Shaw Resources Ltd. v. Pruitt, Gushee & Bachtell, P.C.

2006 UT App 313, 142 P.3d 560, 557 Utah Adv. Rep. 38, 2006 Utah App. LEXIS 332, 2006 WL 2089324
CourtCourt of Appeals of Utah
DecidedJuly 28, 2006
Docket20050304-CA
StatusPublished
Cited by14 cases

This text of 2006 UT App 313 (Shaw Resources Ltd. v. Pruitt, Gushee & Bachtell, P.C.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shaw Resources Ltd. v. Pruitt, Gushee & Bachtell, P.C., 2006 UT App 313, 142 P.3d 560, 557 Utah Adv. Rep. 38, 2006 Utah App. LEXIS 332, 2006 WL 2089324 (Utah Ct. App. 2006).

Opinions

OPINION

GREENWOOD, Associate Presiding Judge:

¶ 1 Plaintiffs Shaw Resources Limited, L.L.C., Scorpio Energy Resources, L.L.C., and Comet Resources, L.L.C. (collectively, Plaintiffs) appeal from a summary judgment dismissing the following nine claims with prejudice: (1) breach of fiduciary duty, (2) constructive trust, (3) aiding and abetting breach of fiduciary duty, (4) civil conspiracy, (5) breach of contract/covenant of good faith and fair dealing, (6) negligence in legal representation, (7) interference with prospective economic relations, (8) fraudulent nondisclosure, and (9) misappropriation of trade secrets.1 Plaintiffs also appeal the trial court’s rule 11 sanction dismissing Defendant Robert S. Thompson III.2 We affirm.

BACKGROUND

¶ 2 This case involves oil and gas fields located in Uintah County on the Uintah and Ouray Reservation of the Ute Indian Tribe (the Tribe) in an area known as the Hill Creek Extension. A map of the area at issue is appended to this opinion. The Tribe owns the surface rights and a portion of the mineral rights in the Hill Creek Extension. The state and federal governments each own por[563]*563tions of the remaining mineral rights in the Hill Creek Extension.3

¶ 3 An area known as Flat Rock Field is located within the 400,000-acre Hill Creek Extension. (Flat Rock Field is designated as B on the appended map.) It consists of tribal surface rights and federal mineral rights. The disputed area, North Hill Creek, is located in the southeastern portion of the Hill Creek Extension, south of Flat Rock Field. (North Hill Creek is designated as C on the appended map.) The Tribe owns both surface and mineral rights in North Hill Creek. The Naval Oil Shale Reserve No. 2 (NOSR-2), consisting of 88,000 acres, lies partly within the Hill Creek Extension. (NOSR-2 is designated as A on the appended map.) Prior to 2001 the federal government owned the mineral rights therein, holding them in reserve for the Navy.

¶4 Dan Shaw formed and managed numerous entities to finance the exploration and development of oil and gas wells in Flat Rock Field, including Plaintiffs Shaw Resources Limited, L.L.C. (Shaw Resources) and Scorpio Energy Resources, L.L.C. (Scorpio). Dan Shaw also managed, with his brother, K.C. Shaw, Plaintiff Comet Resources, L.L.C. (Comet), which was primarily a gas and pipeline company created to transport gas. Plaintiffs had similar, but not identical ownership, and although they shared the same manager, they were separate legal entities. In the summer of 2003, John E. Dyer, of Miller Dyer & Company, replaced Dan Shaw as Plaintiffs’ manager.

¶ 5 On May 12, 1995, Dan Shaw obtained federal and state mineral lease assignments for oil and gas development rights in Flat Rock Field. He retained the lease assignments exclusively in his name until July 29, 2002, when he assigned them to Shaw Resources. Prior to July 29, 2002, none of the Plaintiffs held record title to leases or development rights in Flat Rock Field.

¶ 6 Dan Shaw employed a geologist, David Allin, to identify new development opportunities. He also contracted with Larry Caldwell to act as the field operator in Flat Rock Field.

¶ 7 During the summer of 1999, Plaintiffs redrilled well 32-5A, which is located in Flat Rock Field, north of North Hill Creek. Plaintiffs assert that the drilling indicated that a potentially significant amount of gas could be located in and around Flat Rock Field.

¶ 8 Conversely, both Allin and Caldwell testified in their depositions that they had not recommended pursuing North Hill Creek because they thought there was greater potential for development to the north. They also testified that they had not recommended gas and oil development activities on tribal land because of potential legal difficulties with the Tribe. Dan Shaw testified that, to his knowledge, neither he, nor any of the Plaintiff entities, attempted to acquire mineral lease rights on tribal property in North Hill Creek or elsewhere.

