CHRISTIANSEN BROTHERS v. State

25 Cont. Cas. Fed. 83, 586 P.2d 840, 90 Wash. 2d 872, 25 U.C.C. Rep. Serv. (West) 385, 1978 Wash. LEXIS 1140
CourtWashington Supreme Court
DecidedNovember 9, 1978
Docket45376
StatusPublished
Cited by24 cases

This text of 25 Cont. Cas. Fed. 83 (CHRISTIANSEN BROTHERS v. State) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CHRISTIANSEN BROTHERS v. State, 25 Cont. Cas. Fed. 83, 586 P.2d 840, 90 Wash. 2d 872, 25 U.C.C. Rep. Serv. (West) 385, 1978 Wash. LEXIS 1140 (Wash. 1978).

Opinion

Dolliver, J.

This case originated as an action by Christiansen Brothers, Inc., against the State of Washington to recover damages allegedly arising out of delays in the construction of two buildings at Washington State University (WSU). Detweiler Brothers, Inc., joined the original action as a party plaintiff. The State, as a third-party plaintiff, then brought an action against the architectural firm, Naramore, Bain, Brady and Johanson (NBBJ). During trial, WSU and the architectural firm settled with Christiansen.

On or about February 26, 1968, the State entered into a contract with NBBJ whereby NBBJ, as a part of its agreement, contracted to design and prepare the plans and specifications for the construction of two separate side-by-side structures at WSU. One structure was a 15-story laboratory and classroom tower and the other a 3-story lecture hall unit. NBBJ did not contract to coordinate the work.

Pursuant to construction of the project, five separate prime contracts were executed by WSU and various contractors. Christiansen agreed to perform the "General Work Construction" for $3,869,800 and Detweiler Brothers, Inc., agreed to perform the "Mechanical Work Construction" for $2,246,575. Subsequent change order work increased the contract amounts of Christiansen and Detweiler in the respective amounts of $39,989.02 and $64,563.19.

Although the contract called for completion by May 6, 1973, the trial court found Detweiler's substantial completion did not occur prior to November 18, 1973, and total *874 completion did not occur prior to March 15, 1974. The court determined the delay to be caused by: architectural design errors, the time other contractors took to perform change order work, acts of Christiansen and Permalab (another contractor), weather, and lack of job coordination. The court further found such factors "obstructed and delayed" Detweiler's performance and increased its cost in the amount of $227,753.

The contract executed between WSU and Detweiler included these articles:

Article 17. Delays and Extension of Time
If the Contractor is delayed at any time in the progress of work by any act or neglect of the Owner or the Architect, or of any employee of either, by any separate Contractor employed by the Owner, or by changes ordered in the work, or by strikes, lockouts, fire, unusual delay in transportation, unavoidable casualties, or by delay authorized by the Architect pending arbitration, or by any cause which the Architect shall decide justifies the delay, then the time of completion shall be extended for such reasonable time as the Architect may decide.
No such extension shall be made for delay occurring more than seven days before claim therefor is made in writing to the Architect. In the case of a continuing cause of delay, only one claim is necessary.
If no schedule or agreement stating the dates upon which drawings shall be furnished is made, then no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and not then unless such claim is reasonable.
In no event shall any delays or extensions of time be construed as cause or justification for payment of extra compensation to the Contractor.
Article 30. Damages
Should either party to this Contract suffer damages because of any wrongful act or neglect of the other party or of anyone employed by him, claim shall be made in writing to the party liable within a reasonable time of the first observance of such damage and not later than the final payment, except as expressly stipulated otherwise in the case of faulty work or materials, and shall be adjusted by agreement or arbitration.

*875 After reviewing the contract, the court entered finding of fact No. 38 to which no error is assigned:

The types of delays in work performance experienced by Detweiler on the project and which caused its increased cost of performance were the type of delays contemplated by the contracting parties on a project of this nature. Any recovery for such increased costs is controlled by the contractual remedies provided in the Detweiler and WSU contract.

After finding article 17 precluded recovery by Detweiler, the court went on to establish the amount of damages to which Detweiler would be entitled in the event of reversal on the issue of liability. It further held if WSU is liable to Detweiler, then WSU would be entitled to recover a portion of its total liability on its various cross claims and third-party claims for indemnity from NBBJ and Christiansen. From these rulings, (1) Detweiler appeals the determination of no liability; (2) the State cross-appeals as to the amount of damages; (3) NBBJ cross-appeals as to WSU's right to indemnity and also as to computation of damages; and (4) Christiansen cross-appeals as to WSU's right to indemnity and as to the computation of damages. Because of our disposition of the issue regarding liability, resolution of the three cross appeals is unnecessary.

