Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc.

463 S.E.2d 85
CourtSupreme Court of South Carolina
DecidedOctober 16, 1995
Docket24328
StatusPublished
Cited by47 cases

This text of 463 S.E.2d 85 (Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc., 463 S.E.2d 85 (S.C. 1995).

Opinion

463 S.E.2d 85 (1995)

TOMMY L. GRIFFIN PLUMBING & HEATING CO., Appellant,
v.
JORDAN, JONES & GOULDING, INC., Respondent.

No. 24328.

Supreme Court of South Carolina.

Heard December 8, 1994.
Decided October 16, 1995.

*86 David B. Ratterman and Gerald L. Stovall, both of Goldberg & Simpson, Louisville, Kentucky; and Marvin D. Infinger, of Sinkler & Boyd, Charleston, for Appellant.

W. Jefferson Leath, Jr., of Young, Clement, Rivers & Tisdale, Charleston; and George D. Wenick, of Smith & Fleming, Atlanta, Georgia, for Respondent.

TOAL, Justice:

Tommy Griffin Plumbing & Heating Co. ("Griffin") appeals the circuit court's granting Jordan, Jones & Goulding's ("Engineer") motion for summary judgment. We affirm in part, reverse in part and remand to the circuit court.

FACTS

Griffin was the low bidder on the construction of a water trunk for the County of Charleston. Engineer was the design engineer and supervised the project for the County.

The bid required Griffin to hold the bid price for 60 days to finalize the contract between the County and Griffin. During that time, County discovered that a portion of the project would have to be redesigned by Engineer. Because of the redesign, the award of the contract was delayed. Subsequently, Griffin entered into a contract with the County to construct the water trunk and a "special agreement" in which Griffin released the County and Engineer from any liability for the delay in awarding the contract.

Once construction began, Griffin and Engineer had numerous disagreements. Griffin brought this action claiming Engineer wrongfully closed the job for nearly a month due to false allegations of OSHA violations, Engineer made demands of Griffin which were not in the contract, Engineer wrote a disparaging *87 letter to Griffin's bonding company, Engineer erroneously interpreted the contract to the County and Griffin, and Engineer's false interpretations of the contract required Griffin to hire an expert to interpret the contract between Griffin and the County. The County paid Griffin for all of the extra costs which County agreed were caused by County, but County refused to compensate Griffin for costs incurred by Griffin as a result of Engineer's acts.

Griffin brought this action against Engineer alleging breach of implied warranty, fraud, tortious interference with present and prospective contracts, injurious falsehood, breach of professional responsibility, and economic duress. Griffin also asked for declaratory judgment and punitive damages. The circuit court judge granted summary judgment to the Engineer on all of Griffin's contract claims, finding there was no privity of contract between Griffin and Engineer. Additionally, the circuit court judge granted summary judgment to Engineer on all of Griffin's tort claims, holding Griffin could not recover in tort for purely "economic loss." Griffin appeals.

LAW/ANALYSIS

Economic Loss

The trial judge, relying on Carolina Winds Owners' Association, Inc. v. Joe Harden Builder, Inc., 299 S.C. 224, 383 S.E.2d 463 (Ct.App.1988), held Griffin could not recover economic loss for the tort of professional malpractice. Griffin contends this was error. We agree.

Beachwalk Villas Condominium Association, Inc. v. Martin, 305 S.C. 144, 406 S.E.2d 372 (1991) specifically recognized that Kennedy v. Columbia Lumber & Mfg. Co., Inc., 299 S.C. 335, 384 S.E.2d 730 (1989) overruled Carolina Winds. Therefore, any reliance on Carolina Winds by the trial judge was an error of law.

Whether design professionals incur malpractice tort liability to the contractor for purely economic loss is a novel question in South Carolina. Traditionally, almost all states uniformly held that design professionals were not liable in tort to the plaintiff for purely economic loss. See, e.g., R.H. Macy & Co., Inc. v. Williams Tile & Terrazzo Co., Inc., 585 F.Supp. 175 (N.D.Ga.1984) (based on Georgia's privity statute); Floor Craft Floor Covering, Inc. v. Parma Community Gen. Hosp. Ass'n., 54 Ohio St.3d 1, 560 N.E.2d 206 (1990) (in absence of privity of contract between parties, there is no duty to exercise reasonable care to avoid economic losses to another); Spivack v. Berks Ridge Corp., Inc., 402 Pa.Super. 73, 586 A.2d 402 (1990) (economic losses may not be recovered in tort (negligence) absent physical injury or property damage); Blake Constr. Co., Inc. v. Alley, 233 Va. 31, 353 S.E.2d 724 (1987) (in action between contractor and architect, purely economic losses cannot be recovered in tort absent privity of contract). In the last few years, a growing number of states have refused to apply the "economic loss" rule to actions against design professionals when there is a "special relationship" between the design professional and the contractor.[1]

*88 This Court addressed the "economic loss" rule in both Beachwalk and Kennedy. In Kennedy, we stated that "[t]he `economic loss' rule will still apply where the duties are created solely by contract." Id. 299 S.C. at 347, 384 S.E.2d at 737. We adhere to the Kennedy application of the "economic loss" rule.

We recognize some states use the "economic loss" rule to prohibit all recovery of purely economic damages in tort. See, e.g., Blake v. Alley, 233 Va. 31, 353 S.E.2d 724, 726 (1987) (no recovery in tort absent injury to property or person). The law in South Carolina, however, has long recognized tort actions when the damages are purely economic. See, e.g., Mitchell v. Holler, 311 S.C. 406, 429 S.E.2d 793 (1993) (legal malpractice); Beachwalk Villas Condominium Ass'n v. Martin, 305 S.C. 144, 406 S.E.2d 372 (1991) (architect liability); Georganne Apparel v. Todd, 303 S.C. 87, 399 S.E.2d 16 (Ct.App.1990) (accountant malpractice dismissed for failure to prosecute).

In our view, the Kennedy application of the "economic loss" rule maintains the dividing line between tort and contract while recognizing the realities of modern tort law. Purely "economic loss" may be recoverable under a variety tort theories.[2] The question, thus, is not whether the damages are physical or economic. Rather the question of whether the plaintiff may maintain an action in tort for purely economic loss turns on the determination of the source of the duty plaintiff claims the defendant owed. A breach of a duty which arises under the provisions of a contract between the parties must be redressed under contract, and a tort action will not lie. A breach of a duty arising independently of any contract duties between the parties, however, may support a tort action. State Ports Auth. v. Booz-Allen, 289 S.C. 373, 346 S.E.2d 324 (1986).

In most instances, a negligence action will not lie when the parties are in privity of contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
463 S.E.2d 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/griffin-plumbing-heating-co-v-jordan-jones-goulding-inc-sc-1995.