Cullum Mechanical Construction, Inc. v. South Carolina Baptist Hospital

520 S.E.2d 809, 336 S.C. 423, 1999 S.C. App. LEXIS 118
CourtCourt of Appeals of South Carolina
DecidedMay 3, 1999
DocketNo. 2985
StatusPublished
Cited by5 cases

This text of 520 S.E.2d 809 (Cullum Mechanical Construction, Inc. v. South Carolina Baptist Hospital) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cullum Mechanical Construction, Inc. v. South Carolina Baptist Hospital, 520 S.E.2d 809, 336 S.C. 423, 1999 S.C. App. LEXIS 118 (S.C. Ct. App. 1999).

Opinion

ORDER DENYING PETITION FOR REHEARING AND SUBSTITUTING OPINION

PER CURIAM:

After careful consideration of the Petition for Rehearing, the Court is unable to discover any material fact or principle of law that has been either overlooked or disregarded and, hence, there is no basis for granting a rehearing. It is, therefore, ordered that the Petition for Rehearing be denied. We withdraw the previously filed opinion and substitute the attached opinion.

HEARN, Judge:

Cullum Mechanical Construction, Inc. filed this action against South Carolina Baptist Hospital, a/k/a Baptist Medical Center (Owner), Jenkins, Hancock & Sides Architects and Planners, Inc. (Architect), Miller-Sharpe, Inc. (General Contractor), John M. Miller, Donald R. Sharpe, and General Accident Insurance Company of America (Surety), seeking $426,728.87 for unpaid goods and services on a project to upfit areas of the Baptist Medical Center.1 The trial court granted Architect’s summary judgment motion, finding it owed no legal or contractual duty to Cullum, a subcontractor. After a bench trial, the trial court ruled in favor of Surety, finding Cullum was not a third-party beneficiary under the bid bond. Cullum appeals both orders. We affirm.

FACTS

In the fall of 1992, Owner retained Architect to upfit the 8th and 9th floors of Baptist Hospital. Architect prepared a Project Manual dated April 11, 1993, to be used by potential contractors in submitting bids. General Contractor was among those contractors invited to bid on the project. On May 4, 1993, General Contractor submitted its bid of $3,540,-[427]*427700.00. After some initial changes, Owner executed a contract on June 10, 1993, with General Contractor for $3,260,430.00. The Notice to Proceed date was June 11,1993.

As portions of the work were completed, Architect certified payments to General Contractor: (1) $77,670.00 on June 28, 1993; (2) $114,967.80 on July 26, 1993; (3) $463,784.40 on August 30, 1993; (4) $476,515.80 on October 4, 1993; (5) $384,043.50 on November 3, 1993; and (6) $449,082.00 on December 3,1993.

Despite receiving these monies, totaling $1,966,063.50, General Contractor did not pay its subcontractors. On October 11, 1993, Cullum wrote General Contractor, stating: “[A]s of September, we had billed you $442,065.60 and haven’t received any payments. Please get our July and August payments to us immediately.” It was not until November 10, 1993, however, that Cullum executed its contract with General Contractor. The contract’s cover letter also acknowledged payment problems: “We billed $225,499.50 on August 19, 1993, and received this payment on November 9, 1993. This is not promptly or timely as indicated by the contract. We have also billed $127,712.70 on September 20, 1993, and payment is due but not received.”

Other subcontractors began to complain about nonpayment. In response to Owner’s inquiry, Architect requested a copy of General Contractor’s payment bond on November 12, 1993. On December 7, 1993, General Contractor submitted a “General Agreement of Indemnity” issued by Chubb Group of Insurance Companies dated August 24, 1993. Despite not receiving a payment bond from General Contractor, Architect apparently approved reducing the retainage from ten to five percent in December 1993. Moreover, Architect certified additional payments totaling $1,284,893.95: (1) $635,911.45 on December 23, 1993; (2) $503,063.85 on January 31, 1994; (3) $94,819.95 on March 2, 1994; and (4) $51,098.70 on April 14, 1994.2