Detweiler first argues that article 17 should be construed so as not to foreclose its claim for delay-caused damages and second, regardless of the construction of the article, it should not be enforced due to public policy considerations.

Article 17 provides that, in no event, shall "any delays or extensions of time be construed as cause or justification for payment of extra compensation to the Contractor." Detweiler urges the court to construe the term "compensation" so as not to include damages. Given this construction, Detweiler then could claim recovery for its damages under article 30.

This contention does not appreciate the well established definitions of compensation which include damages. *876 Black's Law Dictionary 354 (4th ed. 1968), defines "compensation" as, among other things, "payment of damages", while "damages" at page 466 is defined as "Compensation for the loss or injury suffered." We have previously dealt with the terms as synonymous (see McFerran v. Heroux, 44 Wn.2d 631, 642, 269 P.2d 815 (1954)), and hold that damages are included within the term "compensation" as it appears in article 17.

Detweiler next argues the "no-damages-for-delay" clause should not be interpreted to exclude recovery for delays which were the result of owner "obstruction". It cites cases from various jurisdictions which declined to preclude recovery for delays caused by (1) fraud or active interference by the owner; (2) unreasonably extended delays; (3) delays not within those specifically enumerated in the contract; or (4) those not contemplated by the contracting parties. Detweiler urges this court to create an exception where the delays are due to owner "obstruction".

The trial court did not specifically hold that WSU "obstructed" Detweiler's performance. In finding of fact No. 31, the trial court stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Torgerson v. One Lincoln Tower, LLC
210 P.3d 318 (Washington Supreme Court, 2009)
SCOCCOLO CONST. v. City of Renton
145 P.3d 371 (Washington Supreme Court, 2006)
Scoccolo Construction, Inc. v. City of Renton
158 Wash. 2d 506 (Washington Supreme Court, 2006)
Fortune View Condo. Ass'n v. Fortune Star Development Co.
90 P.3d 1062 (Washington Supreme Court, 2004)
Fortune View Condominium Ass'n v. Fortune Star Development Co.
151 Wash. 2d 534 (Washington Supreme Court, 2004)
Urban Development, Inc. v. Evergreen Building Products, LLC
59 P.3d 112 (Court of Appeals of Washington, 2003)
Scoccolo Const., Inc. v. City of Renton
9 P.3d 886 (Court of Appeals of Washington, 2000)
Scoccolo Construction, Inc. v. City of Renton
102 Wash. App. 611 (Court of Appeals of Washington, 2000)
U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc.
480 S.E.2d 447 (Supreme Court of South Carolina, 1997)
JO Hooker & Sons v. Roberts Cabinet
683 So. 2d 396 (Mississippi Supreme Court, 1996)
Tacoma Athletic Club, Inc. v. Indoor Comfort Systems, Inc.
902 P.2d 175 (Court of Appeals of Washington, 1995)
Arango Construction Co. v. Success Roofing, Inc.
730 P.2d 720 (Court of Appeals of Washington, 1986)
Gilbert Central Corp. v. State
716 P.2d 654 (Supreme Court of Oklahoma, 1986)
Garrett v. Janiewski
480 So. 2d 1324 (District Court of Appeal of Florida, 1985)
Fuller v. Director of Finance
694 P.2d 1045 (Utah Supreme Court, 1985)
Bekins Bar v. Ranch v. Huth
664 P.2d 455 (Utah Supreme Court, 1983)
Jeffery v. Weintraub
648 P.2d 914 (Court of Appeals of Washington, 1982)
Althoff Industries, Inc. v. Elgin Medical Center, Inc.
420 N.E.2d 800 (Appellate Court of Illinois, 1981)
Lester N. Johnson Co. v. City of Spokane
588 P.2d 1214 (Court of Appeals of Washington, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
25 Cont. Cas. Fed. 83, 586 P.2d 840, 90 Wash. 2d 872, 25 U.C.C. Rep. Serv. (West) 385, 1978 Wash. LEXIS 1140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/christiansen-brothers-v-state-wash-1978.