Berschauer/Phillips Construction Co. v. Seattle School District No. 1

881 P.2d 986, 124 Wash. 2d 816, 1994 Wash. LEXIS 576
CourtWashington Supreme Court
DecidedOctober 6, 1994
Docket60226-3
StatusPublished
Cited by197 cases

This text of 881 P.2d 986 (Berschauer/Phillips Construction Co. v. Seattle School District No. 1) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berschauer/Phillips Construction Co. v. Seattle School District No. 1, 881 P.2d 986, 124 Wash. 2d 816, 1994 Wash. LEXIS 576 (Wash. 1994).

Opinion

Guy, J.

We granted review to decide whether a general contractor may recover in tort $3.8 million in economic dam-ages for construction delays against an architect, a structural engineer and a project inspector, none of whom were in privity of contract with the general contractor. The Superior Court held the economic loss rule does not allow a general contractor to recover purely economic damages in tort. We affirm.

Background

This lawsuit arises out of a construction project for renovation work and new construction at the Lawton Elementary School in Seattle, Washington. In 1986, the Seattle School District (District), the owner of the construction *819 project, contracted with Harry Lee Cummings, d.b.a. Cummings Associates Architects (Cummings), to design Lawton Elementary. Cummings, in turn, subcontracted with K.M. Maw, d.b.a. K.M. Maw & Associates (Maw), to provide structural engineering services. The District at no time contracted with Maw. The District contracted with Pacific Testing Laboratories, Inc. (PTL) to perform field inspections of the construction work at Lawton Elementary.

In October 1988, Berschauer/Phillips Construction Company (Berschauer/Phillips) submitted a bid to the District to construct Lawton Elementary. Berschauer/Phillips’ estimated construction costs were based on the plans and specifications furnished by the District. The District relied on Cummings and Maw to develop the plqn for Lawton Elementary. In November 1988, Berschauer/Phillips was awarded the general contract.

Berschauer/Phillips completed construction at Lawton Elementary and subsequently filed a lawsuit against the District for breach of contract. Berschauer/Phillips alleges in its complaint that the District’s incomplete and defective plans for constructing Lawton Elementary, together with the District’s failure to manage or participate in construction inspections, breached express and implied contractual obligations to Berschauer/Phillips. Berschauer/Phillips requests $3.8 million in damages. Berschauer/Phillips concedes the damages it seeks are purely economic:

Berschauer/Phillips’ claims are solely and simply for economic loss. Quite simply, Berschauer/Phillips expended more funds than expected and was delayed in its completion of its work, and consequently was damaged monetarily.
This matter involves no claims for injury or death to person, or harm to property.

Clerk’s Papers, at 320.

Berschauer/Phillips amended its original complaint to include tort claims against Cummings, Maw and PTL. Berschauer/Phillips alleges the architectural plans prepared by Cummings and the structural engineering plans prepared by Maw were inaccurate and incomplete. Berschauer/Phil *820 lips alleges PTL was negligent for failing to competently inspect the erection of the structural steel at Lawton Elementary. Berschauer/Phillips asserts these acts of negligence significantly increased the cost to renovate and construct Lawton Elementary.

Berschauer/Phillips settled with the District and both parties signed an agreed order dismissing the District with prejudice. As part of the settlement agreement, the District assigned to Berschauer/Phillips "any and all such claims relating to this project” against Cummings, Maw and PTL. Clerk’s Papers, at 279. Following the settlement agreement, Berschauer/Phillips filed a second amended complaint to assert the assigned claims.

In September 1992, Cummings filed a Motion for Partial Summary Judgment requesting dismissal of Berschauer/ Phillips’ assigned breach of contract claim. Cummings argued the antiassignment provision contained in the contract between the District and Cummings prohibited the District from assigning the breach of contract cause of action to Berschauer/Phillips. Alternatively, Cummings argued the District, and thus Berschauer/Phillips, is prohibited under the doctrine of equitable estoppel from asserting a breach of contract cause of action. The Superior Court granted Cummings’ motion for partial summary judgment on both grounds.

