This text of 64 S.E.2d 885 (Hill v. Polar Pantries) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hill v. Polar Pantries, 64 S.E.2d 885, 219 S.C. 263, 25 A.L.R. 2d 1080, 1951 S.C. LEXIS 49 (S.C. 1951).

Opinion

OxnER, Justice.

This is an action for the recovery of damages alleged to have been caused by the negligence of appellant in furnishing unsuitable and defective plans and specifications for the insulation of a frozen food locker plant and in failing to properly supervise the work. The trial resulted in a verdict for respondent in the sum of $10,100.00. The only question for determination on this appeal is whether the Court below erred in refusing a motion by appellant for a directed verdict. Appellant contends that there is no proof of a breach of the contract made with respondent and no evidence showing the cause of the damage complained of.

Appellant, a South Carolina corporation, has operated a frozen food locker plant at Greenville, South Carolina, since 1940. During July, 1945, respondent became interested in constructing a similar plant at Belton, South Carolina. He *266 had never had any experience in this business and, in fact, had never been in a frozen food locker plánt. Shortly thereafter he met and discussed the matter' with Mr. C. M. Snelling, Jr., President of the appellant corporation. On October 29, 1945, these parties entered into a contract wherein appellant, in consideration of the payment by respondent of a commission of 22^2% of the cost of the equipment and insulation, agreed (1) to furnish the design of the layout of a frozen food locker plant to be constructed by respondent at-Belton, S. C., together with blueprints of such design, (2) to fully advise respondent and offer suggestions deemed desirable as to the structure and the materials necessary to adequately serve the needs of the plant, (3) to furnish and install in accordance with good -practice necessary .controls and equipment, including insulation required for successful operation, (4) to purchase all equipment at the best possible price and to allow respondent the benefit of all discounts, and (5) if desired, to instruct in its Greenville plant any employees of respondent so as to familiarize such employees with the operation of a frozen food locker plant. The costs of the building, insulation and equipment were to be paid by respondent. There are other stipulations contained in this contract but they need not be reviewed since they are not germane to the controversy.

It is clear from an examination of the entire contract that the commissions to be paid appellant were primarily intended to compensate it for furnishing the skill and knowledge necessary for the proper construction - and equipment of a frozen food locker plant. Appellant held itself out as specially qualified to perform work of this nature as shown by the following recitals in the contract:

“Whereas, Polar Pantries óf Greenville, South Carolina, having designed, equipped and operated its own frozen-food locker plant since 1940 and also by reason of being dealer-distributor for Prigidaire locker plant equipment, is prepared to design, equip and operate locket plants in this vicinity and to instruct in the detailed operations of this business, and

*267 “Whereas, the uhdersigned, Fred Hill, proposes to establish a locker plant at Belton, South Carolina, and desires to obtain the benefit and use of the experience acquired by Polar Pantries both in the design and operation of such plant * *

Plans and specifications, calling for a building approximately 58 by 63 feet, including a locker room with space for 636 lockers, were duly prepared in accordance with appellant’s design. On December 6, 1945, a contract for the construction of the building was awarded tO' Morris Construction Company of Greenville. The building, including the insulation, was completed about April, 1946. The equipment was installed in September. The total cost of the plant amounted to approximately $35,000.00. About October 1, 1946, the cooling process in the locker room was turned on. The temperature was first fixed above freezing and gradually reduced until it reached about zero. Three or four weeks later pin cracks appeared in the floor. At first not a great deal of significance was attached to these small cracks but they graudally grew larger and in about a year reached a point where they were approximately three inches in width. There was a bulge in the floor in some places as much as seven inches. Finally, the walls cracked. During. the fall of 1948 it had become impossible to use the locker room and the lockers were then removed to a new room which respondent had constructed. Respondent made a claim against appellant for damages but appellant denied liability. Thereafter in April, 1949, this action was commenced.

It is alleged in the complaint that appellant breached the contract (1) by furnishing faulty, defective and unsuitable plans and specifications for the insulation of said plant and (2) by improperly supervising the work of insulation. Appellant " interposed a general denial, alleged that respondent had failed to follow its drawings, blueprints and specifications, asserted that its authorty was limited to giving advice and making suggestions which were frequently disregarded, and further alleged contributory negligence on the part of *268 respondent in failing to comply with its- written and oral specifications.

