Salt Lake City Corp. v. Erm-West, Inc.

984 F. Supp. 2d 1156, 2013 WL 5873292, 2013 U.S. Dist. LEXIS 156313
CourtDistrict Court, D. Utah
DecidedOctober 30, 2013
DocketCase No. 2:11-CV-1174 TS
StatusPublished
Cited by1 cases

This text of 984 F. Supp. 2d 1156 (Salt Lake City Corp. v. Erm-West, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Salt Lake City Corp. v. Erm-West, Inc., 984 F. Supp. 2d 1156, 2013 WL 5873292, 2013 U.S. Dist. LEXIS 156313 (D. Utah 2013).

Opinion

MEMORANDUM DECISION AND ORDER GRANTING ERM’S MOTION TO DISMISS

TED STEWART, District Judge.

This matter is before the Court on Defendant ERM-West, Inc.’s (“ERM”) Motion to Dismiss.1 The Court heard oral argument on ERM’s Motion on October 24, 2013. Having considered the arguments raised at oral argument, reviewed the materials submitted by the parties, and being otherwise fully informed, the Court will grant ERM’s Motion.

I. BACKGROUND

This dispute arises from the environmental remediation of hydrocarbon-impacted sediments from a section of the Northwest Oil Drain (“NWOD”) Canal. On August 12, 2003, Plaintiffs Salt Lake City Corporation (the “City”), BP Products North America, Inc. (“BP”), and Chevron USA, Inc. (“Chevron”) (referred to collectively as “Plaintiffs”) entered into an Administrative Order on Consent (the “AOC”) with the Environmental Protection Agency (“EPA”) to conduct remediation on the NWOD Canal. Plaintiffs formed an association called the Northwest Oil Drain Working Group (the ‘Working Group”) to carry out this obligation.

Pursuant to the AOC, Plaintiffs were required to effect complete physical removal of hydrocarbon-impacted sediments from the NWOD canal. The AOC also specifically required that the Working Group designate a project coordinator to be responsible for administration of the actions required under the AOC. On August 23, 2003, the City entered into a Professional Services Agreement (the “PSA”) with ERM on behalf of the Working Group.

In oral argument, Plaintiffs represented that the PSA was entered into prior to the AOC. The timing of the execution of the PSA is not readily ascertainable from the documents attached as exhibits to Plaintiffs’ Complaint. However, the allegations of Plaintiffs’ Second Amended Complaint provide that the AOC was entered into on August 12, 2003, and the PSA was entered into on August 23, 2003. For purposes of this Motion, the Court will accept as true the allegations of Plaintiffs’ Second Amended Complaint.

According to the Recitals of the PSA, ERM was to: (1) “provide the [Working Group] Project Management Services to oversee the construction phase of the Northwest Oil Drain clean up;” (2) “handle all ‘daily duties’ that are required consistent with the remedial alternative selected;” and (3) “assist the Working Group in preparing submittals required in the AOC.”2 Pursuant to the PSA, ERM’s services were to “be performed in accordance with the best professional judgment and skill.”3

[1158]*1158ERM was to assist the Working Group in selecting a remediation contractor, including developing project technical specifications, construction bid documents, and managing the bidding process.4 As Project Manager, ERM was also required to develop a work plan to accomplish the complete removal of hydrocarbon-impacted sediments that included, among other documents, a Quality Assurance Project Plan and Sampling and Analysis Plan to ensure completion of project objectives.5 “As Project Manager, ERM was required to ‘monitor all work items for compliance with project documents.’ ”6 “During construction, ERM was to ‘manage all daily elements of the implementation’ to ensure that all project requirements were met, including the project’s ultimate goal of complete physical removal of all hydrocarbon-impacted sediments.”7

On January 15, 2004, the Working Group sent a letter to the EPA designating ERM as its “Project Coordinator to oversee work in the PRP Group Work Area, as defined in the AOC.”8 “In short, ERM was hired and designated as the Working Group’s agent to coordinate the remediation of the NWOD Canal and ensure compliance with the AOC on behalf of the Working Group.”9

The subject of the instant Motion is Plaintiffs’ fifth cause of action for breach of agency duties, brought on behalf of all Plaintiffs against ERM. Plaintiffs allege that they “hired ERM as their Project Coordinator and agent to administer the Working Group’s duties under the AOC, and they specifically designated ERM as their representative and agent to the EPA.”10 Plaintiffs further allege that ERM “consented to such an agency relationship by ... specifically providing in the Compass Contract (which ERM drafted) that it was the OWNER’S representative and agent and by acting as such throughout the course of the NWOD Project.” 11

According to Plaintiffs, ERM breached its duties as Plaintiffs’ agent by: (1) “failing to ensure compliance with project objectives;” 12 (2) “failing to perform its services in accordance with the best professional judgment and skill, as required by the PSA;”13 (3) “recommending a deficient remediation technology;”14 (4) “developing a deficient sampling method and failing to even ensure proper implementation of that method;”15 (5) “failing to properly oversee the construction;”16 (6) “certifying that the project was complete and allowing Compass to demobilize when in fact project objectives had not been met;” 17 and (7) “by failing to adequately inform the Working Group of the gravity of the sampling exceedances and of its failure to obtain proper approval from the EPA for those exceedances.”18

[1159]*1159II. STANDARD OF REVIEW

In considering a motion to dismiss for failure to state a claim upon which relief can be granted under Rule 12(b)(6), all well-pleaded factual allegations, as distinguished from conclusory allegations, are accepted as true and viewed in the light most favorable to Plaintiffs as the nonmoving party.19 Plaintiffs must provide “enough facts to state a claim to relief that is plausible on its face,”20 which requires “more than an unadorned, the-defendant-unlawfully harmed-me accusation.”21

“A pleading that offers ‘labels and conclusions’ or ‘a formulaic recitation of the elements of a cause of action will not do.’ Nor does a complaint suffice if it tenders ‘naked assertion[s]’ devoid of ‘further factual enhancement.’ ”22 “The court’s function on a Rule 12(b)(6) motion is not to weigh potential evidence that the parties might present at trial, but to assess whether the plaintiffs complaint alone is legally sufficient to state a claim for which relief may be granted.”23

As the Court in Iqbal stated,

only a complaint that states a plausible claim for relief survives a motion to dismiss. Determining whether a complaint states a plausible claim for relief will ... be a context-specific task that requires the reviewing court to draw on its judicial experience and common sense. But where the well-pleaded facts do not permit the court to infer more than the mere possibility of misconduct, the complaint has alleged — but it has not show[n] — that the pleader is entitled to relief.24

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
984 F. Supp. 2d 1156, 2013 WL 5873292, 2013 U.S. Dist. LEXIS 156313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/salt-lake-city-corp-v-erm-west-inc-utd-2013.