Paul Mueller Co. v. Cache Valley Dairy Ass'n

657 P.2d 1279, 1982 Utah LEXIS 1129
CourtUtah Supreme Court
DecidedDecember 6, 1982
Docket17743, 17745
StatusPublished
Cited by27 cases

This text of 657 P.2d 1279 (Paul Mueller Co. v. Cache Valley Dairy Ass'n) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paul Mueller Co. v. Cache Valley Dairy Ass'n, 657 P.2d 1279, 1982 Utah LEXIS 1129 (Utah 1982).

Opinion

HALL, Chief Justice:

Appellants Paul Mueller Company (Mueller) and Dahle Construction Company (Dahle) appeal from the trial court’s refusal to enforce their claimed mechanic’s liens *1282 against respondent Cache Valley Dairy Association on whey drying equipment possessed by the latter. Respondent, in turn, cross-appeals from that court’s denial of its counterclaim relating to defective manufacture and installation of the equipment by appellants. In addition, appellants and respondent all contest the amount of attorney fees awarded by the court to respondent.

I. Appellants’ Claim

In 1978, respondent contracted with Maxum Corporation (Maxum), a Delaware firm, for the installation of a whey drying system on respondent’s premises. Maxum subcontracted with appellant Mueller to construct four large drying cylinders, a drying chamber and other parts of the system and with appellant Dahle to assemble and install the system. In order to house the whey drying equipment, respondent engaged a separate contractor to pour a cement foundation and to assemble a four-story prefabricated metal building thereon.

Following the manufacture by Mueller of the parts ordered by Maxum, Dahle assembled the large drying chamber and cylinders and moved them into the building. Dahle also constructed a manlift and walkways within the building and installed various ducts, frameworks and other equipment in order to connect parts of the system to each other and to the building.

After respondent had paid Maxum in full for the drying system, Maxum declared bankruptcy, leaving unpaid balances owing to both Mueller and Dahle. Mueller and Dahle each filed a notice of lien upon the whey drying equipment under the provisions of U.C.A., 1953, §§ 38-1-3 and 38-1-4. The former statute states:

Contractors, subcontractors and all persons performing any services or furnishing or renting any materials or equipment used in the construction, alteration, or improvement of any building or structure or improvement to any premises in any manner ... shall have a lien upon the property upon or concerning which they have rendered service, performed labor or furnished or rented materials, or equipment for the value of the service rendered, labor performed or materials or equipment furnished or rented by each respectively, whether at the instance of the owner or any other person acting by his authority as agent, contractor or otherwise.

Appellants then filed this action against respondent to foreclose the alleged liens, claiming also that respondent should bear liability for the debts of its contractor under the provisions of U.C.A., 1953, §§ 14-2-1 and 1A-2-2. Those statutes provide, respectively, as follows:

The owner of any interest in land entering into a contract, involving $2,000 or more, for the construction, addition to, or alteration or repair of, any building, structure or improvement upon land shall, before any such work is commenced, obtain from the contractor a bond in a sum equal to the contract price, with good and sufficient sureties, conditioned for the faithful performance of the contract and prompt payment for material furnished and labor performed under the contract. Such bond shall run to the owner and to all other persons as their interest may appear; and any person who has furnished materials or performed labor for or upon any such building, structure or improvement, payment for which has not been made, shall have a direct right of action against the sureties upon such bond for the reasonable value of the materials furnished or labor performed, not exceeding, however, in any case the prices agreed upon .... [Emphasis added.]
Any person subject to the provisions of this chapter, who shall fail to obtain such good and sufficient bond, or to exhibit the same, as herein required, shall be personally liable to all persons who have furnished materials or performed labor under the contract for the reasonable value of such materials furnished or labor performed, not exceeding, however, in any case the prices agreed upon.

