Brigham Young University v. Paulsen Construction Co.

744 P.2d 1370, 42 Educ. L. Rep. 982, 68 Utah Adv. Rep. 5, 1987 Utah LEXIS 800
CourtUtah Supreme Court
DecidedOctober 27, 1987
Docket19638
StatusPublished
Cited by37 cases

This text of 744 P.2d 1370 (Brigham Young University v. Paulsen Construction Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brigham Young University v. Paulsen Construction Co., 744 P.2d 1370, 42 Educ. L. Rep. 982, 68 Utah Adv. Rep. 5, 1987 Utah LEXIS 800 (Utah 1987).

Opinions

ZIMMERMAN, Justice:

This is an appeal from a judgment on the pleadings entered in favor of Paulsen Construction Company (“Paulsen”) and Chris-tiansen Brothers & Associates, Inc. (“Chris-tiansen”), against Brigham Young University (“BYU”). The district court held that BYU’s claims against the two construction contractors are barred because they were not brought within the three-year period of limitation imposed by section 78-12-26(1) of the Code. Before this Court, BYU contends that the six-year limitation period of section 78-12-23(2) should apply and that the statute did not begin to run on BYU’s claims until after it discovered that the construction supervised by Paulsen and Christiansen was defective. We agree that the six-year statute applies. However, on the facts of this case, we decline to hold that the statute was tolled pending BYU’s discovery of the defective construction. We reverse as to the claims against Chris-tiansen and affirm as to the claims against Paulsen.

In 1973, BYU had plans prepared for a facility presently known as the Missionary Training Center. It was to be constructed in two separate phases. In July of 1974, BYU chose Paulsen to act as the general contractor for Phase I. That phase was completed on November 1, 1976. BYU then selected Christiansen to act as general contractor for Phase II, which was completed on October 31, 1978.

In July of 1978, BYU first discovered that underground pipes serving Phase I were leaking. By May of 1979, the leakage was so severe that BYU excavated and inspected the pipes of both phases. The hot water pipes were badly corroded and were replaced immediately.

BYU commenced this action on February 1, 1983. It alleged that the corrosion resulted from the negligent failure of Paul-sen and Christiansen to perform their supervisory responsibilities under their contracts with BYU. Specifically, BYU [1372]*1372claimed that Paulsen and Christiansen negligently allowed subcontractors to install pipe insulation material that did not conform to the project construction specifications. BYU sought to recover the cost of replacing the pipes.

The defendants moved to dismiss, alleging that the statute of limitations had run on the claims. The district court held that the six-year limitation period of section 78-12-23(2), which applies to “action[s] upon any contract, obligation, or liability founded upon an instrument in writing,” was not applicable. Utah Code Ann. § 78-12-23(2) (1977). Instead, the court found that BYU’s claims fell within the operation of section 78-12-26’s three-year limitation period, which applies to “action[s] for waste, or trespass upon or injury to real property.” Utah Code Ann. § 78-12-26(1) (1977). Because BYU filed its action more than three years after each contractor had completed its work, BYU’s action was barred.

In Bracklein v. Realty Insurance Co., 95 Utah 490, 500, 80 P.2d 471, 476 (1938), this Court set forth the test for determining whether the six-year period of section 78-12-23(2) applies to a particular ease: “[I]f the fact of liability arises or is assumed or imposed from the instrument itself, or its recitals, the liability is founded upon an instrument in writing.” The present case appears to satisfy the Brack-lein standard. BYU asserts liability based entirely on written instruments. It alleges that Paulsen and Christiansen “were each negligent in carrying out the supervisory responsibilities as general contractors as defined under their individual agreements” by allowing subcontractors to install “an insulation substance materially different from the insulation specified in the construction documents." Complaint at 4-5 (emphasis added). Absent the contractual obligations of Paulsen and Chris-tiansen to BYU, the two contractors would have had no obligation to supervise construction of the Missionary Training Center. Only the alleged breach of their contractual duties gives BYU any basis for asserting that they are liable for the cost of replacing the pipes.1 BYU’s claims are, therefore, actions upon contracts founded on instruments in writing and, as such, clearly fall within the scope of the six-year period of limitation in section 78-12-23.

