Donatelli v. D.R. Strong Consulting Eng'rs, Inc.

CourtWashington Supreme Court
DecidedNovember 14, 2013
Docket86590-6
StatusPublished

This text of Donatelli v. D.R. Strong Consulting Eng'rs, Inc. (Donatelli v. D.R. Strong Consulting Eng'rs, Inc.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donatelli v. D.R. Strong Consulting Eng'rs, Inc., (Wash. 2013).

Opinion

FILE IN CLERKS OFFICE 11J1REME COURT, STATE OF WASHING10tl OATE .NOV 1 4 2013

Wq c4•£afi· This oplnJOnwas filed for record' at g ; oc; arO on "'('"' tj , 2-o 13

·6~~ ~onalc! R. Carpenier ~upreme Court Clerk

IN THE SUPREME COURT OF THE STATE OF WASHINGTON

STEVE and KAREN DONATELLI, ) a married couple, ) ) Respondents, ) No. 86590-6 ) v. ) ENBANC ) D.R. STRONG CONSULTING ) NOV 14 2013 Filed: ----------------- ENGINEERS, INC., a Washington ) corporation, ) ) Petitioner. ) ________________________) FAIRHURST, J.-Steve and Karen Donatelli hired D.R. Strong Consulting

Engineers Inc. to help the Donatellis develop their real property. Before

development of the property could be completed, however, the Donatellis suffered

substantial financial losses and lost the property in foreclosure. The Donatellis

sued D.R. Strong for breach of contract, violation of the Consumer Protection Act

(CPA), chapter 19.86 RCW, negligence, and negligent misrepresentation. D.R.

Strong moved for partial summary judgment on the CPA and negligence claims. Donatelli v. D.R. Strong, No. 86590-6

D.R. Strong argued that the negligence claims must be dismissed under the

economic loss rule because the relationship between the parties was governed by

contract and the damages claimed by the Donatellis were purely economic. The

trial court and Court of Appeals held that as a matter of law, the Donatellis'

negligence claims were not barred. We affirm.

I. FACTUAL AND PROCEDURAL HISTORY

The Donatellis consulted with and hired D.R. Strong to help the Donatellis

develop their King County real property into two short plats. According to Steve

Donatelli, D.R. Strong's representatives orally agreed to help the Donatellis with

the county permitting process and to manage the project "through to [the] final

recording of the short plats." Clerk's Papers (CP) at 65. In their complaint, the

Donatellis alleged that D.R. Strong agreed to:

a. Perform the necessary surveys and analyses; b. Create the required plans for, inter alia, soil erosion, storm water drainage; c. Prepare the necessary reports and County permit applications; and d. Take all other actions necessary to get the short plats recorded with King County so that Donatelli could build houses on each lot.

CP at 2. According to the Donatellis, D.R. Strong represented that it would be able

to finish the project within "approximately one and [one-half] years, if not less

time." CP at 4.

D.R. Strong's first involvement in the project was apparently helping the

Donatellis apply for preliminary approval for the project with King County 2 Donatelli v. D.R. Strong, No. 86590-6

pursuant to King County Code 19A.08.150. King County granted preliminary

approval on October 4, 2002. In its letter granting preliminary approval, the county

noted that the "preliminary approval is valid for a period of 60 months." CP at 28.

On October 11, 2002, D.R. Strong sent the Donatellis a written contract for

engineering services entitled "Revised Proposal for Engineering Services." CP at

21. In the contract, D.R. Strong agreed to perform six phases of engineering

services in exchange for an estimated fee totaling $33,150. The contract did not

reflect whether D.R. Strong agreed to provide managerial services or to oversee the

day-to-day operation of the project. The contract limited D.R. Strong's

professional liability to $2,500 or its professional fee, whichever was greater.

Steve Donatelli apparently signed the contract on October 31, 2002, although he

now claims that he did not know what he was signing.

According to the Donatellis, between October 2002 and October 2007, D.R.

Strong assumed a managerial role over the project and worked closely with other

contractors, builders, and vendors involved with the project. See CP at 67 (D.R.

Strong "ran the daily operations of the Project."); id. at 68 (D.R. Strong "[was]

running the show."). Although in the written contract D.R. Strong estimated its fee

would be $33,150, D.R. Strong allegedly charged the Donatellis "approximately

$120,000 in costs and fees" over the course of the project. CP at 2.

3 Donatelli v. D.R. Strong, No. 86590-6

In October 2007, the preliminary approval expired and the project was still

not complete. The expiration of the preliminary approval came as a complete

surprise to the Donatellis. According to Steve Donatelli, employees ofD.R. Strong

"apologized many times, said that they screwed up, and that they would make

everything right." CP at 67. D.R. Strong began the process of obtaining a new

preliminary approval for the project. Before D.R. Strong could obtain a new

preliminary approval, however, the Donatellis suffered substantial financial losses

and eventually lost the property in foreclosure.