*1283 The trial court found that the equipment manufactured by Mueller and much of the equipment installed by Dahle constituted personal property rather than improvements to realty as required by §§ 14-2-1 and 38-1-4, and that appellants therefore held no statutory liens upon the equipment. Although the court found the manlift and walkways constructed by Dahle to be fixtures to which a statutory lien might apply, the court refused to recognize such a lien on the part of Dahle, finding no substantial evidence to indicate what percentage of Maxum’s debt to Dahle represented work on the latter items and what percentage represented assembly of the items found to be personal property. Appellants contend that the evidence clearly preponderates against these findings, requiring instead a finding that all of the whey drying equipment constituted “structure[s] or improvement[s] upon land” subject to the statutory liens.

In distinguishing between real and personal property for statutory lien purposes, this Court has adopted a tripartite test, giving consideration to the following factors:

(1) [the] manner in which the item is attached or annexed to realty; (2) whether the item is adaptable to the particular use of the realty; and (3) the intention of the annexor to make an item a permanent part of the realty. 1

The trial court referred to the above three factors in determining the lien status of respondent’s equipment, finding:

After the examination [of] the manner in which the equipment was attached, and the particular use of the machinery and the intent of the parties, the Court determines the said equipment to be personalty ....

We therefore review the evidence presented concerning the elements of annexation, adaptation and intent in order to determine whether such evidence supports the trial court’s findings. Appellants and respondent agree that if, and only if, the evidence “clearly preponderates” against the court’s findings, this Court must overrule those findings. 2

A. Annexation

The evidence shows that the whey drying equipment was attached to the building by means of ducts, wiring and welding and that some equipment was bolted into the cement floor. However, mere physical attachment to a building does not necessarily confer fixture status upon what would otherwise constitute personal .property. 3 In the present case, respondent presented evidence to show that most of the ducts and wires connecting equipment to the metal building consisted of detachable sections designed for easy removal and that respondent requested the attachment of lifting lugs to the larger pieces of equipment so that they could be more easily lifted and transported from the building. The trial court, having personally inspected the whey drying equipment in the presence of counsel, found that the bolts securing machinery to the floor could be disconnected easily and that equipment could be removed without damage to the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beesley v. Brinton
D. Utah, 2025
Xlear v. Focus Nutrition
Tenth Circuit, 2018
Xlear, Inc. v. Focus Nutrition, LLC
893 F.3d 1227 (Tenth Circuit, 2018)
Cache County v. Beus
2005 UT App 204 (Court of Appeals of Utah, 2005)
Air Products & Chemicals, Inc. v. Eaton Metal Products Co.
272 F. Supp. 2d 482 (E.D. Pennsylvania, 2003)
American Towers Owners Ass'n v. CCI Mechanical, Inc.
930 P.2d 1182 (Utah Supreme Court, 1996)
Richard Barton Enterprises, Inc. v. Tsern
928 P.2d 368 (Utah Supreme Court, 1996)
Salmon v. Davis County
916 P.2d 890 (Utah Supreme Court, 1996)
Crossroads Plaza Ass'n v. Pratt
912 P.2d 961 (Utah Supreme Court, 1996)
Salt Lake City Corp. v. Kasler Corp.
855 F. Supp. 1560 (D. Utah, 1994)
Cottonwood Mall Co. v. Sine
830 P.2d 266 (Utah Supreme Court, 1992)
Robertson v. Gem Insurance Co.
828 P.2d 496 (Court of Appeals of Utah, 1992)
John Wagner Associates v. Hercules, Inc.
797 P.2d 1123 (Court of Appeals of Utah, 1990)
Commerce Financial v. Markwest Corp.
806 P.2d 200 (Court of Appeals of Utah, 1990)
Ringwood v. Foreign Auto Works, Inc.
786 P.2d 1350 (Court of Appeals of Utah, 1990)
Taylor v. Estate of Taylor
770 P.2d 163 (Court of Appeals of Utah, 1989)
Dixie State Bank v. Bracken
764 P.2d 985 (Utah Supreme Court, 1988)
Barnes v. Wood
750 P.2d 1226 (Court of Appeals of Utah, 1988)
Cabrera v. Cottrell
694 P.2d 622 (Utah Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
657 P.2d 1279, 1982 Utah LEXIS 1129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paul-mueller-co-v-cache-valley-dairy-assn-utah-1982.