Village of Cross Keys, Inc. v. United States Gypsum Co.

556 A.2d 1126, 315 Md. 741, 1989 Md. LEXIS 71
CourtCourt of Appeals of Maryland
DecidedMay 3, 1989
Docket36 and 37, September Term, 1987
StatusPublished
Cited by57 cases

This text of 556 A.2d 1126 (Village of Cross Keys, Inc. v. United States Gypsum Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Village of Cross Keys, Inc. v. United States Gypsum Co., 556 A.2d 1126, 315 Md. 741, 1989 Md. LEXIS 71 (Md. 1989).

Opinion

McAULIFFE, Judge.

The Council of Unit Owners of Harper House Condominium sued the Village of Cross Keys, Inc. (VCK) and the Rouse Company (Rouse), contending that VCK and Rouse, as developers of the Harper House building, were respon *744 sible for damages resulting from defective exterior walls. VCK and Rouse, hereinafter referred to collectively as the developer, 1 in turn sued Frank O. Gehry & Associates, Inc., the design architect, for indemnity or contribution. 2 The developer and the architect each sued United States Gypsum Company (USG), claiming that they relied upon USG’s design for the construction of the exterior walls, and that the design and certain representations concerning it were faulty. USG filed motions to dismiss, contending, among other things, that: it had not designed a proprietary exteri- or wall system; any representations it made concerning a generic system shown in its brochure were accurate; it had not contracted with anyone in connection with the construction of the Harper House building; its materials were not involved in the construction of the exterior walls; and, it owed no legal duty to the developer or to the architect. Judge Thomas E. Noel of the Circuit Court for Baltimore City treated USG’s motions as motions for summary judgment and, after considering the voluminous depositions and exhibits that had been produced by extensive discovery, granted the motions. The trial judge then entered final judgment in favor of USG, expressly finding that there was no just reason for delay. Maryland Rule 2-602(b). The developer and the architect appealed, and we granted certiorari before consideration by the Court of Special Appeals.

This appeal presents interesting and difficult questions concerning potential liability for negligence. In this case, petitioners’ claim that a tort duty must be imposed upon one who has erred generates the specter of “liability in an indeterminate amount for an indeterminate time to an inde *745 terminate class,” a liability that concerned Justice Cardozo in Ultramares Corporation v. Touche, 255 N.Y. 170, 174 N.E. 441, 444 (1931), and continues to concern courts today. We are asked to consider the sometimes subtle difference between a cause of action for negligence in general and one for negligent misrepresentation, and whether the difference is material here. Additionally, we are asked to revisit the question of economic loss versus risk of physical harm, and the impact of each type of damage upon the question of how far a duty should extend. See Council of Co-Owners v. Whiting-Turner, 308 Md. 18, 517 A.2d 336 (1986). For a better understanding of the context in which these questions arise, we set forth a more detailed description of the underlying facts.

The building in question is a 15 story, 194 unit, luxury high-rise condominium. The developer began planning for construction in the late 1960’s, and construction specifications were issued in March 1974. Shortly after completion of the building in 1976, water leaks were reported in various units throughout the building, and to date at least 50 units have shown evidence of intrusion of water from the outside. The developer attempted several corrective measures, but was not successful. The exterior wall system was examined by a number of experts, who predictably came to somewhat different conclusions concerning the cause of the problem. There is substantial evidence, however, to support the contention of the developer that the only adequate means of correcting the defective conditions that now exist involve the complete removal of the brick veneer, replacement or correction of the backup wall system as required, and installation of new brick. This work has begun, and according to the developer will cost 15-20 million dollars, in addition to the 3 million dollars already expended in the initial remedial measures.

The extensive record already developed in this case suggests there may be multiple causes of the exterior wall problem, including deficiencies in materials, workmanship, supervision, design, and specifications. Petitioners contend *746 that at least a substantial cause of the problem may be the design of the brick veneer, steel stud, curtain wall system used in the building — a design they say was developed, published and promoted by IJSG.

