S & G INC. v. Intermountain Power Agency

913 P.2d 735, 1996 Utah LEXIS 36, 1996 WL 120514
CourtUtah Supreme Court
DecidedMarch 11, 1996
Docket940597
StatusPublished
Cited by11 cases

This text of 913 P.2d 735 (S & G INC. v. Intermountain Power Agency) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S & G INC. v. Intermountain Power Agency, 913 P.2d 735, 1996 Utah LEXIS 36, 1996 WL 120514 (Utah 1996).

Opinion

STEWART, Associate Chief Justice:

S & G Incorporated appeals a district court order dismissing with prejudice its claims for relief. S & G’s complaint alleged three claims against Intermountain Power Agency (IPA) that arose out of a contract wherein S & G agreed to sell to IPA water rights appurtenant to land S & G owned near Delta, Utah. The district court dismissed S & G’s first and third claims, one sounding in contract and the other in tort, on statute of limitations grounds; and on cross-motions for summary judgment the court ruled that S & G had entered into an accord and satisfaction and released the second claim for relief. We affirm.

I. BACKGROUND

Prior to 1980, S & G owned 228 acres in Millard County, Utah, that included a well used for irrigation purposes and a water right that allowed the use of 5 cubic feet per second from April to October of each year, up to a maximum of 2,140 acre feet each season. On July 22, 1980, S & G and IPA entered into a ‘Water Right Purchase Contract” which allowed IPA to buy 521 acre feet of water from S & G to be used for municipal culinary purposes. On April 17, 1981, the parties amended the contract to allow IPA to purchase S & G’s entire water right and to require IPA to pay $1,750 per acre foot for the first 521 acre feet of water and $875 for each additional acre foot approved for diversion by the Utah state engineer. The amended contract further provided that if the state engineer, or the Utah courts on review of the engineer’s decision, failed to quantify the amount of water for diversion, the parties would “presume” a quantity of 4.0 acre feet per acre, or a total of 912 acre feet.

Pursuant to the contract, IPA filed the requisite change application with the state engineer. S & G did not participate in the administrative proceedings related to this application. On September 10, 1984, the engineer set the transferable quantity of water at 775.2 acre feet but indicated that the decision was “interlocutory” and subject to change by subsequent findings of the state engineer or court rulings. On November 5, 1984, S & G contacted IPA, requesting that IPA file a civil suit, pursuant to Utah Code Ann. §§ 73-3-14 to -15 (1980), challenging the state engineer’s decision. IPA declined to do so and suggested that S & G could file the suit on its own. On November 9, 1984, the last day on which the suit could be filed, S & G, acting alone, filed a complaint in the Fourth District Court of Millard County, challenging the transferable quantity of water set by the state engineer.

On January 29,1985, S & G requested that IPA make early payment for the 775.2 acre feet of water approved by the state engineer. In response, IPA sent S & G a “Partial Payment Contract,” which was revised and incorporated into a document designated as a “Change Order” on September 18, 1985. The change order (1) confirmed that IPA had paid S & G for a total of 684 acre feet of water and (2) reiterated the language of the amended contract that in the event the courts did not “fix the quantity of water in acre feet approved [by the state engineer,] for change to municipal use, the quantity [would] be presumed to be 912.0 acre feet.”

On October 3, 1986, the district court dismissed S & G’s suit against the state engineer on the ground that S & G’s interest was not within the “zone of interest” that provided it standing for an appeal from the engineer’s order. This Court affirmed the district court’s decision on the narrower ground that S & G had waived its right to judicial *738 review of the state engineer’s findings by failing to participate in the administrative proceedings relating to the change application filed by IPA. S & G Inc. v. Morgan, 797 P.2d 1085, 1087-88 (Utah 1990).

On July 3, 1990, IPA paid S & G the balance due on the 775.2 acre feet of water set by the state engineer. On receiving payment, S & G executed a “Receipt and Release” which stated that it discharged IPA from all claims by S & G except for claims related to IPA’s failure to file suit challenging the state engineer’s decision.

On March 27, 1992, S & G filed the complaint 1 which is the subject of the present appeal. S & G’s first two causes of action alleged that IPA breached its contract by (1) failing to seek judicial review of the state engineer’s decision, and (2) failing to pay for the “presumed” quantity of water specified in the contract (912 acre feet). In its third cause of action, S & G alleged a claim of fraud based on the same operative facts as those alleged in the first cause of action.

The district court, on IPA’s motion to dismiss, ruled that the first and third claims were barred by the applicable statutes of limitations. The court also granted IPA’s motion for summary judgment on S & G’s second claim on the ground that there was no issue of material fact as to S & G’s having executed an accord and satisfaction of the second claim in the receipt and release document of July 3, 1990, and was entitled to judgment as a matter of law.

Summary judgment is appropriate when no genuine issues of material fact exist and the moving party is entitled to judgment as a matter of law. Winegar v. Froerer Corp., 813 P.2d 104, 107 (Utah 1991). Because a challenge to summary judgment presents for review only questions of law, we accord no particular deference to the district court’s conclusions but review them for correctness. Schurtz v. BMW of N. Am., Inc., 814 P.2d 1108, 1111-12 (Utah 1991).

We first discuss the issue of accord and satisfaction with respect to S & G’s second cause of action and then treat the statutes of limitations issue with respect to S & G’s first and third causes of action.

II. ACCORD AND SATISFACTION

S & G alleges that IPA breached the amended contract of April 17, 1981, because IPA did not pay for the full 912 acre feet of water “presumed” to have been sold by S & G under the contract (and reiterated in the change order of September 18, 1985) if neither the state engineer nor the courts fixed the transferable quantity of the water right. S & G contends that because the engineer’s decision stated that it was “interlocutory,” it did not “fix” the quantity of water that was transferable to IPA. S & G further asserts that because the district court and this Court rejected S & G’s challenge of the engineer’s decision on procedural grounds, those courts did not reach the merits of S & G’s claims and did not fix a transferable quantity of water. For these reasons, S & G asserts that it is entitled to payment for an additional 136.8 acre feet of water at $875 per acre foot as provided in the amended contract.

IPA argues that regardless of whether the engineer fixed the amount of transferable water, S & G’s execution of the July 3,1990, receipt and release constituted an accord and satisfaction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Johnson
224 F. Supp. 3d 1220 (D. Utah, 2016)
Pearson v. South Jordan
2012 UT App 88 (Court of Appeals of Utah, 2012)
Pearson v. South Jordan City
2012 UT App 88 (Court of Appeals of Utah, 2012)
Friolo v. Frankel
28 A.3d 752 (Court of Special Appeals of Maryland, 2011)
Larry J. Coet Chevrolet v. Labrum
2008 UT App 69 (Court of Appeals of Utah, 2008)
Clarke v. Living Scriptures, Inc.
2005 UT App 225 (Court of Appeals of Utah, 2005)
Admiral Mortgage, Inc. v. Cooper
745 A.2d 1026 (Court of Appeals of Maryland, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
913 P.2d 735, 1996 Utah LEXIS 36, 1996 WL 120514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-g-inc-v-intermountain-power-agency-utah-1996.