Commercial Painting Company, Inc. v. The Weitz Company, LLC (Dissent)

CourtTennessee Supreme Court
DecidedSeptember 28, 2023
DocketW2019-02089-SC-R11-CV
StatusPublished

This text of Commercial Painting Company, Inc. v. The Weitz Company, LLC (Dissent) (Commercial Painting Company, Inc. v. The Weitz Company, LLC (Dissent)) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Painting Company, Inc. v. The Weitz Company, LLC (Dissent), (Tenn. 2023).

Opinion

09/28/2023 IN THE SUPREME COURT OF TENNESSEE AT JACKSON November 9, 2022 Session

COMMERCIAL PAINTING COMPANY INC. v. THE WEITZ COMPANY LLC ET AL.

Appeal by Permission from the Court of Appeals Chancery Court for Shelby County No. CH-06-1573 JoeDae L. Jenkins, Chancellor ___________________________________

No. W2019-02089-SC-R11-CV ___________________________________

SARAH K. CAMPBELL, J., with whom JEFFREY S. BIVINS, J., joins, dissenting.

The economic-loss doctrine bars recovery in tort for purely economic losses in certain situations. In this case, the Court is asked to apply that doctrine to bar tort claims brought by a subcontractor against a general contractor, where the relationship between the subcontractor and general contractor is governed by a contract. The majority opinion cabins the economic-loss doctrine to products liability cases and refuses to extend it to contracts for services for fear that doing so would require that we also create various exceptions. I respectfully disagree with that holding. The core rationale underlying the economic-loss doctrine—to create a boundary line between tort and contract law to ensure that parties can allocate risks and responsibilities as they see fit—applies equally to cases involving contracts for services. And to the extent that any exceptions to the rule would be needed, their creation would not be nearly as difficult or messy as the majority predicts. I would hold that the economic-loss doctrine applies here and precludes the subcontractor from recovering punitive damages and pre-judgment interest.

I.

This appeal arises from a decades-old dispute between a general contractor—The Weitz Company, LLC—and its drywall subcontractor—Commercial Painting Company, Inc.—during the construction of a retirement community in Shelby County. Weitz is a large commercial contractor that, at the time of the project, was the largest builder of continuing- care retirement communities in the country. Commercial Painting had a staff of thirty-five employees.

In 2004, Weitz and Commercial Painting executed a standard form subcontract agreement related to the Shelby County project. Commercial Painting’s president reviewed the subcontract terms in detail, initialing each page, and requested a number of changes to certain parts of the subcontract, including the scope of work provisions. The agreement provided that Commercial Painting would be paid $3.22 million for proper performance.

The subcontract incorporated the plans and specifications for the project and addressed in detail the scope of Commercial Painting’s work, the project schedule, available remedies, attorney’s fees, and myriad other items. Of particular relevance here, the subcontract provided that Commercial Painting “shall be entitled to an extension of the Subcontract Time and/or reimbursement for delay damages only to the extent that [Weitz] actually receives an extension of time and/or reimbursement for delay damages under the Prime Contract for events pertaining to [Commercial Painting’s] Work.” With the exception of those pass-through rights, Commercial Painting “waive[d] and release[d] [Weitz] from any and all [c]laims for such delay damages, including without limitation [c]laims attributable to breach of contract or tort.”

In a provision titled “Contract Terms Control,” the subcontract further stated that Weitz would “[i]n no event . . . be obligated to pay [Commercial Painting] any anticipatory profit or indirect, special or consequential damages, however caused” and made clear that Commercial Painting was “waiv[ing] all such [c]laims.” In the same provision, Commercial Painting “specifically agree[d] that it shall not be entitled to assert . . . any [c]laims in quantum meruit, interest on late payments, or any other measure of damages other than as specifically provided” in certain other provisions of the subcontract.

The subcontract detailed whether and when Weitz and Commercial Painting could modify the scope of Commercial Painting’s work or the amounts owed under the subcontract. For example, the subcontract expressly permitted Weitz to charge Commercial Painting for the cost of any “additional services . . . required . . . to assist [Commercial Painting] in performing its obligations” under the subcontract, including “supplemental manpower.” And it entitled Commercial Painting to payment for additional work only as “properly authorized” by Weitz.