[428]*428Finally, on May 13,1994, General Contractor admitted there was no payment bond on the project and that the monies it received from Owner had been used to pay unrelated legal bills. Cullum and other subcontractors sued Owner, General Contractor, Surety, and two principals of General Contractor; Cullum also sued Architect. Uncollectible default judgments were obtained against General Contractor. Cullum’s claims against Owner were settled.3 The trial judge granted Architect’s motion for summary judgment. Cullum appeals this order. After a trial concerning Surety’s liability, the trial judge found for Surety. Cullum, on behalf of all plaintiffs, appeals this order.

APPEAL AS TO ARCHITECT

Cullum first argues the trial court erred by granting Architect’s summary judgment motion. We disagree.

“Summary judgment is proper where there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law.” Tupper v. Dorchester County, 326 S.C. 318, 325, 487 S.E.2d 187, 191 (1997); see Rule 56(c), SCRCP. Summary judgment should be granted when it is clear that “further inquiry into the facts is not desirable to clarify application of the law.” Hyder v. Jones, 271 S.C. 85, 87, 245 S.E.2d 123, 124-25 (1978); Parker v. Williams & Madjanik, Inc., 269 S.C. 662, 664, 239 S.E.2d 487, 488 (1977).

Cullum acknowledges it had no contract with Architect.4 However, relying on Tommy L. Griffin Plumbing & Heating [429]*429Co. v. Jordan, Jones & Goulding, Inc., 320 S.C. 49, 463 S.E.2d 85 (1995), Cullum contends Architect owed it a professional duty distinct from any contractual duty. Cullum maintains the project manual, the contracts between Owner and Architect, and the contract between Owner and General Contractor create a genuine issue of material fact whether Architect owed the subcontractors a legal duty. Cullum contends Architect undertook to marshal and assemble contract documents and to supervise payments on the project, thereby creating a duty to do so with due care. Further, Cullum alleges that Architect had a legal duty not to injure foreseeable parties with whom it had a special relationship even absent contractual privity.

Cullum introduced expert testimony supporting its assertion of a special relationship between subcontractors and Architect. Cullum’s expert, Roy D. Smith, opined:

Under [Architect’s] professional services contract with Baptist Medical Center (“Owner”) it was Jenkins, Hancock & Sides’ (“Architect”) professional responsibility to marshall [sic] and assemble the contract documents, including review of the payment and labor bond for sufficiency, under the contract documents.... The Architect breached its professional duty of care by failing to secure a payment bond from the contractor as part of the preconstruction submittal package. The Architect breached it professional duty of care by misrepresenting that failure to Cullum.
[430]*430The Architect also had a professional duty to accurately certify payment requests of the contractor in order that those items for which the Owner was issuing payment were in fact performed or delivered. The Architect owed a professional duty not to certify payment applications without reasonably assuring that the labor and payment bond had been provided. The Architect breached its professional duty by approving such payment application without ascertaining the existence of the labor and material payment bond....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cullum Mechanical Construction, Inc. v. South Carolina Baptist Hospital
544 S.E.2d 838 (Supreme Court of South Carolina, 2001)
CULLUM MECHANICAL v. SC Baptist Hosp.
544 S.E.2d 838 (Supreme Court of South Carolina, 2001)
F & D Electrical Contractors, Inc. v. Powder Coaters, Inc.
537 S.E.2d 285 (Court of Appeals of South Carolina, 2000)
Boren v. Thompson & Associates
2000 OK 3 (Supreme Court of Oklahoma, 2000)
CULLUM MECHANICAL v. SC Baptist Hosp.
520 S.E.2d 809 (Court of Appeals of South Carolina, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
520 S.E.2d 809, 336 S.C. 423, 1999 S.C. App. LEXIS 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cullum-mechanical-construction-inc-v-south-carolina-baptist-hospital-scctapp-1999.