Perry v. Pioneer Wholesale Supply Co.

681 P.2d 214, 38 U.C.C. Rep. Serv. (West) 1274, 1984 Utah LEXIS 806
CourtUtah Supreme Court
DecidedApril 16, 1984
Docket18657
StatusPublished
Cited by79 cases

This text of 681 P.2d 214 (Perry v. Pioneer Wholesale Supply Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perry v. Pioneer Wholesale Supply Co., 681 P.2d 214, 38 U.C.C. Rep. Serv. (West) 1274, 1984 Utah LEXIS 806 (Utah 1984).

Opinion

OAKS, Justice:

Utah’s enactment of the Uniform Commercial Code provides that actions for breach of warranty in a contract for the sale of goods must be commenced within four years after delivery of the goods. U.C.A., 1953, § 70A-2-725. The district court relied on that statute in granting summary judgment to bar a purchaser’s action against a supplier and a manufacturer. We affirm.

Third-party plaintiff Perry was a subcontractor to furnish doors and millwork on a construction project for the Dixie Medical Center in St. George. Perry ordered the doors by telephone from the supplier, Pioneer Wholesale, which then ordered them from the manufacturer, Paine Lumber. The supplier received the doors on September 24, 1974, and stored them in an area protected from the elements. In due course, the doors were shipped to the job site in St. George, where Perry received them on December 14, 1974, and stored them for a time before hanging them. On March 27, 1975, the general contractor, Acord-Harris Construction Co., gave Perry written notice of rejection of the doors for defects. When Perry failed to remedy the defects, the contractor purchased replacement doors directly from the supplier on July 1, 1975.

The general contractor originated this action on March 25, 1977, with a complaint against Perry for breach of contract. It was not until February 26,1980, that Perry filed this third-party complaint against the supplier, and on October 17, 1980, Perry amended the complaint to include the manufacturer. The amended third-party complaint alleged that the supplier and the manufacturer had warranted the doors and that both of these third-party defendants had breached their warranties. Perry’s only claim for relief stated that in the event he was held liable to the general contractor he should have judgment against the supplier and the manufacturer in the same amount.

After the trial court granted third-party defendants’ motions for summary judgment on the basis of the four-year statute of limitations in § 70A-2-725, Perry stipulated to a judgment against him by the general contractor. Perry now appeals the granting of summary judgment in his third-party action against the supplier and the manufacturer.

I. GENERAL CONTRACT STATUTE OF LIMITATIONS

Perry first contends that the trial court erred by failing to apply § 78-12-23, which provides a six-year limitation period for an action upon a contract in writing. Even if this were an action on a written contract, which third-party defendants dispute, the trial court was correct in rejecting the application of this general statute of limitations. When two statutory provisions appear to conflict, the more specific provision will govern over the more general provision. Millett v. Clark Clinic Corp., Utah, 609 P.2d 934 (1980). Thus, where the Uniform Commercial Code sets forth a limitation period for a specific type of action, this limitation controls over an older, more general statute of limitations. Payne v. Far-Mar-Co., Mo., 612 S.W.2d 54 (1981); Reiss v. Pacific Steel Pool Corp., 73 Misc.2d 78, 341 N.Y.S.2d 364 (1973). That rule establishes § 70A-2-725 as the applicable statute of limitations for the cause of action alleged in this case.

II. RELATION BACK

Perry argues that under Utah R.Civ.P. 15(c) his amended third-party complaint should relate back to the filing of the *217 original action in 1977. This argument is without merit because the relation-back doctrine does not apply to an amendment that adds new parties who have no identity of interest with existing parties.

Generally Rule 15(c), U.R.C.P., will not apply to an amendment which substitutes or adds new parties for those brought before the court by the original pleadings — whether plaintiff or defendant. This [is] for the reason that such would amount to the assertion of a new cause of action, and if such were allowed to relate back to the filing of the complaint, the purpose of a statute of limitation would be defeated.

