Georgetown Steel Corp. v. Union Carbide Corp.

806 F. Supp. 74, 1992 U.S. Dist. LEXIS 17669, 1992 WL 332016
CourtDistrict Court, D. South Carolina
DecidedNovember 6, 1992
DocketCiv. A. 2:85-0440-1
StatusPublished
Cited by1 cases

This text of 806 F. Supp. 74 (Georgetown Steel Corp. v. Union Carbide Corp.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Georgetown Steel Corp. v. Union Carbide Corp., 806 F. Supp. 74, 1992 U.S. Dist. LEXIS 17669, 1992 WL 332016 (D.S.C. 1992).

Opinion

ORDER

HAWKINS, Chief Judge.

This suit arose from foundation damage to a track scale, a truck scale, a refractory warehouse, and an oxygen separating plant located at the Georgetown Steel Corporation (GSC) plant in Georgetown, South Carolina. At GSC’s request, Pittsburgh Testing Laboratory, Inc. (PTL) performed tests on steel slag, a by-product of' the steel milling process, to determine if the steel slag had certain properties and characteristics that would permit its use as backfill material. Steel slag has expansive properties that were not revealed by the particular tests PTL was asked to perform. Slag was used as backfill under the track scale, the truck scale and the warehouse. Additionally, steel slag was used as backfill beneath an oxygen separation plant built by Union Carbide at a site on the premises of GSC.

GSC leased a site to Union Carbide (Carbide) to build an oxygen separation plant on GSC’s steel mill premises so that GSC could obtain liquid oxygen and nitrogen at a lesser cost. The highly sensitive instruments of the oxygen separation plant have an extremely low tolerance for even minimal foundation movement from settlement. GSC contracted with Law Engineering Testing Company (Law) to perform engineering and soil testing services for the site preparation. Use of steel slag as back-fill was approved by Law, though Law performed no tests on the slag to determine its suitability for such use.

After the plant was completed, the slag beneath the building began to swell and, eventually, the swelling rendered the oxygen plant useless and dangerous. The oxygen plant had to be closed down on May 5, 1985.

GSC filed suit against PTL for damage to the track scale, the truck scale and the *76 refractory warehouse and against both PTL and Law for damages sustained from the destruction of the oxygen separation plant. GSC sued PTL and Law on claims of negligence, and breach of express and implied warranties. GSC filed suit against Carbide for declaratory judgment to determine the rights of the respective parties. 1 Carbide cross-claimed against Law and PTL and counterclaimed against GSC. The case was tried to this court and that decision 2 was appealed to the Fourth Circuit Court of Appeals.

This court’s order allowed GSC to recover for PTL’s negligence only for the damage to the track scale. Having found that GSC should have been on notice regarding problems with the use of slag as backfill after the problems arose with the track scale, the district court found that GSC’s contributory negligence barred recovery from PTL for the damage to the other buildings. The lower court further found PTL had breached its implied warranty to GSC but denied damages because use of the slag as backfill material to be placed under a particular structure was not foreseeable to PTL. The district court found no express warranty from PTL to GSC.

The trial court denied GSC’s negligence and express and implied warranty causes of actions against Law upon a finding that the expansiveness of the slag did not fall within Law’s scope of duties as defined in its agreements with GSC. Further, the lower court denied GSC’s claims against PTL and Law. Lastly, all of Carbide’s claims against Law were denied on the theory that GSC was Carbide’s agent and that GSC’s contributory negligence was imputed to Carbide.

The Fourth Circuit Court of Appeals affirmed 3 the finding of GSC’s contributory negligence as to the claims against PTL. The court of appeals also affirmed the finding that GSC could not recover from PTL for damages to any structure other than the track scale. The amount of damages due from PTL to GSC for backfill expansion under the track scale house has already been determined by the lower court to be $3,233 and judgment has been satisfied. 4

However, the court of appeals held that Law was negligent in approving the use of slag for backfill without first testing it for suitability. The appellate court also found that GSC’s failure to inform Law of the problems at the track scale did not rise to the level of contributory negligence, and further, that GSC was not contributorily negligent when it informed Law that slag had successfully been used as backfill in other operations at the plant. Additionally, the Fourth Circuit found that Law breached its warranty to GSC when Law rendered its opinion that slag would be suitable as a fill material without first testing the slag.

As to Carbide’s claims against PTL, the court of appeals agreed that PTL had no duty to Carbide. However, as to the finding that an agency relationship existed between Carbide and GSC, imputing GSC’s knowledge to Carbide and thus, precluding Carbide from recovering from Law, the appellate court held the finding to be clearly erroneous.

On remand this court must determine the amount of damages due to GSC for Law’s negligence and breach of warranty, and must determine whether Law is liable to Carbide and, if so, the amount of damages resulting therefrom.

Law urges a finding that the limitation of liability and warranty provision, contained in the contract between Law and GSC, is an express warranty and limitation of liability for any professional negligence *77 in Law’s performance of duties under the contract.

The relevant contractual provision reads: WARRANTY AND LIMITATION OF LIABILITY — The only warranty or guarantee made by Law Engineering Testing Company in connection with the services performed hereunder, is that we will use that degree of care and skill ordinarily exercised under similar conditions by reputable members of our profession practicing in the same or similar locality. No other warranty, expressed or implied is made or intended by our proposal for consulting services or by our furnishing oral or written reports.
Our liability for any damage on account of any error, omission, or other professional negligence will be limited to a sum not to exceed $50,000 or our fee, whichever is greater. In the event the client does not wish to limit our professional liability to this sum, we agree to waive this limitation upon receiving client’s written request, and agreement by the client to pay additional consideration of 4% of our total fee or $200.00-whichever is greater.

Exculpatory clauses are not generally favored in the law and are strictly construed against the party seeking to enforce a limitation on its own negligence. See, Pride v. Southern Bell Telephone and Telegraph Co., 244 S.C. 615, 138 S.E.2d 155, 157 (1964). However, in a contract between private parties of roughly equal bargaining power such limitations may be upheld. In the instant case, GSC is a business sophisticate. As this court has already noted, 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
806 F. Supp. 74, 1992 U.S. Dist. LEXIS 17669, 1992 WL 332016, Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgetown-steel-corp-v-union-carbide-corp-scd-1992.