V. C. Edwards Contracting Co. v. Port of Tacoma

514 P.2d 1381, 83 Wash. 2d 7, 1973 Wash. LEXIS 594
CourtWashington Supreme Court
DecidedOctober 18, 1973
Docket42686
StatusPublished
Cited by45 cases

This text of 514 P.2d 1381 (V. C. Edwards Contracting Co. v. Port of Tacoma) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
V. C. Edwards Contracting Co. v. Port of Tacoma, 514 P.2d 1381, 83 Wash. 2d 7, 1973 Wash. LEXIS 594 (Wash. 1973).

Opinion

Utter, J.

V. C. Edwards, a contractor, brought suit against the Port of Tacoma for damages allegedly incurred as a result of the port’s acts in relation to a construction contract between the parties. The port impleaded their engineer, McDowell-Wellman Engineering Company, and cross-complained against Edwards. The trial to the court resulted in a verdict in favor of Edwards against the port for $225,595.49, and a dismissal of the third-party defendant, McDowell-Wellman Engineering Company.

The port raises four issues in the appeal. (1) Is the port chargeable for delay of construction suffered by Edwards? (2) If delays were caused by the port, did they constitute a breach of contract which was compensable in money damages? (3) If delays were caused by the port which are compensable by money damages, were such damages properly assessed? (4) Was the trial court correct in dismissing the third-party complaint against McDowell-Well-man Engineering Company? 1

We affirm the trial court on all issues.

**The Port of Tacoma (Port) and V. C. Edwards Contracting Company (Edwards) entered into a contract on December 13, 1967. The contract provided that Edwards would construct a rail service yard and connecting trackage on the Port’s premises, the Tacoma tideflats, and the Port would supply the necessary materials. McDowell-Wellman Engineering Company, independent consulting engineers, had prepared the plans and specifications according to information supplied by the Port. Among other things, the *9 plans called for 1,000 yards of fill to be used as ballast under the track. This fill was to be excavated by the contractor from other portions of the site. After consulting with McDowell-Wellman, the Port issued an addendum (No. 2) to the plans on November 15, 1967 which called the contractor’s attention to five separate places where a sewer project would interfere with this rail project. The bids were opened 1 week later.

Notice to proceed was given to Edwards and construction began on January 18, 1968. For several reasons the work was not completed within the 270 days specified in the contract documents.

Edwards brought this suit against the Port alleging that the delay was caused by, among other things, defective plans, failure of the Port to supply necessary materials and failure of the Port to warn the plaintiff of conflicts with other contractors in the area. The Port entered a general denial, cross-complained for work to be completed and filed a third-party complaint against McDowell-Wellman alleging responsibility for the defective plans.

The trial court found that the Port substantially breached its contract in several respects. The court found the Port’s failure to make decisions within a reasonable time, failure to furnish the promised material, and the Port’s unintentionally misleading addendum No. 2 caused the plaintiff substantial delay in completing the work and was a substantial breach of contract.

The court also found that the contractor had to correct several design errors in the plans and that addendum No. 2 was misleading because the paths of Edwards and the sewer contractor crossed in over 30 places, not in only 5 as specified. The correction of the design errors entailed resurveying and recalculating parts of the plans plus importing an extra 92,000 yards of fill to be used as ballast when the plans called for only 1,000 yards. The misleading addendum and the Port’s failure to supply materials and make decisions required Edwards to construct the railroad piecemeal and to shut down operations entirely for a short time *10 during August 1968. All this required Edwards to perform extra work not contemplated in the contract. The court found the contractor’s cost (minus $18,000 due to overmanning) for this extra work to be reasonable so awarded plaintiff recovery for the extra costs plus profit in quantum meruit.**

The court found, insofar as the port’s case against McDowell-Wellman, that

no act or omission of the third party defendant . . . was responsible for any damages done to the plaintiff . . . That any inadequacies or errors or omissions were such as to be known to the defendant, Port of Tacoma, prior to the commission or omission of the same, and it was, therefore, responsible for such omissions or commissions.

