CECO Corp. v. Concrete Specialists, Inc.

772 P.2d 967, 106 Utah Adv. Rep. 3, 1989 Utah LEXIS 27, 1989 WL 35659
CourtUtah Supreme Court
DecidedApril 11, 1989
Docket19769
StatusPublished
Cited by48 cases

This text of 772 P.2d 967 (CECO Corp. v. Concrete Specialists, Inc.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CECO Corp. v. Concrete Specialists, Inc., 772 P.2d 967, 106 Utah Adv. Rep. 3, 1989 Utah LEXIS 27, 1989 WL 35659 (Utah 1989).

Opinion

*968 ZIMMERMAN, Justice:

Plaintiff CECO Corporation appeals from a trial court’s grant of summary judgment dismissing its action against third-party plaintiff Blumenthal Brothers, Inc. CECO claims that the trial court erred in holding that CECO was estopped from asserting its claim against Blumenthal. Blumenthal cross-appeals from the trial court’s dismissal of its third-party action for indemnification against Stansbury Mining Corporation, Victor Borcherds, and others. In the event that this Court reverses the trial court’s grant of summary judgment, Blumenthal seeks reinstatement of its third-party claim. We reverse the trial court’s dismissal of CECO’s claim against Blumenthal and of Blumenthal’s indemnification action against the third-party defendants.

This case was presented to the trial court on stipulated facts, which are summarized below. In November of 1980, Blumenthal signed a contract with the Board of Education of the Murray School District. Blu-menthal was to act as general contractor for the construction of an addition to the Murray High School gymnasium. Blumen-thal posted a 100 percent labor and materials payment bond with the School District, as required by sections 53-11-1 and 63-56-38 of the Utah Code. 1 In December of 1980, Blumenthal subcontracted the concrete work on the project to Concrete Specialists, Inc. (“CSI”), which did not post a bond. In January of 1981, CSI sub-subcontracted a portion of its work to CECO. CECO fully performed its work under the CSI/CECO contract between May and August of 1981.

Blumenthal made periodic payments to CSI as construction progressed. By Au *969 gust of 1981, CSI had received approximately $180,000 from Blumenthal, but had not paid CECO anything. Therefore, during the first week of August of 1981, James Trenam, CECO’s district manager, telephoned William H. Blumenthal, Vice-President of Blumenthal. Trenam asked Blumenthal if any payments had been made to CSI, notified him that CSI had not yet paid CECO for the work it had performed, and asked Blumenthal if he could put some pressure on CSI to pay CECO. Blumenthal responded that he had made regular payments to CSI and that he would attempt to help CECO. He offered to make checks for CSI’s next payments payable jointly to CSI and CECO. Trenam replied that CSI had agreed to pay CECO on August 14, 1981, and asked Blumenthal to refrain from making a payment to CSI until after that date. Blumenthal complied with this request.

On August 19, 1981, Trenam called William Blumenthal again. Trenam notified Blumenthal that CECO had received payment from CSI on its first invoice and that, although CSI still owed CECO approximately $21,500 on subsequent invoices, CSI had represented that it would pay this amount to CECO. Trenam stated that it appeared it would not be necessary for Blumenthal to pay CSI by checks jointly payable to CSI and CECO in order to ensure CECO’s being paid, that Blumenthal should go ahead and pay CSI in the ordinary way as it had in the past, as is the custom in the industry, and that CECO would continue to seek payment directly from CSI. Blumenthal subsequently paid CSI $16,020 on August 20,1981, and $9,630 on September 25, 1981, without making the checks jointly payable to CSI and CECO. Sometime in September, CSI failed to perform further on its contract with Blumen-thal. CSI also failed to make any more payments to CECO and eventually filed a petition in bankruptcy. On November 4, 1981, CECO notified Blumenthal in writing of CSI’s payment default, as required by Blumenthal’s payment bond and informed Blumenthal that it was making a claim for $25,399.70 as amounts due but unpaid from CSI. Trenam also telephoned William Blu-menthal on December 16, 1981, and personally informed him that CSI had made no payments after August 19, 1981. Blumen-thal replied that Blumenthal did not owe any further sums to CSI and therefore could not help CECO with checks made jointly payable to CSI and CECO.

