American Towers Owners Ass'n v. CCI Mechanical, Inc.

930 P.2d 1182, 306 Utah Adv. Rep. 3, 1996 Utah LEXIS 109, 1996 WL 729563
CourtUtah Supreme Court
DecidedDecember 20, 1996
Docket950136
StatusPublished
Cited by112 cases

This text of 930 P.2d 1182 (American Towers Owners Ass'n v. CCI Mechanical, Inc.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Towers Owners Ass'n v. CCI Mechanical, Inc., 930 P.2d 1182, 306 Utah Adv. Rep. 3, 1996 Utah LEXIS 109, 1996 WL 729563 (Utah 1996).

Opinion

HOWE, Justice:

Plaintiff American Towers Owners Association, Inc. (the Association), brought this action against numerous defendants, alleging design and construction defects in the plumbing and mechanical systems of a large condominium complex. The district court granted defendants’ motions for summary judgment, and the Association appeals.

BACKGROUND

In reviewing this grant of summary judgment, we view the facts in the light most favorable to the Association and recite them accordingly. The American Towers complex consists of two 26-stoiy towers containing 357 residential units and some commercial space. Architectural services for the complex commenced in 1980, and a general contractor was hired in 1981. The complex was substantially completed in July 1983.

Defendants were all involved in the complex’s design, development, and construction. CCI Mechanical, Inc. (CCI), was the complex’s mechanical subcontractor and engineer and was responsible for the planning and installation of the culinary water, sewer, heating, cooling, and fire protection systems. Christiansen Brothers, Inc., was the general contractor. American Towers, Inc., was the original developer and was one of the original borrowers on the complex’s construction loan. Trossen Wright Architects, P.A., Donald A. Wright, and Duane A. Trossen were the architects. Block 58 Associates, Block Associates, Inc., Dee W. Christiansen, West Temple Associates, CL Management, Ltd., Howard S. Clark, the late George A. Learning, and MB Management, Inc., were all involved in the development and/or financing of the complex. 1 Daw Incorporated was the dry wall subcontractor. Hunter Insulation, Inc., was the insulation subcontractor. First Security Bank of Utah, N.A., and its wholly owned subsidiary REH Inc., foreclosed its security interest in 1984 and became a successor developer of the complex. 2

The Association’s second amended complaint 3 sought damages for unjust enrichment, breach of contract/warranty (third-party beneficiary), negligence, and breach of implied warranty. 4 The allegations generally concern problems with the complex’s plumbing and mechanical systems. For example, instead of using premanufactured T-shaped joints at the ninety degree plumbing connections, builders fabricated the joints on site. These joints were allegedly incorrectly made, resulting in thin walls that are inherently weaker than standard premanufactured joints. These weak joints began to progressively spring leaks in late 1990 as the complex reached full occupancy. Other problems include (1) piping systems that were installed without adequate provision for expansion and contraction and without sufficient guides and anchors, resulting in pipe breaks and leaks, (2) pipes that are too small in some locations, resulting in pressure loss and failures, (3) domestic water system pressure that exceeds the code limit at some fixtures, and (4) lack of outside air vents and exhaust systems.

First Security filed a motion to dismiss the complaint which the district court treated as *1185 a motion for summary judgment. The court granted the motion, concluding that First Security entered into a May 1989 release with the Association that covered the claims asserted in the complaint and that the release was not subject to rescission on the basis of mutual mistake.

Most of the remaining defendants moved for summary judgment beginning in May 1994. In response, the Association moved for a continuance under rule 56(f) of the Utah Rules of Civil Procedure, on which motion the court apparently did not rule. In July 1994, the Association filed a second rule 56(f) motion.

The district court conducted a hearing in August 1994, denied the Association’s rule 56(f) motion, and granted all of the summary judgment motions, concluding that (1) the unjust enrichment claim fails because the subject matter of the claim was preempted by the existence of express contracts and because the Association conferred no benefit upon defendants, (2) the third-party beneficiary claim fails because the Association was not an intended beneficiary, (3) the negligence claim fails because the alleged damages are for economic loss, not for injury to persons or other property, (4) the implied warranty of habitability claim fails because Utah does not recognize such a claim in this circumstance, (5) all of the Association’s claims accrued more than six years prior to the commencement of this action and are time-barred, and (6) the discovery rule does not apply to toll the running of the statute of limitations. 5

Following the court’s decision, Hunter Insulation, Inc., and American Towers, Inc., moved for summary judgment. The court granted the motions on the same basis as the prior motions.

The sole remaining defendant, Block Associates, Inc., did not respond to the second amended complaint. Consequently, the Association moved for entry of default judgment. The district court directed entry of Block Associates’ default but denied the request for a money judgment, holding that granting one would be inconsistent with the court’s prior holdings in the case.

On review of a grant of summary judgment, we will affirm only if there is no genuine dispute of material fact and the moving party is entitled to judgment as a matter of law. Andreini v. Hultgren, 860 P.2d 916, 918 (Utah 1993).

FIRST SECURITY & REH

We first address the district court’s grant of summary judgment to First Security and its wholly owned subsidiary REH (collectively, “First Security”) on a basis unique from the other defendants. The court held that (1) First Security entered into a release with the Association that covered the claims asserted in the complaint, and (2) the release is not subject to rescission on the basis of mutual mistake. These are questions of law that we will review for correctness.

In 1983, First Security provided financing for the complex under a participation agreement with American Savings, the original lender on American Towers. In 1984, First Security foreclosed its security interest and took ownership of American Towers. In 1987, the Association sued First Security, claiming that it owed unpaid assessments on the units it owned. In addition, some owners in the complex who were also members of the association filed another action against First Security.

*1186 In May 1989, the Association and First Security entered into a “Settlement Agreement and Mutual Release of Claims” (the Release). The Release states that First Security denied liability for the past due assessments and had its own claims and offsets against the Association. The Release also provides:

WHEREAS, the Association did not assert other claims in [its action], but is willing to release all other claims against Lenders it may have

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
930 P.2d 1182, 306 Utah Adv. Rep. 3, 1996 Utah LEXIS 109, 1996 WL 729563, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-towers-owners-assn-v-cci-mechanical-inc-utah-1996.