Wa State Dept. Of Transportation, V. Seattle Tunnel Partners

Court of Appeals of Washington·Decided June 14, 2022·No. 54425-3·Unpublished

Opinion

Filed

Washington State

Court of Appeals

Division Two

June 14, 2022

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

WASHINGTON STATE DEPARTMENT OF No. 54425-3-II TRANSPORTATION,

Respondent,

v.

SEATTLE TUNNEL PARTNERS, a joint UNPUBLISHED OPINION venture, TUTOR PERINI CORPORATION; DRAGADOS USA, INC.,

Appellants.

CRUSER, A.C.J. – The Washington State Department of Transportation (WSDOT) and Seattle Tunnel Partners (STP) entered into a contract that required STP to construct a tunnel. STP’s boring machine was damaged while it was boring the tunnel, and STP missed the contractually required completion date. WSDOT filed suit, alleging STP breached the contract by failing to meet the contract’s deadline. STP acknowledged it did not meet the deadline but asserted the delay was excusable under the contract. STP argued that its equipment was damaged because it encountered a steel pipe that WSDOT failed to disclose. STP also counterclaimed, alleging WSDOT breached the contract when it did not grant STP additional time and compensation after the equipment was damaged.

Prior to trial, the court granted WSDOT’s motions for partial summary judgment, dismissing the portions of STP’s claim that involved damage to the boring machine and

subcontractor pass-through claims. The court also sanctioned STP for losing evidence relevant to the lawsuit.

During trial, STP objected to the admittance of certain evidence offered by WSDOT and proposed evidence that the trial court excluded. STP also objected to the court’s inclusion of specific jury instructions and proposed instructions the trial court declined to include. The jury ultimately found in WSDOT’s favor on all claims.

On appeal, STP argues the trial court committed multiple errors in its evidentiary rulings and erred in instructing the jury. Additionally, STP contends that the court erred in sanctioning STP for losing evidence.

We affirm.1 FACTS

I. THE PROJECT

A. BACKGROUND The Alaskan Way Viaduct was a critical piece of transportation infrastructure for Seattle.

Following an earthquake in 2001 it was determined that the viaduct needed to be replaced with a tunnel due to damage to the viaduct.

To find an appropriate contractor to construct the tunnel, WSDOT issued a request for proposals. Along with the request, WSDOT included multiple documents, such as the contract terms and technical requirements for the project, a “Geotechnical Baseline Report” (GBR) and a “Geotechnical and Engineering Data Report” (GEDR). The GBR provided an overview of the

1 STP also asks this court, in the event we reverse, to review decisions made on summary judgment that dismissed portions of its claim earlier in the proceeding below. Because we affirm, we decline to consider these assignments of error.

subsurface conditions, and the GEDR provided the data underlying the GBR. The GBR instructed that it (the GBR) “must be read in conjunction with” the GEDR. Ex. 5, at 10.

WSDOT also included “Reference Documents” to provide potential contractors additional background information. However, the Reference Documents, were not considered a part of the contract.2 B. STP BECOMES THE DESIGN-BUILDER FOR THE PROJECT WSDOT selected STP’s proposal. STP acknowledged that “in developing its Proposal, [STP] gave full consideration to the contents of the Geotechnical Baseline Report, Environmental Baseline Report [(EBR)] and the Geotechnical & Environmental Data Report.” Ex. 2, at 24. The parties then signed a contract in which WSDOT agreed to pay STP $1.35 billion to construct the tunnel.

STP was “in complete control of defining how [STP] would proceed with both design and construction on this project.” 7 Verbatim Report of Proceedings (VRP) (Oct. 14, 2019) at 728. STP was required to design and provide all the materials and labor necessary to construct the tunnel. STP hired a third company to design and manufacture a tunnel boring machine (TBM). The TBM was 425 feet long and 57 feet in diameter. The TBM had a cuttinghead design that was essentially a round disc that had spokes that were attached at the rim and met in the center. The spokes had cutting tools on the front and sides. The soil fell into a chamber behind the cuttinghead and a conveyor belt took the soil through the TBM to fall into a muck bin at the back.

2 At trial the jury heard testimony that the Reference Documents were not a part of the contract.

II. THE TBM CUTS INTO TW-2 On December 4, 2013, the TBM ran into Test Well (TW) 2, a pipe that had a “3/8 inch thick, eight-inch diameter, steel well casing.” Clerk’s Papers (CP) at 2164. “When the TBM struck TW-2, a portion of the pipe was pushed up from the ground,” the pipe was cut, and this piece became known as Piece #1. Id. On December 5, 2013, STP also removed two boulders and two pieces of steel (Pieces #2 and #3) from TBM’s conveyor belt. Greg Hauser, STP’s Deputy Project Manager at that time, instructed employees to retain the pieces of steel pipe coming from the TBM because he knew the pipe might be the basis of a claim against WSDOT. On December 11, 2013, STP pulled a 55-foot long piece of TW-2 out of the ground, Piece #4.

