apr. 22, 1992).

The district court’s ruling barred Gillen from recovering all but $82,000 of the damages it sought. 2 The parties subsequently settled that portion of the suit.

II. ANALYSIS

On appeal, Gillen contends that the district court erred in finding that the majority of its alleged damages were delay damages barred by its contract with Lake Forest. Gillen also contends that its complaint stated a viable claim for equitable reformation of the contract that should not have been dismissed.

A. The Nature of Gillen’s Damages Claims

Illinois courts have consistently honored contractual provisions that preclude the recovery of damages resulting from delay. Bates & Rogers Constr. Corp. v. Greeley & Hansen, 109 Ill.2d 225, 93 Ill.Dec. 369, 372, 486 N.E.2d 902, 905 (1985). 3 Gillen does not dispute that SC-12.5 of its contract with Lake Forest bars delay damages, nor does it challenge the validity of the clause under Illinois law. It takes issue solely with the district court’s finding that the bulk of its damages were, in fact, delay damages. We review this decision de novo, viewing the record in the light most favorable to Gillen and determining whether it reveals any material dispute of fact that precludes summary judgment. Colburn v. Trustees of Indiana Unin,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
N.D. Illinois, 2026
United States v. Samuel Knowles
Eleventh Circuit, 2026
Carter v. Kuspa
E.D. Wisconsin, 2023
Morgan v. Twitter Inc
E.D. Washington, 2023
SIMPSON v. HORNING
W.D. Pennsylvania, 2023
Woodson v. Remish
N.D. Ohio, 2022
HAWK v. FEDERAL BUREAU OF PRISONS
M.D. Pennsylvania, 2019
In Re Villanueva
633 F. App'x 1 (Second Circuit, 2015)
McGugan v. Aldana-Bernier
Second Circuit, 2014
Perma-Pipe, Inc. v. Liberty Surplus Insurance
38 F. Supp. 3d 890 (N.D. Illinois, 2014)
De v. City of Chicago
912 F. Supp. 2d 709 (N.D. Illinois, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
3 F.3d 192, 1993 U.S. App. LEXIS 20980, 1993 WL 311938, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-e-gillen-company-a-wisconsin-corporation-v-city-of-lake-forest-ca7-1993.