This controversy hinges largely upon the construction of the floor of the locker room.' Although the actual construction was done by the Morris Construction Company, the plans and specifications were prepared by Mr. Snelling, who also directed and supervised the work. The following type of insulation was used in this floor: The ground was graded and four inches of stone placed on a clay bottom. The stone was then covered with what is termed “vapor seal”, consisting of tarred felt and asphalt, which was designed to keep out moisture from the ground. On top of this vapor seal there was placed fifteen inches of a mixture of concrete and vermiculite, a lightweight insulating material. About fourteen or fifteen gallons of water were used to each cubic foot of cement. This mixture dries very slowly. Electric heaters and coke burners were used in the drying process. Several weeks after the vermiculite mixture had been laid, Mr. Snelling and a representative of the vermiculite manufacturer made a test’ by drilling- some holes and concluded that it was sufficiently dry to proceed with the construction. The vermiculite ’ was then covered with two and a half inches of concrete.

It is appellant’s contention that there is no evidence reasonably warranting the.inference that any negligence on its part caused the damage sustained by respondent. It is said in appellant’s brief: “The plaintiff’s loss could be due to the neglect on the part of the defendant. It could just as well be due to negligence on the part of Morris Construction Company, who built the building and who installed the insulation in the floor’. It could be due to negligence on the part of plaintiff in operating the plant. It could just as- well have been the result of an unforeseeable accident. The evidence, direct and circumstantial, does not indicate which.”

'Both respondent and Mr. Morris of the Morris Construction Company, testified that the' damage was causéd by ice forming ini the-floor. Mr. Morris further testified:

*269 “Q. You got any idea what caused ice to get in there? A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foundation v. Fred's Inc.
Court of Appeals of South Carolina, 2020
Cacchiotti Properties, LLC v. Bradley Phillips, et ux
Court of Appeals of Washington, 2017
Colleton Preparatory Academy, Inc. v. Hoover Universal, Inc.
666 S.E.2d 247 (Supreme Court of South Carolina, 2008)
Watts Construction Company v. Feltes
Court of Appeals of South Carolina, 2006
Burbo v. Harley C. Douglass, Inc.
125 Wash. App. 684 (Court of Appeals of Washington, 2005)
Cruet v. Carroll, No. X06-Cv-00-0166704s (Nov. 27, 2001)
2001 Conn. Super. Ct. 15941-jq (Connecticut Superior Court, 2001)
Eastern Steel Constructors, Inc. v. City of Salem
549 S.E.2d 266 (West Virginia Supreme Court, 2001)
State v. Tisdale
527 S.E.2d 389 (Court of Appeals of South Carolina, 2000)
CULLUM MECHANICAL v. SC Baptist Hosp.
520 S.E.2d 809 (Court of Appeals of South Carolina, 1999)
Cullum Mechanical Construction, Inc. v. South Carolina Baptist Hospital
520 S.E.2d 809 (Court of Appeals of South Carolina, 1999)
Tommy L. Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc.
463 S.E.2d 85 (Supreme Court of South Carolina, 1995)
Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc.
463 S.E.2d 85 (Supreme Court of South Carolina, 1995)
APAC Carolina, Inc. v. Town of Allendale
41 F.3d 157 (Fourth Circuit, 1994)
APAC-Carolina, Inc. v. Towns of Allendale & Fair Fax
868 F. Supp. 815 (D. South Carolina, 1993)
Georgetown Steel Corp. v. Union Carbide Corp.
806 F. Supp. 74 (D. South Carolina, 1992)
BEACHWALK VILLAS COND. ASSOC. INC. v. Martin
406 S.E.2d 372 (Supreme Court of South Carolina, 1991)
Kennedy v. Columbia Lumber & Manufacturing Co.
384 S.E.2d 730 (Supreme Court of South Carolina, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
64 S.E.2d 885, 219 S.C. 263, 25 A.L.R. 2d 1080, 1951 S.C. LEXIS 49, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hill-v-polar-pantries-sc-1951.