Brasfield & Gorrie, LLC v. Harrod Concrete and Stone Co.

CourtDistrict Court, E.D. Kentucky
DecidedApril 15, 2021
Docket3:18-cv-00066
StatusUnknown

This text of Brasfield & Gorrie, LLC v. Harrod Concrete and Stone Co. (Brasfield & Gorrie, LLC v. Harrod Concrete and Stone Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brasfield & Gorrie, LLC v. Harrod Concrete and Stone Co., (E.D. Ky. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF KENTUCKY CENTRAL DIVISION FRANKFORT

BRASFIELD & GORRIE, LLC, ) ) Plaintiff, ) Civil No. 3:18-cv-00066-GFVT-EBA ) v. ) ) HARROD CONCRETE AND STONE CO., ) MEMORANDUM OPINION ) & Defendant. ) ORDER

*** *** *** ***

This is a case about concrete. For thousands of years, builders have created magnificent and lasting structures using concrete as the primary building material—and although the composition of concrete has changed over the centuries, the longevity appeal of concrete has remained.1 In 1875, the first concrete home was built in the United States, and it still stands today.2 In 1904, Cincinnati, Ohio, became home to the Ingalls Building, which is still standing and is the first concrete high-rise building ever constructed.3 Concrete is built to last. However, problems with concrete sometimes do arise, and cracks in concrete can lead parties to search for cracks in contracts. At issue in this case is whether Harrod Concrete and Stone Co. breached its contract with Brasfield & Gorrie, LLC by failing to provide concrete that met certain specifications. Harrod

1 For a deep dive into the history and development of cement and concrete, see Per Jahren and Tongbo Sui, History of Concrete: A Very Old and Modern Material (2017). 2 See Nick Gromicko & Kenton Shepard, The History of Concrete, Int. Assoc. of Cert. Home Inspectors, https://www.nachi.org/history-of-concretehtm (last visited Apr. 9, 2021). 3 Id. has filed a motion for summary judgment, arguing that there are no genuine issues of material fact and that Harrod should therefore prevail as a matter of law. For the reasons set forth herein, Harrod’s Motion for Summary Judgment will be DENIED. I

This case arises out of a contract dispute between Brasfield and Harrod over concrete that Harrod provided for a mixed-use development in Lexington, Kentucky, known as the Summit at Fritz Farm. Brasfield, the general contractor, contracted with Harrod for the supply of concrete for the project. [R. 47-1 at 2; R. 50 at 5.] The concrete specifications were prepared by Nimrod Long and Associates, Inc., a landscape architecture firm and third-party defendant in this case. [R. 47-1 at 3.] Harrod supplied vast amounts of concrete prepared to various specifications for buildings, infrastructure and the hardscape, and Brasfield accepted the concrete as it was delivered throughout the entirety of the project. Id. at 7. The majority of the deck washes, which are a part of the parking structures built for the Fritz Farm project, were poured around August of 2016, and the hardscape features were placed

in January through August of 2017, with the majority being placed in February through May of 2017. [R. 47-1 at 2; R. 50 at 11.] In February of 2018, less than one year after the project was completed, the owner informed Brasfield that some of the deck wash concrete and hardscape concrete began “scaling” or flaking into small pieces. [R. 47-1 at 3; R. 50 at 6.] Ten days after receiving notice of the scaling from the owner of the development, Brasfield reached out to Harrod through counsel regarding the scaling for assistance with the remediation efforts. [R. 47- 1 at 15; R. 50 at 11.] Brasfield also retained consultants to test the failing concrete, and according to Brasfield, the consultants determined that the primary cause of the concrete failure was low air content that did not comply with the specifications of Harrod’s mix designs. [R. 50 at 12.] Harrod declined to assist in the remediation efforts, and Brasfield spent over $600,000 on remedial work, arguing that it was contractually responsible to the project owner for making the repairs. [R. 47-1 at 3; R. 50 at 14.] Brasfield ultimately repaired approximately 10,000 square feet of the concrete out of approximately 110,000 square feet that was originally poured. [R. 47-

1 at 3.] As part of the remedial work, Brasfield also resurfaced the parking deck washes. Id. On November 16, 2018, Brasfield filed suit against Harrod. [R. 1.] Both parties agree that the damage to the concrete was caused by freeze-and-thaw conditions. [R. 47-1 at 3; R. 50 at 1.] Brasfield argues that the freeze-thaw conditions damaged the concrete because of low air entrainment levels that did not meet the contractually agreed- upon levels. [R. 50 at 1.] Brasfield specifically argues 1) that the Hardscape Specifications specified that the concrete would contain four to six percent entrained air and Harrod prepared a mix design stating that the concrete provided would contain six percent entrained air and a 0.532 water-to cement ratio; 2) that Harrod supplied concrete with less than six percent air content, and 3) that Brasfield sustained damages because Harrod’s concrete failed to meet the contractual specifications.4 [R. 1-2 at 5; R. 1-3 at 2; R. 1-4; R. 50 at 3–5.]