¶ 9 In a September 15, 1999 letter from Allin to Caldwell, Allin reported on the status of unleased federal mineral rights in Flat Rock Field and other nearby areas. He did not mention the status of unleased tribal mineral rights in the area. Allin wrote that he had enclosed a “highly confidential” map known as the “Dakota Structure Map” (the Dakota Map) of unleased federal lands in the area for the purpose of showing Caldwell the area’s promising opportunities for development. At the end of the letter, Allin wrote that they would be talking “more about these issues and further research requested on mineral ownership in [Flat Rock Field].” The letter did not mention North Hill Creek or Tribe-owned mineral rights.

¶ 10 On the same date, Allin wrote to the Bureau of Land Management (BLM) regarding the same unleased federal mineral rights. In the letter, he also explained Plaintiffs’ drilling activities in Flat Rock Field. He made no mention of North Hill Creek.

¶ 11 Dan Shaw hired Defendant Pruitt, Gushee & Bachtell, P.C. (the Law Firm) on April 5, 1999.4 Thomas W. Bachtell and A. [564]*564John Davis III were attorneys at the Law Firm. Initially, Dan Shaw retained the Law Firm, and specifically Davis, to represent Plaintiff Comet in a dispute with a party who claimed ownership of and rights-of-way to the Comet pipeline. The April 5, 1999 engagement letter confirmed the Law Firm’s representation of Dan Shaw and Comet “and its related entities in ... matters related to the gas pipeline and facilities owned by Comet in Uintah County.” Dan Shaw acknowledged in his deposition testimony that he did not engage the Law Firm to explore or develop oil and gas opportunities.

¶ 12 Defendant Wind River Resources Corporation (Wind River) was a company engaged in oil and gas exploration and development. Bachtell was a shareholder of Wind River during the time at issue. Davis acquired shares in Wind River in February 2000. Wind River’s geologist, Marc Eckels, had explored oil and gas production possibilities in the Hill Creek Extension in November 1998. In February 1999, Wind River entered into an agreement with the Tribe to develop NOSR-2, which lies in the northwest section of the Hill Creek Extension, in anticipation of the Tribe one day owning the mineral rights there. During the summer of 1999, as part of Eckels’s evaluation of NOSR-2, he evaluated other oil and gas fields in the area, including Flat Rock Field. Eckels obtained a news article from the Rocky Mountain Region Report, dated August 10, 1999, that documents the historical performance of well 32-5A, as well as Plaintiffs’ intent to redrill it. He also assembled other public records, such as charts and logs documenting data about wells in the Flat Rock Field vicinity, including well 32-5A. The only information Eckels obtained from Plaintiffs was a map of Comet’s pipeline that he submitted with an application for a Department, of Energy (DOE) grant. Eckels requested the map from Davis, who obtained it from K.C. Shaw.

¶ 13 In October 1999, Eckels applied for a DOE grant to conduct a 3-D seismic survey of the North Hill Creek area. In November 1999, Eckels submitted an application to the Tribe to explore and develop Tribe-owned mineral rights in North Hill Creek. The Tribe agreed to allow him to conduct the seismic survey.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vanderwood v. Woodward
2019 UT App 140 (Court of Appeals of Utah, 2019)
USA POWER, LLC v. PacifiCorp
2010 UT 31 (Utah Supreme Court, 2010)
Chilton v. Young
2009 UT App 265 (Court of Appeals of Utah, 2009)
Free Motion Fitness, Inc. v. Wells Fargo Bank West, NA
2009 UT App 120 (Court of Appeals of Utah, 2009)
Rhodes v. Department of Transportation
2008 UT App 374 (Court of Appeals of Utah, 2008)
SUPERIOR RECEIVABLE SERVICES v. Pett
2008 UT App 225 (Court of Appeals of Utah, 2008)
Harper v. Evans
2008 UT App 165 (Court of Appeals of Utah, 2008)
Orvis v. Johnson
2008 UT 2 (Utah Supreme Court, 2008)
Orvis v. Johnson
2006 UT App 394 (Court of Appeals of Utah, 2006)
Shaw Resources Ltd. v. Pruitt, Gushee & Bachtell, P.C.
2006 UT App 313 (Court of Appeals of Utah, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2006 UT App 313, 142 P.3d 560, 557 Utah Adv. Rep. 38, 2006 Utah App. LEXIS 332, 2006 WL 2089324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shaw-resources-ltd-v-pruitt-gushee-bachtell-pc-utahctapp-2006.