Cullum Mechanical Construction, Inc. v. South Carolina Baptist Hospital

544 S.E.2d 838, 344 S.C. 426, 2001 S.C. LEXIS 52
CourtSupreme Court of South Carolina
DecidedMarch 26, 2001
DocketNo. 25265
StatusPublished
Cited by3 cases

This text of 544 S.E.2d 838 (Cullum Mechanical Construction, Inc. v. South Carolina Baptist Hospital) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cullum Mechanical Construction, Inc. v. South Carolina Baptist Hospital, 544 S.E.2d 838, 344 S.C. 426, 2001 S.C. LEXIS 52 (S.C. 2001).

Opinion

ON WRIT OF CERTIORARI TO THE COURT OF APPEALS

MOORE, Justice:

We granted a writ of certiorari to review the Court of Appeals’ decision finding that respondent (Architect) did not owe a duty of reasonable care to petitioner (Cullum). Cullum Mechanical Constr., Inc. v. South Carolina Baptist Hosp., 336 S.C. 423, 520 S.E.2d 809 (Ct.App.1999). We reverse.

[429]*429FACTS

Cullum, a subcontractor, filed an action against South Carolina Baptist Hospital, a/k/a Baptist Medical Center (Owner), Architect, Miller-Sharpe, Inc. (General Contractor) and its principals, and General Accident Insurance Company of America (Surety) seeking $426,728.87 for unpaid goods and services on a project to perform construction on certain floors of the Medical Center. While other subcontractors filed similar suits, only Cullum sued Architect on the theory that Architect owed a duty to use reasonable care in the administration of contractual provisions that were designed to ensure payment to subcontractors.

In September 1992, Owner and Architect contracted to conduct renovations in the Medical Center. Architect prepared a Project Manual for potential contractors to use in submitting bids. After entering a successful bid, General Contractor and Owner executed an agreement on June 10, 1993.

Before bidding on the subcontractual work for General Contractor, Cullum had several individuals review the Project Manual. Cullum’s responsibilities, after its bid was accepted, were to perform heating, ventilation, air conditioning, and plumbing work on the project.

Architect’s responsibilities under its contract with Owner included reviewing General Contractor’s payment applications, certifying the amounts due General Contractor,1 and determining whether Owner and General Contractor had performed according to the requirements of their contract upon written request of either party. Owner was responsible for giving prompt written notice to Architect if Owner became aware of any fault or defect in the project or nonconformance with the contract documents.

[430]*430Under General Contractor’s contract with Owner, Architect had the ability to withhold the certification of payments if General Contractor failed to properly pay subcontractors.

General Contractor was required to post a performance and payment bond, which would be delivered to Owner at or prior to delivery of the signed agreement between Owner and General Contractor. The payment bond would ensure payment to those who provided labor or materials to the project. However, General Contractor did not deliver the bond as required. Despite General Contractor’s failure to provide a bond, Owner and General Contractor entered into their contract.

General Contractor’s responsibilities also included promptly paying Cullum, and other subcontractors, upon receipt of payment from Owner and, upon request, furnishing a copy of the bond. Further, General Contractor had to submit to Architect with each payment application satisfactory evidence that all indebtedness connected with the part of the work for which application for payment was made had been paid, and submit “a properly executed subcontractor waiver of lien ... for the previously paid application for payment, stating [the] amounts paid.” However, General Contractor never attached the lien waivers to the payment applications.

While the construction project was proceeding, General Contractor was dilatory in making payments to Cullum. Before Cullum executed its contract with General Contractor, Cullum wrote General Contractor stating, although Cullum had billed $442,065.60, no payments had yet been received. Cullum and Architect also engaged in a telephone conversation in which Cullum informed Architect it and other subcontractors were not being paid. Cullum asked Architect if General Contractor was bonded, and Architect responded that it did not know.

On November 10, 1993, Cullum finally executed its contract with General Contractor. The cover letter stated that while some payments had been untimely made, $127,712.70 was still outstanding. Cullum requested in the letter that General Contractor give Cullum the name of the bonding company on the project. However, the name was never given. Cullum [431]*431stated that it was unaware that General Contractor had not submitted a payment bond until after the job was completed.

When other subcontractors began to complain about nonpayment, Architect, in response to Owner’s inquiry, requested a copy of General Contractor’s payment bond. General Contractor submitted a “General Agreement of Indemnity,” which did not comply with the contract terms because it was not a payment bond. However, Owner stated that it believed the “General Agreement of Indemnity” indicated a bond existed. Architect never recommended to Owner that Owner should terminate General Contractor because General Contractor had not provided a payment bond. Architect stated that it simply passed the. information received from General Contractor to Owner.

Although Architect knew there was not a payment bond and that subcontractors were not being paid, Architect continued to certify payments and reduced the amount Owner retained2 from the payments from ten percent to five percent.3

[432]*432After the project was completed and Cullum had not been fully paid by General Contractor, Cullum sued Architect. Architect’s motion for summary judgment was granted, and the trial court found that Architect did not owe a duty to Cullum. Cullum appealed the order to the Court of Appeals, which affirmed. Cullum Mechanical Constr., Inc. v. South Carolina Baptist Hosp., supra. We granted a writ of certiorari to review the Court of Appeals’ decision.

ISSUE

May an architect owe a duty to ensure a general contractor pays its subcontractors?

DISCUSSION

A trial court may properly grant a motion for summary judgment when “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Rule 56(c), SCRCP. Summary judgment is not appropriate, however, when further inquiry into the facts of the case is desirable to clarify the application of the law. Brockbank v. Best Capital Corp., 341 S.C. 372, 534 S.E.2d 688 (2000) (citing Tupper v. Dorchester County, 326 S.C. 318, 487 S.E.2d 187 (1997)). In determining whether any triable issues of fact exist, the court must view the evidence and all reasonable inferences that may be drawn- from the evidence in the light most favorable to the non-moving party. Id. (citing Manning v. Quinn, 294 S.C. 383, 365 S.E.2d 24 (1988)).

“A breach of a duty arising independently of any contract duties between the parties ... may support a tort action.” Tommy L. Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc., 320 S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hard Hat Workforce Solutions, LLC v. Mechanical HVAC Services, Inc.
750 S.E.2d 921 (Supreme Court of South Carolina, 2013)
Eaton Corp. v. Trane Carolina Plains
350 F. Supp. 2d 699 (D. South Carolina, 2004)
CULLUM MECHANICAL v. SC Baptist Hosp.
544 S.E.2d 838 (Supreme Court of South Carolina, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
544 S.E.2d 838, 344 S.C. 426, 2001 S.C. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cullum-mechanical-construction-inc-v-south-carolina-baptist-hospital-sc-2001.