Salt Lake City Corp. v. Kasler Corp.

855 F. Supp. 1560, 24 U.C.C. Rep. Serv. 2d (West) 518, 1994 U.S. Dist. LEXIS 8514, 1994 WL 282602
District Court, D. Utah·Decided June 8, 1994·No. Civ. 90-C-382G·Published·Cited by 13 cases

Opinion

AMENDED MEMORANDUM DECISION AND ORDER RE: SUMMARY JUDGMENT

J. THOMAS GREENE, District Judge.

Introduction

This matter came before the Court on third-party defendant Monroe’s motion for summary judgment and third-party plaintiff Kasler’s constitutional challenge to Utah’s Uniform Commercial Code statute of repose, Utah Code Ann. (1990) § 70A-2-725. Third-party plaintiff, Kasler, was represented by Lynn Larsen and Jack Reed. Third-party defendant Monroe was represented by George Naegle, Michael Drake and Nelson L. Hayes. Pursuant to 28 U.S.C. § 2403, which declares that the state shall be allowed to intervene on a constitutional challenge to any statute “affecting the public interest,” Utah’s Attorney General was notified of this constitutional challenge and provided the opportunity to intervene. The State of Utah did not intervene. The parties filed extensive memoranda and supporting materials, after which the Court heard oral argument and took the matter under advisement. On January 10, 1994, this Court issued its Memorandum Decision and Order. Salt Lake City Corp. v. Kasler Corp., 842 F.Supp. 1380 (D.Utah 1994). Thereafter, defendants timely filed a Motion for Reconsideration and the parties submitted further memoranda and documentation. The matter was discussed at an informal hearing on May 27, 1994, and was again taken under advisemént. Now being fully advised, the Court renders its Amended Memorandum Decision and Order.

Factual Background

Salt Lake City Airport Authority (“Airport Authority”) undertook construction of an apron and connecting taxiway for Concourse D at the Salt Lake City International Airport. Kasler Corporation (“Kasler”) was hired in August of 1983 as the general contractor for the project. In September of 1983, Kasler entered into two purchase agreements (the “Agreements”) with Monroe, Inc. (“Monroe”). Pursuant to the Agreements, Monroe agreed to provide coarse and fine aggregates for the project and completed its obligations at least by December of 1984. 1

Shortly after completion of the project, the concrete began spalling. 2 The Airport Authority notified Kasler that the surface had begun deteriorating by letter dated May 21, 1985. 3 In November 1985, a Kasler representative visited the Salt Lake Airport, and concluded that the problem was localized and very minor.

In May 1988, a different Kasler representative, Bob Varshay, inspected the site. No action was taken to resolve the problem. By letter dated January 22, 1990, Salt Lake City, on behalf of the Airport Authority, informed Kasler that it intended to pursue legal action against Kasler. On June 14, 1990, Salt Lake City filed a complaint against Kasler, alleging breach of contract, breach of guarantee, breach of implied warranties, and negligence. Immediately thereafter, Kasler filed a third-party complaint against Monroe, asserting various contract and tort claims. On May 21, 1991, Salt Lake City settled its claims against Kasler for $1.5 million. Kasler received an assignment of all of Salt Lake City’s rights against Monroe, including rights to damages, contribution and indemnity as part of the settlement.

Kasler’s third-party complaint is the genesis of Monroe’s summary judgment motion. Kasler alleged breach of contract, breach of express and implied warranties, strict liability, negligence, negligent misrepresentation, products liability, breach of indemnification agreement and contribution. Kasler alleges that Monroe breached the contract by pro *1564 viding aggregate that did not meet the specifications of the contract. Monroe claims that the statute of limitations bars the action and that Kasler and Salt Lake City knowingly accepted out-of-specification materials.

Standard op Review

Summary judgment is appropriate if “the pleadings, depositions, answers to interrogatories and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56. In considering summary judgment, the judge does not weigh the evidence and determine the truth of the matter, but rather determines whether there is a genuine issue for trial. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249, 106 S.Ct. 2505, 2510-11, 91 L.Ed.2d 202 (1986).

Analysis

I. THE UNIFORM COMMERCIAL CODE CONTROLS THIS DISPUTE.

This Court determines as a matter of law that the Uniform Commercial Code (“UCC”) controls this litigation. Kasler argues that the UCC does not apply because Kasler is not a merchant dealing in goods for UCC purposes. Monroe counters that Kasler is a merchant and the subject of this dispute is a contract for goods.

Pursuant to Section 70A-2-104(1) of the Utah Code, a merchant is:

a person who deals in goods of the kind or otherwise by his occupation holds himself out as having knowledge or skill peculiar to the practices or goods involved in the transaction;

Utah Code Ann. § 70A-2-104(1) (1990). Kasler, a general engineering contractor, is in the business of making concrete and constructing concrete objects. Kasler’s occupation requires it to deal in aggregates and requires skill peculiar to the use and particulars of such aggregates. Monroe is in the business of providing the aggregates neeessary to make concrete. It is undisputed that both parties hold themselves out as experts in their respective professions. This Court rules that Kasler and Monroe are merchants for UCC purposes.

Kasler also argues that the materials provided under the Agreements are not “goods” for purposes of the UCC, and that the UCC does not govern this dispute. The Agreements obligated Monroe to supply aggregate subbase, crushed aggregate base, pcc and leb aggregate, one-inch concrete gravel, and concrete sand to Kasler for the purpose of mixing cement. 4 Agreements ¶ 2. Under the UCC, a sale of “goods” includes:

a contract for the sale of minerals or the like ... to be removed from realty is a contract for the sale of goods within this chapter if they are to be severed by the seller____

Id. § 70A-2-107. The materials supplied under the Agreements clearly fit within this definition. See City of Salem v. Clearwater Construction Co., 84 Or.App. 674, 735 P.2d 373 (1987) (a contract for sand is a sale of goods governed by the UCC). A contract to provide sand, gravel and aggregate is a contract for the sale of goods. Kasler and Monroc are merchants who contracted for the sale of goods.

Free access — add to your briefcase to read the full text and ask questions with AI

Salt Lake City Corp. v. Kasler Corp., 855 F. Supp. 1560, 24 U.C.C. Rep. Serv. 2d (West) 518, 1994 U.S. Dist. LEXIS 8514, 1994 WL 282602 (D. Utah 1994).

855 F. Supp. 1560 (Salt Lake City Corp. v. Kasler Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hanks v. Anderson
D. Utah, 2024
Johns v. CR Bard
S.D. Ohio, 2020
Egbert v. NISSAN MOTOR CO., LTD.
2010 UT 8 (Utah Supreme Court, 2010)
Hunter v. Woodburn Fertilizer, Inc.
144 P.3d 970 (Court of Appeals of Oregon, 2006)
Condos v. Musculoskeletal Transplant Foundation
208 F. Supp. 2d 1226 (D. Utah, 2002)
Joswick v. Chesapeake Mobile Homes, Inc.
765 A.2d 90 (Court of Appeals of Maryland, 2001)
Joswick v. Chesapeake Mobile Homes, Inc.
747 A.2d 214 (Court of Special Appeals of Maryland, 2000)
Straub v. Fisher and Paykel Health Care
1999 UT 102 (Utah Supreme Court, 1999)
American Towers Owners Ass'n v. CCI Mechanical, Inc.
930 P.2d 1182 (Utah Supreme Court, 1996)