CECO instituted this action against Blu-menthal and its indemnity bond carrier. The trial court granted Blumenthal summary judgment. It held that because Trenam refused Blumenthal’s offer to issue checks to CSI made jointly payable to CSI and CECO, permitted' Blumenthal to pay CST directly, and represented that it would look to CSI for payment, CECO was estopped from later asserting a claim against Blu-menthal for sums that would be otherwise due under the bond. On appeal, CECO argues that the trial court erred in holding that it was estopped. CECO contends that the facts essential to create an estoppel defense are missing.

The standard of review when considering a challenge to a summary judgment is settled. A grant of summary judgment is appropriate only when no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. Utah R.Civ.P. 56(c); see, e.g., Geneva Pipe Co. v. S & H Ins. Co., 714 P.2d 648, 649 (Utah 1986). And in deciding whether the trial court properly granted judgment as a matter of law to the prevailing party, we give no deference to the trial court’s view of the law; we review it for correctness. See Mountain Fuel Supply Co. v. Salt Lake City Corp., 752 P.2d 884, 887 (Utah 1988); Atlas Corp. v. Clovis Nat’l Bank, 737 P.2d 225, 229 (Utah 1987); Scharf v. BMG Corp., 700 P.2d 1068, 1070 (Utah 1985). Here, because there is no dispute as to the facts, we are faced with a purely legal question: Do the facts show estop-pel?

Estoppel is an equitable defense that requires proof of three elements: (i) a statement, admission, act, or failure to act by one party inconsistent with a claim later asserted; (ii) reasonable action or inaction by the other party taken or not taken on the basis of the first party’s statement, *970 admission, act, or failure to act; and (iii) injury to the second party that would result from allowing the first party to contradict or repudiate such statement, admission, act, or failure to act. Celebrity Club, Inc. v. Utah Liquor Control Comm’n, 602 P.2d 689, 694 (Utah 1979); see also Blackhurst v. Transamerica Ins. Co., 699 P.2d 688, 691 (Utah 1985); United American Life Ins. Co. v. Zions First Nat’l Bank, 641 P.2d 158, 161 (Utah 1982); J.P. Koch, Inc. v. J.C. Penney Co., 534 P.2d 903, 905 (Utah 1975).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Derma Pen, LLC v. 4EverYoung Ltd.
76 F. Supp. 3d 1308 (D. Utah, 2014)
Veysey v. Veysey
2014 UT App 264 (Court of Appeals of Utah, 2014)
Bahr v. Imus
2011 UT 19 (Utah Supreme Court, 2011)
Estate of Higley v. State, Department of Transportation
2010 UT App 227 (Court of Appeals of Utah, 2010)
Bahr v. Imus
2009 UT App 155 (Court of Appeals of Utah, 2009)
SFR, INC. v. Comtrol, Inc.
2008 UT App 31 (Court of Appeals of Utah, 2008)
Shaw Resources Ltd. v. Pruitt, Gushee & Bachtell, P.C.
2006 UT App 313 (Court of Appeals of Utah, 2006)
Dahl Investment Co. v. Hughes
2004 UT App 391 (Court of Appeals of Utah, 2004)
State v. Hamilton
2003 UT 22 (Utah Supreme Court, 2003)
IHC Health Services, Inc. v. D & K Management, Inc.
2003 UT 5 (Utah Supreme Court, 2003)
Carlile v. Wal-Mart
2002 UT App 412 (Court of Appeals of Utah, 2002)
Nunley v. Westates Casing Services, Inc.
1999 UT 100 (Utah Supreme Court, 1999)
Johnson v. City of Bountiful
996 F. Supp. 1100 (D. Utah, 1998)
House v. Armour of America, Inc.
929 P.2d 340 (Utah Supreme Court, 1996)
S & G INC. v. Intermountain Power Agency
913 P.2d 735 (Utah Supreme Court, 1996)
Barnard v. Wassermann
855 P.2d 243 (Utah Supreme Court, 1993)
Harline v. Barker
854 P.2d 595 (Court of Appeals of Utah, 1993)
McKinnon v. Tambrands, Inc.
815 F. Supp. 415 (D. Utah, 1993)
First Security Bank of Utah v. Creech
858 P.2d 958 (Utah Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
772 P.2d 967, 106 Utah Adv. Rep. 3, 1989 Utah LEXIS 27, 1989 WL 35659, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ceco-corp-v-concrete-specialists-inc-utah-1989.