Lester N. Johnson Co. v. City of Spokane

588 P.2d 1214, 22 Wash. App. 265, 1978 Wash. App. LEXIS 2775
CourtCourt of Appeals of Washington
DecidedDecember 27, 1978
Docket2553-3
StatusPublished
Cited by19 cases

This text of 588 P.2d 1214 (Lester N. Johnson Co. v. City of Spokane) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lester N. Johnson Co. v. City of Spokane, 588 P.2d 1214, 22 Wash. App. 265, 1978 Wash. App. LEXIS 2775 (Wash. Ct. App. 1978).

Opinion

Green, J.

Plaintiff, Lester N. Johnson Co., a contractor, brought this action seeking damages against the defendant, City of Spokane, for breach of a sewer construction contract. After trial to the court, judgment was entered for plaintiff in. the amount of $28,239 plus post-judgment interest and costs. Both parties appeal.

The appeals raise the following issues: (1) Did the City breach the construction contract? (2) If so, does the contract limit the contractor's remedy for the breach to an extension in time? (3) If not, did the trial court adopt a proper method of calculating the damages? (4) Are the damages payable from the City's general fund or L.I.D. *267 funds? and (5) Is the contractor entitled to prejudgment interest?

Lester N. Johnson Co. (hereinafter referred to as "contractor") was the low bidder for the construction of a defined sanitary sewer in the city of Spokane. In December 1974, the contractor and the City entered into an agreement in which the contractor agreed to build the sanitary sewer for $63,142, to be paid only from Local Improvement Fund, District No. 6570 created by assessments against the property included within the District. 1

The contractor commenced work on February 12, 1975. The project lay in a drainage basin and, consequently, substantial ground water was encountered which slowed the progress of its work. Towards the end of February, a spring thaw and rain aggravated this condition. Then, on March 1, the City started pumping raw sewage from a nearby overloaded sanitary sewer into a field uphill from the project area. The pumping continued 24 hours a day until March 5. This action was necessary to keep the affected sewer from backing up into the homes of certain Spokane residents. On March 10, 1975, the contractor wrote a letter to the City in which it claimed that the pumping had created a condition not anticipated by either party. Specifically, the contractor alleged that the raw sewage and water had seeped from the field down into the contractor's work site, causing equipment to mire down in mud and disrupting the contractor's work plans. The City denied that a changed condition existed under the contract, and the contractor proceeded with construction, making the adjustments necessary to work in the saturated ground. Although the contract called for completion of the project within 45 working days, the contractor did not finish its work until June 17. The City does not seek damages for the delay and the trial court *268 found the City had waived its claim, if any, for damages resulting from the delay.

On August 25, the City council adopted an ordinance approving the assessment roll for the local improvement district. The amount of the assessment was based upon the contractor's final invoice for $64,257. Subsequently, on October 6, the contractor filed a written claim with the City clerk for damages and extra cost arising from its performance of the sewer contract. On October 20, the contractor commenced this action, alleging that (1) the ground water was an unanticipated sub-surface condition, and (2) the City's pumping of raw sewage constituted interference with its work. In this action, the contractor sought $67,613 in damages. The court denied damages based on the ground water allegation 2 but granted damages for the City's interference with the contractor's work.

First, the City contends that it did not breach any terms of the contract. Instead, it argues that the contract expressly authorized the type of activity which occurred here. We disagree. Recent cases have recognized that there is an implied term in every construction contract that the owner or the person for whom the work is being done will not hinder or delay the contractor. Bignold v. King County, 65 Wn.2d 817, 399 P.2d 611 (1965); V.C. Edwards Contracting Co. v. Port of Tacoma, 83 Wn.2d 7, 13, 514 P.2d 1381 (1973); Seattle v. Dyad Constr., Inc., 17 Wn. App. 501, 517, 565 P.2d 423 (1977). Here, the trial court found that the pumping significantly interfered with the contractor's work site. The surface water seepage from the pumping caused the contractor's equipment to mire down in the mud creating problems requiring the contractor to incur additional expense and to perform additional work in order to meet its contract obligations. These problems were not *269 within the contemplation of the parties at the time the bids were made or when the contract was executed. Therefore, the court properly concluded that the City had breached its implied duty under the contract not to hinder the contractor in the performance of its work. Based on this conclusion, the court properly proceeded to determine and award damages to the contractor. The trial court's finding is amply supported by the testimony of Thomas Johnson, then vice-president of the contractor. He was present at the work site during the times in question. His testimony constitutes substantial evidence in support of the trial court's finding, and the finding, in turn, supports its conclusion that the City had breached the contract.

Nor are we persuaded by the City's argument that paragraph 21 of the parties' agreement, which reserves to the City the right to perform other work at or near the work site, 3 expressly authorized the activity which took place here. It is not reasonable to assume that the contractor committed itself to perform this job and at the same time agreed to allow the City to substantially interfere with its work. The provision contemplates those inconveniences encountered whenever two separate groups of workers must operate in proximity to each other. Here, the City's actions resulted in more than an inconvenience. Rather, those actions made it nearly impossible for the contractor to accomplish its work. Accordingly, we hold that paragraph 21 of the agreement did not authorize the City to interfere with the contractor's work in the manner in which it did here. 4

*270 Second, the City asserts that the contract limits the contractor's remedy for this type of breach to an extension of time. The contract incorporates the "Standard Specifications for Municipal Public Works Construction, Washington State Chapter, American Public Works Association." Section 9.02 of the standard specifications states that:

The Contractor shall accept the compensation, as herein provided, in full payment . . . for performing all work contemplated and embraced under the contract; also for loss or damage arising from . . . unforeseen difficulties which may be encountered . . .

(Italics ours.) Section 8.07 of the specifications provides:

Should the Contractor be delayed in the prosecution or completion of the work by the act, neglect, or default of the Owner . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

F.p.h. Construction, Inc. v. Mahmoud Shahrezaei
Court of Appeals of Washington, 2017
Young v. Young
164 Wash. 2d 477 (Washington Supreme Court, 2008)
Hadley v. Maxwell
84 P.3d 286 (Court of Appeals of Washington, 2004)
Lakes v. Vondermehden
70 P.3d 154 (Court of Appeals of Washington, 2003)
Lakes v. von der Mehden
70 P.3d 154 (Court of Appeals of Washington, 2003)
Yates v. Taylor
791 P.2d 924 (Court of Appeals of Washington, 1990)
Riverview Floral, Ltd. v. Watkins
754 P.2d 1055 (Court of Appeals of Washington, 1988)
Eaton v. Engelcke Manufacturing, Inc.
681 P.2d 1312 (Court of Appeals of Washington, 1984)
Murdock-Bryant Construction, Inc. v. Pearson
703 P.2d 1206 (Court of Appeals of Arizona, 1984)
Highland Construction Co. v. Union Pacific Railroad
683 P.2d 1042 (Utah Supreme Court, 1984)
Haner v. Quincy Farm Chemicals, Inc.
627 P.2d 571 (Court of Appeals of Washington, 1981)
Kintz v. Read
626 P.2d 52 (Court of Appeals of Washington, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
588 P.2d 1214, 22 Wash. App. 265, 1978 Wash. App. LEXIS 2775, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lester-n-johnson-co-v-city-of-spokane-washctapp-1978.