As for the schedule, the subcontract obligated Commercial Painting to “meet or better the durations established in [Weitz’s] [s]chedule” but also provided that the schedule would be “updated periodically to reflect actual job progress.” Commercial Painting was required to “provide sufficient crews, materials and equipment to maintain or improve upon [Weitz’s] [s]chedule.” Weitz, meanwhile, had “the right to suspend [Commercial Painting’s] performance from time to time, or to reschedule or re-sequence [its] [w]ork.”

Weitz was already more than eight months behind schedule when the subcontract was executed. Although Weitz was aware of the delay, it did not share that information with Commercial Painting before entering the subcontract and instead included an outdated construction schedule as an exhibit to the subcontract.

-2- Trouble began soon after Commercial Painting started work on the project. Because of pre-existing delays and slow progress by other subcontractors, Commercial Painting struggled to comply with the performance schedule set by Weitz. Weitz hired additional workers to supplement Commercial Painting’s work. Weitz also issued “notices to comply” to Commercial Painting, claiming that Commercial Painting was failing to perform a “Level 4” drywall finish even though the subcontract required only a “Level 3” finish. By the end of the project, Weitz had withheld more than half a million dollars in payments to Commercial Painting for “supplementation charges and supervision charges.” And it refused Commercial Painting’s requests for additional compensation related to extra work necessitated by the poor performance of other subcontractors. The project was not completed until February 2006.

Commercial Painting sued Weitz and various other defendants in late 2004.1 The operative complaint for purposes of this appeal—Commercial Painting’s second amended complaint—asserted breach of contract and tort claims, including negligent and intentional misrepresentation and unjust enrichment claims against Weitz.2 Commercial Painting alleged that it had fully performed the subcontract and that Weitz had breached the agreement by failing to pay in full. It further alleged that Weitz had made material misrepresentations by failing to inform Commercial Painting that the project schedule would be compressed or that it would supplement Commercial Painting’s drywall work with other subcontractors. Commercial Painting sought compensatory damages of nearly $2 million plus pre-judgment interest and attorney’s fees, along with punitive damages of $200 million.

Weitz counterclaimed and alleged that Commercial Painting had breached the subcontract by delaying the project and performing defective work. Weitz sought damages of $500,000, interest, and attorney’s fees.

A jury trial was held in September and October 2018. As relevant here, the jury returned verdicts in favor of Commercial Painting on its breach of contract, intentional misrepresentation, and unjust enrichment claims against Weitz and further found that Commercial Painting was entitled to pre-judgment interest and punitive damages. The trial court approved the verdict and awarded Commercial Painting $1,729,122 in compensatory

1 Weitz’s sureties—Federal Insurance Company and St. Paul Fire & Marine Insurance Company— were among those defendants. They are also appellants in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gunkel v. Renovations, Inc.
822 N.E.2d 150 (Indiana Supreme Court, 2005)
Brian & Christie, Inc. v. Leishman Electric, Inc.
244 P.3d 166 (Idaho Supreme Court, 2010)
Lincoln General Insurance Co. v. Detroit Diesel Corp.
293 S.W.3d 487 (Tennessee Supreme Court, 2009)
Filak v. George
594 S.E.2d 610 (Supreme Court of Virginia, 2004)
Ramerth v. Hart
983 P.2d 848 (Idaho Supreme Court, 1999)
City Express, Inc. v. Express Partners
959 P.2d 836 (Hawaii Supreme Court, 1998)
McCarthy Well Co. v. St. Peter Creamery, Inc.
410 N.W.2d 312 (Supreme Court of Minnesota, 1987)
Seely v. White Motor Co.
403 P.2d 145 (California Supreme Court, 1965)
American Towers Owners Ass'n v. CCI Mechanical, Inc.
930 P.2d 1182 (Utah Supreme Court, 1996)
Grams v. Milk Products, Inc.
2005 WI 112 (Wisconsin Supreme Court, 2005)
Linden v. Cascade Stone Company, Inc.
2005 WI 113 (Wisconsin Supreme Court, 2005)
Ritter v. Custom Chemicides, Inc.
912 S.W.2d 128 (Tennessee Supreme Court, 1995)
Indemnity Ins. Co. v. American Aviation
891 So. 2d 532 (Supreme Court of Florida, 2004)
Moransais v. Heathman
744 So. 2d 973 (Supreme Court of Florida, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Commercial Painting Company, Inc. v. The Weitz Company, LLC (Dissent), Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-painting-company-inc-v-the-weitz-company-llc-dissent-tenn-2023.