In October 1992, PTL filed a Motion for Partial Summary Judgment requesting dismissal of Berschauer/Phillips’ assigned breach of contract claim. PTL argued public policy prohibited the District from assigning the breach of contract cause of action to Berschauer/Phillips. PTL, similar to Cummings, also argued the District, and thus Berschauer/ Phillips, is prohibited under the doctrine of equitable estoppel from asserting a breach of contract cause of action. The Superior Court denied PTL’s Motion for Partial Summary Judgment on both grounds.

Cummings, Maw and PTL separately filed Motions for Partial Summary Judgment requesting dismissal of Berschauer/Phillips’ direct and assigned causes of action in tort. Cummings, Maw and PTL argued the economic loss rule *821 prevents the recovery in tort of purely economic damages. The Superior Court agreed, and on February 25, 1993, Cummings and Maw were dismissed from the lawsuit and PTL’s Motion for Partial Summary Judgment was granted.

The Superior Court entered a final judgment pursuant to CR 54(b) to allow an immediate appeal. Berschauer/Phillips filed a Notice of Appeal directly with this court requesting review of the Superior Court’s rulings dismissing Cummings and Maw and granting partial summary judgment to PTL. PTL filed a Notice of Cross Appeal requesting review of the Superior Court’s decision denying PTL’s motion for partial summary judgment. We granted review.

Issues

The primary issue is whether the economic loss rule prevents a general contractor from recovering purely economic damages in tort from an architect, an engineer and an inspector, none of whom were in privity of contract with the general contractor. Also at issue is whether a general antiassignment provision in a contract prohibits the assignment of a breach of contract cause of action, whether equitable estoppel enjoins a party from bringing a breach of contract cause of action, and whether public policy forbids the assignment of a contract cause of action.

Analysis

I

The Superior Court dismissed all of Berschauer/Phillips’ direct and assigned tort claims tort claims against Cummings, Maw and PTL. The Superior Court ruled the economic loss rule prevents a general contractor from recovering purely economic damages in tort. We agree and affirm the Superior Court.

The economic loss rule marks the fundamental boundary between the law of contracts, which is designed to enforce expectations created by agreement, and the law of torts, which is designed to protect citizens and their property by imposing a duty of reasonable care on others. Sidney R. Barrett, Jr., Recovery of Economic Loss in Tort for Construction Defects: A Critical Analysis, 40 S.C. L. Rev. 891, 894-95 *822 (1989). The economic loss rule was developed to prevent disproportionate liability and allow parties to allocate risk by contract. Michael D. Lieder, Constructing a New Action for Negligent Infliction of Economic Loss: Building on Cardozo and Coase, 66 Wash. L. Rev. 937, 940-41 (1991).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re The Dependency Of: Z.a.
Court of Appeals of Washington, 2023
Dependency Of: B.b.b.
Court of Appeals of Washington, 2023
Dan Young, V. Todd S. Rayan
533 P.3d 123 (Court of Appeals of Washington, 2023)
Commr. Eric Watness, Apps. v. The City Of Seattle, Res.
481 P.3d 570 (Court of Appeals of Washington, 2021)
Fairlee v. Forcier Aldrich & Associates
Vermont Superior Court, 2019
Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP
155 A.3d 445 (Court of Appeals of Maryland, 2017)
John Doe G v. Department of Corrections
391 P.3d 496 (Court of Appeals of Washington, 2017)
Seattle City Light, Respondent, v. Aaron Swanson, Appellant
373 P.3d 342 (Court of Appeals of Washington, 2016)
Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP
130 A.3d 1024 (Court of Special Appeals of Maryland, 2016)
Dorothy A. Millican v. N.a. Degerstrom Inc.
Court of Appeals of Washington, 2013
Donatelli v. D.R. Strong Consulting Engineers, Inc.
312 P.3d 620 (Washington Supreme Court, 2013)
River House Development, Inc. v. Integrus Architecture
272 P.3d 289 (Court of Appeals of Washington, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
881 P.2d 986, 124 Wash. 2d 816, 1994 Wash. LEXIS 576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berschauerphillips-construction-co-v-seattle-school-district-no-1-wash-1994.