The Donatellis sued D.R. Strong, claiming damages in excess of $1.5

million and alleging breach of contract, CPA violations, negligence, and negligent

misrepresentation. D.R. Strong moved for partial summary judgment on the CPA,

negligence, and negligent misrepresentation claims. D.R. Strong argued that the

economic loss rule barred the Donatellis' negligence claims. The trial court denied

summary judgment on the two negligence claims but granted summary judgment

on the CPA claims. The trial court found that "professional negligence claims can

be stated even in the context of a contractual relationship." CP at 95.

The Court of Appeals affirmed, holding that the independent duty doctrine

did not bar the Donatellis from bringing negligence claims against D.R. Strong

because professional engineers owe duties to their client independent of any

contractual relationship. Donatelli v. D.R. Strong Consulting Eng 'rs, Inc., 163

4 Donatelli v. D.R. Strong, No. 86590-6

Wn. App. 436, 443, 261 P.3d 664 (2011). We granted D.R. Strong's petition for

review. Donatelli v. D.R. Strong Consulting Eng'rs, Inc., 173 Wn.2d 1025, 272

P.3d 851 (2012).

II. ISSUES

A. Did the trial court properly deny summary judgment as to the Donatellis' negligence claim when there were genuine issues of material fact regarding the scope ofD.R. Strong's contractual obligations to the Donatellis?

B. Did the trial court properly deny summary judgment as to the Donatellis' negligent misrepresentation claim when the Donatellis alleged D.R. Strong misrepresented the time and expense necessary to complete the project and such representations induced the Donatellis to contract with D.R. Strong?

III. STANDARD OF REVIEW

Typically, we review an order on summary judgment de novo, engaging in

the same inquiry as the trial court. Mohr v. Grantham, 172 Wn.2d 844, 859, 262

P.3d 490 (2011). Summary judgment is appropriate when "there is no genuine

issue as to any material fact and ... the moving party is entitled to a judgment as a

matter of law." CR 56(c). In this case, the trial court did not consider whether

there were genuine issues of material fact underlying D.R. Strong's motion for

summary judgment because the motion presented a purely legal question-does

the economic loss rule bar the Donatellis from bringing claims of negligence and

negligent misrepresentation against D.R. Strong? We review alleged errors of law

de novo. Jongeward v. BNSF Ry., 174 Wn.2d 586, 592, 278 P.3d 157 (2012)

(citing State v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emrich v. Connell
716 P.2d 863 (Washington Supreme Court, 1986)
Hartley v. State
698 P.2d 77 (Washington Supreme Court, 1985)
DePhillips v. Zolt Const. Co.
959 P.2d 1104 (Washington Supreme Court, 1998)
Jarrard v. Seifert
591 P.2d 809 (Court of Appeals of Washington, 1979)
American Nursery Products, Inc. v. Indian Wells Orchards
797 P.2d 477 (Washington Supreme Court, 1990)
Snyder v. Lovercheck
992 P.2d 1079 (Wyoming Supreme Court, 1999)
Alverado v. Washington Public Power Supply System
759 P.2d 427 (Washington Supreme Court, 1988)
Seattle Western Industries, Inc. v. David A. Mowat Co.
750 P.2d 245 (Washington Supreme Court, 1988)
Mithoug v. Apollo Radio of Spokane
909 P.2d 291 (Washington Supreme Court, 1996)
State v. Knott
493 P.2d 1027 (Court of Appeals of Washington, 1972)
Gilliland v. Elmwood Properties
391 S.E.2d 577 (Supreme Court of South Carolina, 1990)
US Life Credit Life Ins. v. Williams
919 P.2d 594 (Washington Supreme Court, 1996)
Stuart v. Coldwell Banker Commercial Group, Inc.
745 P.2d 1284 (Washington Supreme Court, 1987)
Skagit State Bank v. Rasmussen
745 P.2d 37 (Washington Supreme Court, 1987)
National Bank v. Equity Investors
506 P.2d 20 (Washington Supreme Court, 1973)
MA Mortenson Co. v. Timberline Software Corporation
998 P.2d 305 (Washington Supreme Court, 2000)
Haberman v. Washington Public Power Supply System
750 P.2d 254 (Washington Supreme Court, 1988)
Griffith v. Centex Real Estate Corp.
969 P.2d 486 (Court of Appeals of Washington, 1998)
Presnell Construction Managers, Inc. v. EH Construction, LLC
134 S.W.3d 575 (Kentucky Supreme Court, 2004)
White v. State
929 P.2d 396 (Washington Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Donatelli v. D.R. Strong Consulting Eng'rs, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/donatelli-v-dr-strong-consulting-engrs-inc-wash-2013.