North Georgia Ready Mix Concrete Co. v. L & L Construction, Inc.

508 S.E.2d 722, 235 Ga. App. 68, 98 Fulton County D. Rep. 4047, 1998 Ga. App. LEXIS 1431
CourtCourt of Appeals of Georgia
DecidedNovember 2, 1998
DocketA98A1549
StatusPublished
Cited by4 cases

This text of 508 S.E.2d 722 (North Georgia Ready Mix Concrete Co. v. L & L Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Georgia Ready Mix Concrete Co. v. L & L Construction, Inc., 508 S.E.2d 722, 235 Ga. App. 68, 98 Fulton County D. Rep. 4047, 1998 Ga. App. LEXIS 1431 (Ga. Ct. App. 1998).

Opinion

McMurray, Presiding Judge.

Plaintiff-appellee L & L Construction, Inc. (“L & L”) brought this contract action against defendant-appellant North Georgia Ready Mix Concrete Company, Inc. (“Ready Mix”), alleging that, as part of plaintiff’s contract with S & S Mills, Inc. to construct a carpet warehousing facility in Whitfield County, Georgia, plaintiff engaged Ready Mix “to furnish concrete to be used ... in the floor of said facility[, based in part because Ready Mix] represented] that its product would conform to the specifications for the concrete floor incorporated into . . . the plans and specifications . . . and [also in part because of Ready Mix’s] professed capability to furnish a product that would resist drying shrinkage.” Throughout June 1994, defendant sold to plaintiff “approximately 3800 yards of 4,000 PSI concrete purportedly made with natural as opposed to manufactured *69 sand. . . .” Despite pouring the concrete slab using defendant’s materials in a workmanlike manner, plaintiff subsequently discovered “significant and unacceptable amounts of drying shrinkage resulting in a phenomenon referred to in the industry as ‘curling,’ . . .” as a result of which, plaintiff was “forced to effect repairs to a large portion of the concrete slab at. . . substantial cost. . . .”

Plaintiff further alleged that this “curling” was proximately caused by defendant’s wilful neglect in failing to supply plaintiff with a product fit for its intended purpose, despite plaintiff’s reliance on defendant’s assurances that the product was suitable for its intended application.

Defendant admitted it sold plaintiff 3,800 yards of 4,000 PSI concrete for the S & S Mills, Inc. project but denied the material allegations of breach of warranty. Defendant further counterclaimed for $15,303.75 allegedly owed it by plaintiff on account and also sought OCGA § 13-6-11 expenses of litigation for plaintiff’s alleged stubborn litigiousness and bad faith. The case was tried before a jury which returned a $100,000 verdict in favor of plaintiff against defendant. Defendant’s motion for judgment notwithstanding the verdict or a new trial was denied, and this appeal followed. Held:

1. In five related enumerations of error, defendant contends the trial court erred in denying its motions for directed verdict, arguing plaintiff failed to prove the existence of a contract to provide concrete with 80 percent natural sand and 20 percent manufactured sand; failed to prove any express warranty regarding mix design; failed to prove any intended particular purpose; failed to prove its privity with defendant; and failed to prove any breach was the proximate cause of the damages sustained.

“ ‘If there is no conflict in the evidence as to any material issue and the evidence introduced, with all reasonable deductions therefrom, shall demand a particular verdict, such verdict shall be directed.’ OCGA § 9-11-50 (a). ‘In determining whether any conflict in the evidence exists, the court must construe the evidence most favorably to the party opposing the motion for directed verdict. The standard used to review the grant or denial of a directed verdict is the “any evidence” test. [Cit.]’ [Cit.]” Dept. of Human Resources v. Thomas, 217 Ga. App. 174 (1) (a) (456 SE2d 724). Viewed in the light most favorable to the party securing the verdict, the evidence at trial showed the following:

The floor slab specifications called for “.4[-inch] compacted ‘pug mix’, a graded aggregate base material. . . . The floor will have a 4 mil polyethylene vapor barrier and will be reinforced with 6x6-10/10 welded wire mesh. . . . The floor will be 6" of [4,000] P.S.I. concrete poured on grade. The concrete mix will have natural white sand. . . . The floor will receive a trowel finish and will be sealed with one coat *70 of concrete sealer and hardener. . . . The floor will be sawed into areas approximately 780 sq. ft. . . .” Phillip Gerald Leonard, president of L & L, testified that he did not consider using Ready Mix for this concrete job because he experienced “problems with . . . Ready Mix with curling in the late Eighties,” for which Ready Mix had to reimburse L & L more than $17,000. Leonard repeatedly told Gerald Edward Long, defendant’s area manager for sales, that plaintiff “want[ed] the concrete to be all-natural white sand and no fly ash. . . . Gerald would say, ‘Jerry, no problem, just trade with us [at Ready Mix]. We’ve got the best quality concrete mixes in the area. We have solved our curling problem.’ And this was told to [Leonard] at least probably fifteen (15) to twenty (20) times.” In discussing the details, “Gerald [Long] says, ‘Jerry [Leonard], I would like to add some blue sand in this mix.’ [Leonard] said, ‘Gerald, you know I don’t like blue sand, or manufactured sand at all.’ He [Gerald Long] says, T know that, but we [Ready Mix] need a little bit for coarseness in this mix.’ ” Gerald Long initially proposed a mixture of “[s]eventy percent (70%) natural, thirty percent (30%) on the blue, or the manufactured [sand]. [Leonard was] will[ing to] allow . . . ten percent (10%) . . . blue sand, ninety percent (90%) on the natural sand. . . . Gerald [Long] said, ‘, . . I need more than that.’ And [Leonard] said, ‘Gerald, you know I don’t want any of it. I don’t like it. [Gerald Long replied,] T know that, Jerry, but trust me, we’ve got our curling problem worked out. We have no problem with curling. Just let me go with twenty percent (20%) on the manufactured sand, eighty percent (80%) on white natural.’ [Leonard] said, ‘Gerald, don’t ask me no farther; eighty/twenty (80/20) is as far as I’ll go.’ He [Gerald Long] said, ‘Fine.’ And that’s the way the job was traded on, eighty percent (80%) natural white, twenty percent (20%) blue.” The only reason Leonard even “considered] a trade . . .” with Ready Mix is because of the assurances that Ready Mix had resolved its prior problems with curling.

But Gerald Long “convinced [Leonard] to try to let him use an all blue sand in the footing, and said, ‘Jerry, just let me start with that and we’ll be able to save a little money by doing so. . . .’ He [Gerald Long] said, ‘. . . just let me try it. If we have any problem with it, all you have to do is let me know and I [Gerald Long] will immediately change it. . . .’ The next morning after the [first] pour, [Leonard saw]. . . hairline cracks lead away from [a grade] stob to each side of the width of the footing. [Leonard] called Gerald [Long] up and [told him], ‘Gerald, change the concrete. I don’t want no more of this.’ He [Gerald Long] said, ‘No problem.’ ” Leonard intended that Ready Mix go back to the agreed-upon mixture of 80 percent white natural sand and 20 percent blue manufactured sand. Leonard thought “the concrete that evening worked much, much better.” In Leonard’s experi *71 ence, one does not have “near the shrinkage in natural sand that [one does] with the manufactured sand. Manufactured sand does have much more shrinkage, in turn, it could be in the form of cracking and also in the form of curling. . . . Also, [i]t’s a very harsh mix. To use total blue sand without putting a fly ash with it, it will be a harsher mix.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leica Geosystems, Inc. v. L.W.S. Leasing, Inc.
872 F. Supp. 2d 1191 (D. Colorado, 2012)
Camp v. Eichelkraut
539 S.E.2d 588 (Court of Appeals of Georgia, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
508 S.E.2d 722, 235 Ga. App. 68, 98 Fulton County D. Rep. 4047, 1998 Ga. App. LEXIS 1431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-georgia-ready-mix-concrete-co-v-l-l-construction-inc-gactapp-1998.