On January 2, 2014, STP found another pipe piece, Piece #5, in the TBM’s muck bin, as well as “a collection of small metal fragments” that became known as Piece #6. Id. at 2165. On January 17th, two steel pieces were extracted from the TBM’s spokes, Pieces #7 and #8. Finally, on “January 25, 2014, Piece #9 came off the conveyor belt.” Id.

At some point, Pieces #1, #2, #3, #5, #7, #8, and #9, along with the two boulders, went missing and could not be located. Hauser’s work journal that covered December 2013 through February 2014 also went missing.

In February 2014, the manufacturer of the TBM directed STP to stop mining because the TBM had been damaged and needed to be repaired.

III. DIFFERING SITE CONDITION CLAIM On December 12, 2013, STP submitted to WSDOT an initial notice of a proposed change order, asserting TW-2 was a differing site condition (DSC). The contract defined DSCs as “actual subsurface or latent physical conditions at the Site that are substantially or materially different

from the conditions identified” in the GBR or GEDR. Ex. 3, at 12. STP claimed because the TW- 2 pipe was not properly identified in the GBR or GEDR, the pipe is a DSC and STP was entitled to a time extension. WSDOT rejected STP’s assertion that the pipe was a DSC, noting that TW-2 was identified in the GEDR.

Despite WSDOT’s response, STP still submitted a proposed change order, again asserting that TW-2 was not fully disclosed in the GEDR. WSDOT maintained that TW-2 was not a DSC.

IV. JUDICIAL PROCEEDINGS

On March 9, 2016, WSDOT sued STP because it failed to meet the “substantial completion deadline.” Id. at 7. STP conceded the project was not substantially completed, but claimed that the delay was excusable because it was caused by a DSC, TW-2. STP also counterclaimed, arguing that WSDOT breached the contract when it failed to remove or advise STP of TW-2 and thus STP should have been awarded the additional time and compensation needed to address the problems caused by TW-2. A. SPOLIATION RULINGS Following a discovery request to STP for “[a]ll parts of the TW-2” and “[a]ll boulders removed from the [TBM]”, WSDOT moved for spoliation sanctions, arguing that STP lost or destroyed pieces of the TW-2, the two boulders, and Hauser’s journal. Id. at 1312.

1. Findings of Fact The court found, “On an unknown date, all pieces of the steel pipe except Piece #4 and Piece #6 and the boulders were lost or destroyed. The loss or destruction was not immediately discovered.” Id. at 3245. The court also found that Piece #5 “probably” came from TW-2, but that

it could not determine that with certainty. Id. at 3227. One of Hauser’s journals also went missing and could not be recovered.

Free access — add to your briefcase to read the full text and ask questions with AI

Wa State Dept. Of Transportation, V. Seattle Tunnel Partners, (Wash. Ct. App. 2022).

Wa State Dept. Of Transportation, V. Seattle Tunnel Partners (Wa State Dept. Of Transportation, V. Seattle Tunnel Partners) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Losli v. Foster
222 P.2d 824 (Washington Supreme Court, 1950)
State Ex Rel. Carroll v. Junker
482 P.2d 775 (Washington Supreme Court, 1971)
Pier 67, Inc. v. King County
573 P.2d 2 (Washington Supreme Court, 1977)
Dravo Corp. v. Municipality of Metropolitan Seattle
484 P.2d 399 (Washington Supreme Court, 1971)
Leeper v. Department of Labor & Industries
872 P.2d 507 (Washington Supreme Court, 1994)
Holland v. City of Tacoma
954 P.2d 290 (Court of Appeals of Washington, 1998)
Bignold v. King County
399 P.2d 611 (Washington Supreme Court, 1965)
Modern Builders, Inc. v. Manke
615 P.2d 1332 (Court of Appeals of Washington, 1980)
Gammon v. Clark Equipment Co.
707 P.2d 685 (Washington Supreme Court, 1985)
Henderson v. Tyrrell
910 P.2d 522 (Court of Appeals of Washington, 1996)
Hensel Phelps Construction Co. v. King County
787 P.2d 58 (Court of Appeals of Washington, 1990)
V. C. Edwards Contracting Co. v. Port of Tacoma
514 P.2d 1381 (Washington Supreme Court, 1973)
Basin Paving Co. v. Mike M. Johnson, Inc.
27 P.3d 609 (Court of Appeals of Washington, 2001)
Salas v. Hi-Tech Erectors
230 P.3d 583 (Washington Supreme Court, 2010)
In Re Personal Restraint of Duncan
219 P.3d 666 (Washington Supreme Court, 2009)
Homeworks Const., Inc. v. Wells
138 P.3d 654 (Court of Appeals of Washington, 2006)
Kappelman v. Lutz
217 P.3d 286 (Washington Supreme Court, 2009)
Ripley v. Lanzer
215 P.3d 1020 (Court of Appeals of Washington, 2009)
Gordon Hamilton v. Paula Terrell
358 P.3d 453 (Court of Appeals of Washington, 2015)