Harrod, on the other hand, argues that the scaling, which only occurred on less than ten percent of the hardscape concrete, was caused by a variety of other factors of which Brasfield is ultimately responsible. [R. 47-1 at 3, 7.] Specifically, Harrod argues 1) that it provided concrete that satisfied the mix designs and specifications; 2) that Brasfield failed to test the concrete at the time of delivery as required; 3) that Brasfield failed to properly place and finish the concrete; and

4 Brasfield also argues that Harrod was aware of deficiencies in the hardscape specification provided by Nimrod but failed to communicate those concerns to Brasfield. [R. 50 at 10.] Specifically, Harrod’s plant manager who prepared Harrod’s mix design testified that he questioned the hardscape specification but “just kept it, I guess, my question to myself.” Id. 4) that the experts actually point to a number of factors for the concrete scaling.5 [R. 47-1 at 5– 19.] On January 25, 2021, Harrod filed this Motion for Summary Judgment. [R. 47.] Brasfield Responded on February 16, and Harrod filed the Reply on March 2. [R. 50; R. 54.]

This matter is now ripe for review. The issue in this case is whether the concrete scaling was caused by Harrod’s failure to supply concrete for the project that conformed with their contractual obligations, Brasfield’s failure to properly cure or finish the concrete, or some combination of these factors. II Harrod makes the following four arguments as to why its Motion for Summary Judgment should be granted: 1) Brasfield lacks standing to pursue a claim against Harrod; 2) the breach of contract allegations against Harrod must be dismissed; 3) the breach of warranty claims against Harrod must be dismissed; and 4) the negligence claims must be dismissed. [R. 47-1.] Because the Court granted Brasfield’s request to remove its negligence claims from the Complaint [see R.

57], the Court need not address Harrod’s fourth argument because Brasfield’s negligence and negligent misrepresentation claims are no longer a part of this litigation.6 Harrod’s remaining three arguments will be addressed in turn.

5 Harrod contends that Brasfield engaged two consulting groups to test the concrete and concealed the findings of one of the groups, until compelled by discovery to disclose, that the scaling was due to finishing errors by Brasfield instead of air entrainment levels. [R. 47-1 at 16.] 6 The Court granted Brasfield’s request to remove counts III and IV from the Complaint but denied Brasfield’s Motion to Amend in all other respects because of undue delay and prejudice to Harrod. [R. 57.] However, because the Court is denying Harrod’s Motion to Dismiss and any updated facts Brasfield wanted to include in the Amended Complaint were uncovered during discovery and are therefore known to both parties, Harrod is not ultimately prejudiced by the partial denial of its motion to amend. A An initial matter is the question of standing. Town of Chester, N.Y. v. Laroe Estates, Inc., 137 S. Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Warth v. Seldin
422 U.S. 490 (Supreme Court, 1975)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Bennett v. Spear
520 U.S. 154 (Supreme Court, 1997)
DaimlerChrysler Corp. v. Cuno
547 U.S. 332 (Supreme Court, 2006)
Davis v. Federal Election Commission
554 U.S. 724 (Supreme Court, 2008)
Fifth Third Bank v. Lincoln Financial Securities Corp.
453 F. App'x 589 (Sixth Circuit, 2011)
Eileen A. Logan v. Denny's, Inc.
259 F.3d 558 (Sixth Circuit, 2001)
Chao v. Hall Holding Company, Inc.
285 F.3d 415 (Sixth Circuit, 2002)
North Georgia Ready Mix Concrete Co. v. L & L Construction, Inc.
508 S.E.2d 722 (Court of Appeals of Georgia, 1998)
Willey v. Terry & Wright of Kentucky, Inc.
421 S.W.2d 362 (Court of Appeals of Kentucky (pre-1976), 1967)
Salt Lake City Corp. v. Kasler Corp.
855 F. Supp. 1560 (D. Utah, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Brasfield & Gorrie, LLC v. Harrod Concrete and Stone Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/brasfield-gorrie-llc-v-harrod-concrete-and-stone-co-kyed-2021.