Doxey-Layton Co. v. Clark, Utah, 548 P.2d 902, 906 (1976). “Identity of interest” as used in this context means that the parties are so closely related in their business operations that notice of the action against one serves to provide notice of the action to the other. Such an identity exists, for example, between past and present forms of the same enterprise. See Spiker v. Hoogeboom, Colo.App., 628 P.2d 177, 179 (1981). In this case, there was no evidence showing any identity of interest between the original plaintiff, the defendant, and the third-party defendants other than privity of contract. This is an insufficient identity of interest for the purpose of Rule 15(c). If any third-party action automatically related back to the date of filing of the original complaint, Rule 15(e) would become an all-encompassing rule that would eliminate all limitations on third-party actions. The law is otherwise.

III. INDEMNITY THEORY AND § 70A-2-725

Perry argues that §,70A-2-725 does not apply because his action is in reality one for indemnity, not one for breach of warranty. We consider this argument in the context of the undeniable fact that the subject matter of this entire lawsuit is the sale of goods, which will be governed where applicable by the Utah version of the Uniform Commercial Code. U.C.A., 1953, § 70A-1-101, et seq. The underlying action was for breach of contract, and the amended third-party complaint alleges only a cause of action for breach of warranty. It nowhere mentions indemnity. Nonetheless, we look to the substance of Perry’s claim, regardless of what he chose to call it.

The four-year statute applicable to the indemnity theory does not apply in this case because a sale of goods occurred in 1974 with observable defects (if any), and any cause of action against Third-Party Defendants arose at that time. Otherwise, anyone buying defective goods could resell them before or after the statute had run, and upon being sued for the original defects, file a third-party complaint for indemnity and thus defeat the policy of repose underlying the statute of limitation.

The issue here is whether a purchaser of goods can obtain indemnity from a manufacturer or supplier for damages the purchaser was forced to pay by reason of an alleged breach of warranty even though the purchaser did not file its indemnification action until after the statute of limitations had run on the underlying cause of action. We agree with the district court that the Uniform Commercial Code forbids such a result. 1

Courts in other states have split on whether U.C.C. § 2-725 bars an indemnity action. The Georgia Court of Appeals and the Illinois Supreme Court have held that § 2-725 bars a separate period of limitation for indemnity claims based on breach of warranty. PPG Industries, Inc. v. Genson, 135 Ga.App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deleeuw v. Nationstar Mortg. LLC
2018 UT App 59 (Court of Appeals of Utah, 2018)
Bylsma v. R.C.WilleyHumanTouch
2017 UT 85 (Utah Supreme Court, 2017)
2010-1 RADC/CADC Venture, LLC v. Dos Lagos, LLC
2017 UT 29 (Utah Supreme Court, 2017)
Salt Lake City v. Valdez-Sadler
2015 UT App 203 (Court of Appeals of Utah, 2015)
Willis v. DeWitt
2015 UT App 123 (Court of Appeals of Utah, 2015)
Veysey v. Veysey
2014 UT App 264 (Court of Appeals of Utah, 2014)
VCS, Inc. v. La Salle Development, LLC
2012 UT 89 (Utah Supreme Court, 2012)
Novell, Incorporated v. Microsoft Corporation
429 F. App'x 254 (Fourth Circuit, 2011)
Wells Dairy, Inc. v. American Industrial Refrigeration, Inc.
762 N.W.2d 463 (Supreme Court of Iowa, 2009)
Nunn v. Mid-Century Insurance Co.
215 P.3d 1196 (Colorado Court of Appeals, 2008)
Nu-Med USA, Inc. v. 4Life Research, L.C.
2008 UT 50 (Utah Supreme Court, 2008)
Electric Insurance v. Freudenberg-NOK, General Partnership
487 F. Supp. 2d 894 (W.D. Kentucky, 2007)
In Re Marriage of Kunz
2006 UT App 151 (Court of Appeals of Utah, 2006)
Gary Porter Construction v. Fox Construction, Inc.
2004 UT App 354 (Court of Appeals of Utah, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
681 P.2d 214, 38 U.C.C. Rep. Serv. (West) 1274, 1984 Utah LEXIS 806, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perry-v-pioneer-wholesale-supply-co-utah-1984.