The district court, in rejecting this line of reasoning and holding that the three-year period of section 78-12-26(1) applied to BYU’s claims, reasoned that even if BYU’s cause of action arose out of a breach of contract, the harm suffered was an injury to property. The court then concluded that section 78-12-26(1) governs any action for harm to property, regardless of the legal theory underlying the action.

It is possible to arrive at the district court’s conclusion from a literal reading of the language of section 78-12-26(1), which states that it. applies to “[a]n action for ... injury to real property.” However, a review of the historical development of section 78-12-26(1) indicates that it has always applied to actions grounded in tort,2 [1373]*1373whereas section 78-12-23(2) has always been directed to actions based on a breach-of-contract theory. In fact, this matter has apparently been so well understood that we have found only one case that has even obliquely dealt with the issue. In Thomas E. Jeremy Estate v. Salt Lake City, 87 Utah 370, 374, 49 P.2d 405, 407 (1935), we applied the almost identical predecessor of section 78-12-23(2) to a case in which a breach of contract had caused property damage. The case at bar presents a similar fact situation involving a breach of contract resulting in property damage, and we see no reason to retreat from the approach we took in Jeremy Estate. Therefore, we decline to follow the district court’s reading of the statute, and we hold that the six-year period provided in section 78-12-23(2) governs the claims brought by BYU in the present case.

The authorities on which the district court relied are either inapposite or unpersuasive. The court cited Holm v. B & M Service, Inc., 661 P.2d 951 (Utah 1983), as authority for the proposition that section 78-12-26(1) applies to all actions for injury to real property. A reading of that case makes it evident that the Court was dealing with tortious injuries to property, not injuries to property resulting from a breach of contract. The Court held that the three-year period of limitation applies to causes of action for tortious injury to property, regardless of whether the injury was negligently or intentionally caused. Holm is simply inapposite here.

Similarly, Utah Poultry & Farmer’s Cooperative v. Utah Ice & Storage Co., 187 F.2d 652, 654 (10th Cir.1951), involved tor-tious injury to property. “[W]e are convinced beyond doubt that the action or claim here is in the nature of, or sounds in tort....” In dicta, the court expressed its view that section 78-12-26(2) was not limited to tort actions, but appeared to apply to all actions for taking, detaining, or injuring personal property regardless of the form of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosser v. Elite Craft Homes
2026 UT App 16 (Court of Appeals of Utah, 2026)
Lilley v. JP Morgan Chase
2013 UT App 285 (Court of Appeals of Utah, 2013)
Russell Packard Development, Inc. v. Carson
2005 UT 14 (Utah Supreme Court, 2005)
Russell/Packard Development, Inc. v. Carson
2003 UT App 316 (Court of Appeals of Utah, 2003)
MacRis v. Sculptured Software, Inc.
2001 UT 43 (Utah Supreme Court, 2001)
CIG Exploration, Inc. v. State
2001 UT 37 (Utah Supreme Court, 2001)
Vigos v. Mountainland Builders, Inc.
2000 UT 2 (Utah Supreme Court, 2000)
Estes v. Tibbs
1999 UT 52 (Utah Supreme Court, 1999)
Williams v. Howard
970 P.2d 1282 (Utah Supreme Court, 1998)
Cathco, Inc. v. Valentiner Crane Brunjes Onyon Architects
944 P.2d 365 (Utah Supreme Court, 1997)
Doit, Inc. v. Touche, Ross & Co.
926 P.2d 835 (Utah Supreme Court, 1996)
Berenda v. Langford
914 P.2d 45 (Utah Supreme Court, 1996)
S & G INC. v. Intermountain Power Agency
913 P.2d 735 (Utah Supreme Court, 1996)
Ward v. Intermountain Farmers Ass'n
907 P.2d 264 (Utah Supreme Court, 1995)
Bauman v. Day
892 P.2d 817 (Alaska Supreme Court, 1995)
Records v. Briggs
887 P.2d 864 (Court of Appeals of Utah, 1994)
Salt Lake City Corp. v. Kasler Corp.
855 F. Supp. 1560 (D. Utah, 1994)
Sevy v. Security Title Co. of Southern Utah
857 P.2d 958 (Court of Appeals of Utah, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
744 P.2d 1370, 42 Educ. L. Rep. 982, 68 Utah Adv. Rep. 5, 1987 Utah LEXIS 800, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brigham-young-university-v-paulsen-construction-co-utah-1987.