Additional findings were entered indicating, as well, that the port failed to establish any sum in damages or any basis from which damages could be charged against the third-party defendant, McDowell-Wellman.

We consider the oral opinion of the trial court insofar as it is consistent with and amplifies the formal findings of fact. Ferree v. Doric Co., 62 Wn.2d 561, 383 P.2d 900 (1963). In the oral opinion the court indicated it was primarily impressed on the issue of delay with the port’s failure to accurately advise the contractor of the number of times his work would conflict with the sewer contractor. Although addendum No. 2 indicated there were five points of conflict between the two contractors, it failed to mention there were, in addition, some 30 additional points where lateral sewer lines also crossed the right-of-way. Even though this information was available in separate plans to the contractor, the trial court failed to find a duty on his part to examine the separate plans.

The oral opinion also indicates the court believed the port “was not aggressive enough in facing its problem” with regard to the need for additional ballast and that this also contributed to the delay. There is substantial evidence to support the court’s findings.

*11 The port next contends their contract with the general contractor limits his remedy in the event of owner-caused delays to a time extension. Cases typical of those cited for support of this proposition are: Goss v. Northern Pac. Hosp. Ass’n, 50 Wash. 236, 96 P. 1078 (1908); Ericksen v. Edmonds School Dist. 15, 13 Wn.2d 398, 125 P.2d 275 (1942); United States v. Rice, 317 U.S. 61, 87 L. Ed. 53, 63 S. Ct. 120 (1942).

The disputed contract provision in this case reads:

Provided further, that the Contractor shall not be charged with liquidated damages or any excess cost when the delay in completion of the work is due:
(a) . . .
(b) To unforeseeable cause beyond the control and without the fault or negligence of the contractor, including but not restricted to, acts of God, or of the public enemy, acts of the owner, acts of another Contractor in the performance of a contract with the Owner, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and severe weather . . .

This provision refers only to the rights of the owner against the contractor and says nothing concerning the contractor’s rights against the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of: The Harlan D. Douglass Trust
Court of Appeals of Washington, 2026
MG Dyess v. MarkWest
Colorado Court of Appeals, 2025
MarkWest v. Rose
Colorado Court of Appeals, 2025
Estate of Dormaier v. Columbia Basin Anesthesia, PLLC
177 Wash. App. 828 (Court of Appeals of Washington, 2013)
Scoccolo Const., Inc. v. City of Renton
9 P.3d 886 (Court of Appeals of Washington, 2000)
Scoccolo Construction, Inc. v. City of Renton
102 Wash. App. 611 (Court of Appeals of Washington, 2000)
Auburn Mechanical, Inc. v. Lydig Construction, Inc.
951 P.2d 311 (Court of Appeals of Washington, 1998)
Bernsen v. Big Bend Electric
842 P.2d 1047 (Court of Appeals of Washington, 1993)
Bernsen v. Big Bend Electric Cooperative, Inc.
842 P.2d 1047 (Court of Appeals of Washington, 1993)
Puget Sound Power & Light Co. v. Strong
798 P.2d 1162 (Court of Appeals of Washington, 1990)
Hensel Phelps Construction Co. v. King County
787 P.2d 58 (Court of Appeals of Washington, 1990)
Riverview Floral, Ltd. v. Watkins
754 P.2d 1055 (Court of Appeals of Washington, 1988)
Daves v. Nastos
711 P.2d 314 (Washington Supreme Court, 1985)
KWIK-LOK CORPORATION v. Pulse
702 P.2d 1226 (Court of Appeals of Washington, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
514 P.2d 1381, 83 Wash. 2d 7, 1973 Wash. LEXIS 594, Counsel Stack Legal Research, https://law.counselstack.com/opinion/v-c-edwards-contracting-co-v-port-of-tacoma-wash-1973.