Presnell Construction Managers, Inc. v. EH Construction, LLC

134 S.W.3d 575, 2004 Ky. LEXIS 114, 2004 WL 1123761
CourtKentucky Supreme Court
DecidedMay 20, 2004
Docket2000-SC-0571-DG
StatusPublished
Cited by134 cases

This text of 134 S.W.3d 575 (Presnell Construction Managers, Inc. v. EH Construction, LLC) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Presnell Construction Managers, Inc. v. EH Construction, LLC, 134 S.W.3d 575, 2004 Ky. LEXIS 114, 2004 WL 1123761 (Ky. 2004).

Opinions

OPINION OF THE COURT

I. ISSUE

DeLor Design Group, Inc. (“DeLor”), the owner of a commercial building, contracted with Appellant, Presnell Construction Managers, Inc. (“Presnell”), to act as the construction manager for the building’s renovation (“the Project”). DeLor also contracted with Appellee, EH Construction, LLC (“EH”), to provide “general trades” work for the Project. EH, claiming exclusively economic losses1 from Presnell’s failure to perform properly its contractual duty to coordinate the Project, filed a suit against Presnell in which it brought claims premised upon Presnell’s alleged negligent misrepresentation and negligent supervision of the Project. The trial court found that, under the contract, Presnell owed a duty only to DeLor and therefore dismissed EH’s claims against Presnell. Was EH entitled to maintain an action in tort against Presnell to recover for its alleged economic loss? Because we adopt § 552 of the Restatement (Second) of Torts as the standard for negligent mis[577]*577representation in Kentucky, and because EH’s complaint against Presnell alleged “Presnell ... supplied faulty information and guidance” to the Project’s contractors, we hold that the trial court improperly dismissed EH’s claim for negligent misrepresentation against Presnell. Accordingly, we affirm the Court of Appeals and remand this case to the trial court for further proceedings.

II. BACKGROUND

The material facts involving the issues now before this Court are straightforward and undisputed. In May 1996, DeLor, as part of its efforts to renovate a commercial building owned by it, contracted with Pres-nell to act as construction manager for the Project. DeLor and Presnell completed and signed an American Institute of Architects (“AIA”) document styled, “Standard Form of Agreement Between Owner and Construction Manager where the Construction Manager is NOT a Constructor.” The contract set forth the duties and obligations that DeLor and Presnell owed to each with respect to the Project, and paragraph 10.7 of the contract provides: “Nothing contained in - this Agreement shall create a contractual relationship with or a cause of action in favor of a third party against either the Owner or the Construction Manager.”

Later, in March 1997, DeLor contracted with EH to furnish what the contract referred to as “general trades” work for the Project. DeLor and EH completed and signed an AIA document styled, “Standard Form of Contract Between Owner and Contractor.” The contract set forth the duties and obligations that DeLor and EH owed to each other with respect to the Project. Paragraph 1.1.20 of Article 1 of the contract provides:

The Contractor agrees that nothing contained in the Contract Documents or any agreement between the Owner and the Construction Manager or the Owner and the Design Professional creates any contractual relationship between the Construction Manager ... and the Contractor. The Contractor waives any right the Contractor may have as an alleged third-party beneficiary of any such agreements and covenants not to sue the Construction Manager ... as a third-party beneficiary of such agreements.

And, finally, paragraph 2.1.1 of Article 2 of the contract provides: “The Construction Manager shall administer the Contract as described herein. The Construction Manager in performing under this Contract is acting as the Owner’s principal agent in all matters regarding this Contract.”

After the signing of the contracts, both Presnell and EH, along with other contractors and subcontractors on the Project, proceeded to renovate DeLor’s building under their contracts with DeLor.

However, in November 1997, EH filed a mechanics’ and materialman’s lien in the sum of $268,218.00 against the real property on which the Project was located for unpaid materials and labor that EH claimed that it had furnished to DeLor for the Project. In February 1998, EH filed suit to enforce its lien against DeLor,2 Presnell, and others.3 EH also sought to [578]*578recover damages for its economic losses, which EH alleged were the result of Pres-nell’s alleged negligent misrepresentation and negligent supervision of the Project.4 Specifically, EH’s complaint alleged that Presnell failed “to properly stage and time the work involved” for the Project and that as a result, EH “was required to redo much of the work that it had already completed, due to the other contractors and subcontractors coming in and subsequently destroying work that had already been completed by [EH].” Additionally, EH alleged that “Presnell was careless and negligent in coordinating the Project, and supplied faulty information and guidance and supervision to the contractors working on the Project.”

Presnell filed a motion to dismiss EH’s negligence claims on the ground that it owed no duty to EH.5 The trial court agreed, found that Presnell’s duties under the contract were owed exclusively to De-Lor, and dismissed EH’s claim against Presnell. The Court of Appeals, however, adopted § 552 and held that EH’s tort claim against Presnell was actionable because, under § 552, Presnell owed independent duties, i.e., “a duty to EH to exercise reasonable care or competence in its supervision, collection, and distribution of information and directions that it provided to EH for guidance.” As a result, the Court of Appeals reversed the trial court and remanded the case for trial on EH’s negligent misrepresentation claim against Presnell.6 We granted Presnell’s motion for discretionary review, and we now affirm the decision of the Court of Appeals.

III. ANALYSIS

A proper analysis and resolution of the issues presented by this appeal requires an analysis of two (2) separate topics, i.e.: (1) privity of contract and (2) the tort of negligent misrepresentation. We will discuss each topic in turn and then apply them to this case.

[579]*579A. PRIVITY OF CONTRACT

“Privity of contract” is “[t]he relationship between parties to a contract, allowing them to sue each other but preventing a third party from doing so.”7 Thus, “[o]rdinarily, the obligations arising out of a contract are due only to those with whom it is made; a contract cannot be enforced by a person who is not a party to it or in privity with it, except under a real party in interest statute or, under certain circumstances, by a third-party beneficiary.”8 Consequently, “[a]s a general rule, whenever a wrong is founded upon a breach of contract, the plaintiff suing in respect thereof must be a party or privy to the contract, and none but a party to a contract has the right to recover damages for its breach against any of the parties thereto.” 9

“It is well established that a third person may, in his own right and name enforce a promise made for his benefit even though he is a stranger both to the contract and to the consideration.”10 But, “[n]ot every contract will give one who is not privy thereto a right of action therein, even though such third party might have received a benefit from the completion of the contract.”11

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
134 S.W.3d 575, 2004 Ky. LEXIS 114, 2004 WL 1123761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/presnell-construction-managers-inc-v-eh-construction-llc-ky-2004.