Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP

130 A.3d 1024, 226 Md. App. 420, 2016 Md. App. LEXIS 3, 2016 WL 360875
CourtCourt of Special Appeals of Maryland
DecidedJanuary 28, 2016
Docket0496/14
StatusPublished
Cited by14 cases

This text of 130 A.3d 1024 (Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP, 130 A.3d 1024, 226 Md. App. 420, 2016 Md. App. LEXIS 3, 2016 WL 360875 (Md. Ct. App. 2016).

Opinion

*426 LEAHY, J.

In this appeal we consider whether the economic loss doctrine applies to shield an engineering firm from tort claims brought by a contractor seeking damages for economic losses suffered in consequence of relying on the firm’s allegedly defective designs and projections. Our holding is framed by the fact that, while the engineering firm and the contractor each had separate contracts with the government to perform work on the same design-bid-build construction project, there was no contract between the parties.

The City of Baltimore entered into a contract with Rummel Klepper & Kahl, LLP (“RK & K” or “Appellee”), a design engineering firm, to produce construction designs and associated documents for use by the successful bidder(s) on succeeding proposals for construction of the Patapsco Wastewater Treatment Plant. Fru-Con Construction Corporation, predecessor to Balfour Beatty Infrastructure, Inc. (“BBII” or “Appellant”), 1 was the successful bidder on the plant upgrade projects, and entered into Sanitary Contract 852R with the City in November 2009.

Just over four years later, BBII filed a complaint in the Circuit Court for Baltimore City against RK & K, claiming that, during construction, BBII ran into costly delays and complications in reliance on RK & K’s allegedly defective designs and negligent misrepresentations concerning project timeline projections. The complaint sounded in tort, supported by the theory that RK & K had a duty to BBII based on the “intimate nexus” between them, and asserted three causes of action: 1) professional negligence, 2) information negligently supplied for the guidance of others under Restatement (Second) of Torts § 552, and, 3) negligent misrepresentation.

RK & K filed a motion to dismiss the complaint for failure to state a claim. RK & K’s central argument was that the *427 complaint sought recovery for purely economic losses, and, because there was no contractual privity or its equivalent between BBII and RK & K, the economic loss doctrine barred BBII’s tort claims. The circuit court granted the motion to dismiss in an order entered on April 10, 2014.

We affirm. We hold that BBII failed to state a claim because, as a matter of law, in the absence of privity, death, personal injury, property damage, or the risk of death or serious personal injury, no duty of care in tort runs from an engineer or architect to a contractor for purely economic losses on a public construction project. In reaching this holding, we determine that Maryland does not expand the “intimate nexus” test to include extra-contractual concepts of duty for the recovery of solely economic losses in public construction cases.

BACKGROUND

Design-bid-build contracts

Under the “design-bid-build” project delivery method utilized by the City in this case, the owner first enters into a contract with an architect and/or engineer (“A/E” or “design professional”) to design the project. Typically, the engineering and design is completed before the owner releases a request for proposals for a general contractor to perform the work. 2 1 Bruner & O’Connor Construction Law § 2:11 (2015). Under this method:

(1) the design is fully developed and completed before the pricing of the work, thus, presumably resulting in lowest cost, and (2) selection among responsible and responsive bidders can be made on the basis of price alone ... the contractor is excluded from contributing to the design process ...

*428 Id. The A/E and the contractor each have a contract with the owner, but they have no contractual relationship with each other.

In contrast, integrated delivery methods, such as “design-build,” create a single point of responsibility because the A/E and the contractor are bound under a single contract with the owner. Id. at § 2:12. Typically the contractor who is part of a design-build team is involved in aspects of the design of a project from the beginning, and the A/E remains involved— normally in an oversight and advisory role — during the construction phase. Id.; 5 Bruner & O’Connor Construction Law § 17:52 (2015) (explaining the modern trend to minimize the A/E’s previous “substantial involvement in the construction process” to a lesser obligation to “observe the work and determine in general if the work is being performed in accordance with the contract documents.”). 3

The traditional design-bid-build model often engenders tensions between the A/E and the construction contractor, as explained in one treatise on the subject:

A fundamental difficulty in allocating liability under the design-bid-build model is the inherent tension between the *429 interests of the architect and contractor. Some contractors believe they can increase profits through change orders that are based on ambiguities, errors, or omissions in the architect’s design. Architects have an interest in protecting their designs, and frequently serve as the owner’s representative during construction. In these situations, it benefits the architect to resist any suggestion that the design is flawed and deny change order requests based on defective plans and specifications.
Because of these competing interests, it can be difficult for the owner to determine whether the architect or contractor is responsible for a delay.... To complicate matters further, it may not be possible to join the architect and contractor in a single action[.]

Robert F. Cushman et al., Proving & Pricing Construction Claims § 9.03[A][1] (3d ed.2015). As discussed further infra, under traditional design-bid-build contracts, especially in the public sector, the contractor normally has a contractual entitlement to recover against the owner for construction delays and other benefit-of-the-bargain damages caused by the A/E’s defective specifications and designs.

RK & K’s Professional Engineering Services Contract

According to the complaint, 4 sometime prior to October 2009, 5 the City entered into a contract with RK & K for the design of two interrelated projects to upgrade the plant, termed the “Enhanced Nutrient Removal Facilities.” According to BBII, the City’s contract with RK & K specified that RK & K was to produce accurate, complete, and correct *430 construction designs and drawings for use by the successful bidder(s) who would construct the plant upgrades. RK & K’s duties and responsibilities allegedly included, but were not limited to:

• Development of the design for the two interrelated projects;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
130 A.3d 1024, 226 Md. App. 420, 2016 Md. App. LEXIS 3, 2016 WL 360875, Counsel Stack Legal Research, https://law.counselstack.com/opinion/balfour-beatty-infrastructure-inc-v-rummel-klepper-kahl-llp-mdctspecapp-2016.