Plowden Construction v. Richland-Lexington Riverbanks Park District
This text of Plowden Construction v. Richland-Lexington Riverbanks Park District (Plowden Construction v. Richland-Lexington Riverbanks Park District) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.
THE STATE OF SOUTH CAROLINA
In The Court of Appeals
Plowden Construction Co., Respondent-Appellant,
v.
Richland-Lexington Riverbanks Park District and The LPA Group Incorporated, Appellants-Respondents.
Appeal From Lexington County
Alexander S. Macaulay, Circuit Court Judge
Unpublished Opinion No. 2008-UP-207
Submitted March 4, 2008 Filed March 25,
2008
AFFIRMED
Daniel T. Brailsford and Charles H. McDonald, of Columbia, for Appellants-Respondents.
Thomas Elihue Dudley, III, of Greenville, for Respondent-Appellant.
PER CURIAM: This case arises out of a construction contract between Richland-Lexington Riverbanks Park District (Riverbanks) and Plowden Construction Company, Inc. (Plowden) for Plowden to build a road for Riverbanks. During construction, Plowden encountered excess rock and brought the underlying action against Riverbanks and the project engineer, the LPA Group, Inc., (LPA). Riverbanks and LPA appeal the trial courts ruling for Plowden, and Plowden cross-appeals for prejudgment interest on its award. We affirm.[1]
1. Riverbanks hired LPA to assist with the construction of a new entrance from Highway 378 to the Riverbanks Zoo and Botanical Gardens in Columbia. LPA designed the entrance, prepared bid packages and contract documents for prospective contractors, and acted as Riverbanks representative during construction. Initially, the bid packages were unclassified with regard to the amount of rock excavation that would be encountered on the job.[2] However, the packages were changed to reflect an estimate of 1,000 cubic yards of rock to be excavated. At a pre-bid meeting, potential bidders were assured by LPA that if the encountered rock became a huge problem, they were more than willing to worth with [the bidders].
Plowden was ultimately awarded the job. Soon after construction began, Plowden encountered bedrock, which required blasting in order to be removed. Plowden proceeded with the work, but eventually the amount and size of rocks being excavated began to interfere with the project. The rocks became too large and numerous to leave at the construction site, and Plowden finally halted construction on the project. This resulted in a delay while a location to deposit the rocks was sought by LPA.
Pursuant to a provision in the contract, Plowden sought a change in the contract price to reflect the quality and quantity of rock removal associated with the project. The project manager denied the requested changes finding the contract indicated quantities were approximate, Plowden was responsible for examining the physical conditions of the property before bidding, and the work stoppage was unnecessary. Plowden brought the underlying action against Riverbanks and LPA. The trial court found Riverbanks and LPA jointly and severally liable for $225,270.17, the cost of the additional work, and $66,000 in delay costs. Riverbanks and LPA appeal the trial courts ruling, and Plowden cross-appealed for prejudgment interest.
2. LPA argues the trial court erred in finding LPA liable when LPA lacked privity in the contract between Riverbanks and Plowden and LPA followed the standard of care for design professionals. The trial court found LPA liable for breaching its duty to follow the standard of care of design professionals. In Tommy L. Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc., 320 S.C. 49, 55, 463 S.E.2d 85, 88-89 (1995), the South Carolina Supreme Court held an engineer who designed the project and supervised construction owed a duty to the contractor not to design or to supervise the project negligently because design professionals owe a professional duty, which is separate from contractual duties. Therefore, LPAs liability is grounded in negligence, not contract principles. Accordingly, LPAs privity to Riverbanks and Plowdens contract is irrelevant.
Next, we turn to whether evidence supports the trial courts finding LPA violated its professional duty. In an action at law, when a case is tried without a jury, the trial courts findings of fact will be upheld on appeal when they are reasonably supported by the evidence. Butler Contracting, Inc. v. Court St., LLC, 369 S.C. 121, 127, 631 S.E.2d 252, 255 (2006). Where professional negligence is alleged, expert testimony is usually necessary to establish both the standard of care and the professionals deviation from that standard, unless the subject matter is within the area of common knowledge and experience of the layman so that no special learning is needed to evaluate the professionals conduct. City of York v. Turner-Murphy Co., Inc., 317 S.C. 194, 196, 452 S.E.2d 615, 617 (Ct. App. 1994).
At trial, Herman Snyder, qualified as an expert in road construction in South Carolina, testified it is within industry standards for a contractor to rely on geotechnical information when preparing bids and it is the designers responsibility to reflect accurately the anticipated scope of work in its report to assist the bidder.
Additionally, Carroll Crowther was qualified as an expert in geotechnical engineering and construction consulting. Crowther testified the normal practice in the construction industry is to rely on geotechnical reports when computing bids. Crowther further testified the method used by LPA to produce its report was superficial and required a leap of faith for the report to provide information regarding the locations rock profile. Lastly, Crowther testified LPAs actions only minimally reduced the risk of a contractor encountering unknown situations.
Snyder and Crowther established a basis for the factfinder to conclude that the standard in the industry is for a design professional to provide reasonably accurate estimates, because it is the norm for bidders to rely on the provided information. Furthermore, Crowthers testimony clearly intimates that LPA was negligent in providing bidders with only superficial information about the rock associated with the project. Consequently, the record supports the trial courts finding of professional negligence on the part of LPA.
3. Riverbanks and LPA allege Plowden expressly or primary impliedly assumed the risk the unit price for rock excavation was inadequate. Express assumption of risk applies when the parties expressly agree in advance, either in writing or orally, that the plaintiff will relieve the defendant of his or her legal duty toward the plaintiff. Davenport v. Cotton Hope Plantation Horizontal Prop. Regime, 333 S.C. 71, 79,
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Plowden Construction v. Richland-Lexington Riverbanks Park District, Counsel Stack Legal Research, https://law.counselstack.com/opinion/plowden-construction-v-richland-lexington-riverbanks-park-district-scctapp-2008.