Curtain wall systems have been employed by the building industry for some time. A curtain wall is not a part of the structural skeleton of the building, as would be a weight bearing wall. It simply spans an upper and lower deck (or floor) of the building, enclosing that floor. A wall system consists of the exterior surface, such as brick or stucco, the interior surface, such as plaster, gypsum board, or paneling, and the core or “backup” to which each surface is in some manner connected. The curtain wall used in this building consists of an exterior surface of one wythe of laid-up 4 inch brick, and a backup of 2-1/2 inch steel studs fastened into steel runners at the top and bottom. Exterior sheathing is attached to the outside of the steel studs, and interior gypsum board (wallboard) is attached to the inside. The exterior wall of brick for each floor rests on an angle iron that is fastened to the concrete deck at the base of each floor, and is laid so that there is an air space of approximately 1 inch between the brick and the sheathing. To provide additional support for the brick wall, and apparently to transfer some part of the forces exerted on the brick wall to the backup structure, metal ties, called wall ties or brick ties, are placed at specified intervals. In this system, the ties used are corrugated metal strips, 1 inch wide and several inches long, with a galvanized coating. These ties are supposed to be securely screwed to the steel studs at the same time as or after the exterior sheathing is attached, and the free end of each tie is then to be inserted into a bed of mortar between the bricks as the wall is laid.

Brick veneer walls are not new. Until the mid-1960’s, however, metal stud systems had not been used as a backup for brick veneer on high-rise buildings. Rather, concrete or other masonry walls were used as backup in such cases. For low-rise commercial and residential buildings, a wooden stud system often served as the backup for a brick veneer *747 wall. As metal stud systems proved increasingly popular for use in constructing interior non-load bearing walls, the manufacturers of those systems turned their attention to the potential of utilizing steel studs as a backup for exterior walls in high-rise buildings. USG’s interest is documented by an internal report dated 14 July 1964, which stated:

At present the U.S. Gypsum Company does not participate in the curtain wall market to any appreciable extent. The development of “the curtain wall system” has been undertaken to allow the company to expand into this very large and potentially profitable area.

Six years later, another USG internal report evaluated the market in these terms:

The curtain wall market is huge. If we could make only a 1%

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lavine v. American Airlines
Court of Special Appeals of Maryland, 2025
Brady v. Walmart Inc
D. Maryland, 2024
Steamfitters Local v. Erie Insurance
233 A.3d 59 (Court of Appeals of Maryland, 2020)
Steamfitters Local Union No. 602 v. Erie Ins. Exch.
209 A.3d 158 (Court of Special Appeals of Maryland, 2019)
Dowling v. A.R.T. Inst. of Wash., Inc.
372 F. Supp. 3d 274 (D. Maryland, 2019)
Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP
155 A.3d 445 (Court of Appeals of Maryland, 2017)
Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP
130 A.3d 1024 (Court of Special Appeals of Maryland, 2016)
Cash & Carry America, Inc. v. Roof Solutions, Inc.
117 A.3d 52 (Court of Special Appeals of Maryland, 2015)
White v. Kennedy Krieger Institute, Inc.
110 A.3d 724 (Court of Special Appeals of Maryland, 2015)
Premium of America, LLC v. Sanchez
73 A.3d 343 (Court of Special Appeals of Maryland, 2013)
112 West 34th Street Associates, LLC v. 112-1400 Trade Properties LLC
95 A.D.3d 529 (Appellate Division of the Supreme Court of New York, 2012)
Sapp v. Ford Motor Co.
687 S.E.2d 47 (Supreme Court of South Carolina, 2009)
Gourdine v. Crews
955 A.2d 769 (Court of Appeals of Maryland, 2008)
Doe v. Pharmacia & Upjohn Co.
879 A.2d 1088 (Court of Appeals of Maryland, 2005)
Cooper v. Berkshire Life Insurance
810 A.2d 1045 (Court of Special Appeals of Maryland, 2002)
Fried v. Archer
775 A.2d 430 (Court of Special Appeals of Maryland, 2001)
Smith v. Washington Metropolitan Area Transit Authority
133 F. Supp. 2d 395 (D. Maryland, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
556 A.2d 1126, 315 Md. 741, 1989 Md. LEXIS 71, Counsel Stack Legal Research, https://law.counselstack.com/opinion/village-of-cross-keys-inc-v-united-states-gypsum-co-md-1989.