Sunridge Development Corp. v. RB & G Engineering, Inc.

2010 UT 6, 230 P.3d 1000, 649 Utah Adv. Rep. 28, 2010 Utah LEXIS 5, 2010 WL 391858
CourtUtah Supreme Court
DecidedFebruary 5, 2010
Docket20080160
StatusPublished
Cited by32 cases

This text of 2010 UT 6 (Sunridge Development Corp. v. RB & G Engineering, Inc.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunridge Development Corp. v. RB & G Engineering, Inc., 2010 UT 6, 230 P.3d 1000, 649 Utah Adv. Rep. 28, 2010 Utah LEXIS 5, 2010 WL 391858 (Utah 2010).

Opinion

NEHRING, Justice:

INTRODUCTION

¶ 1 In this case we address the legal relationships created by an assignment. In particular, we examine the scope of an assignee’s right to recover damages from a third party that breached a contract made with, or duty owed to, the assignor. Respondent RB & G, an engineering firm, persuaded a majority of the court of appeals that while it may have breached a contract or duty before the key assignment occurred, the assignee could not recover damages sustained after the date of the assignment. Petitioners Sunridge Development Corporation and Sunridge Enterprises, LLC, argue that an assignee may recover damages that flow from a breach of an assigned contract regardless of when the actual damages occur. We reverse the court of appeals and remand to the district court.

BACKGROUND

¶ 2 In the 1960s, Stephen Stewart formed Sunridge Development Corporation (SDC). In 1981, SDC purchased a parcel of property in Provo, Utah, for the purpose of developing the property into Alpine Brook, a residential development. In 1993, SDC contracted with RB & G Engineering, Inc., a geological engineering firm, to obtain a geologic study of the property. SDC commissioned another geologic report from RB & G in 1995. The two reports describe geologic features of the property, make recommendations for foundation design, and include depictions of the subdivision and the planned units.

¶ 3 In 1996, Mr. Stewart formed Sunridge Enterprises, LLC (Enterprises). 1 Mr. Stewart was the principal of Enterprises, which was the entity that took on the responsibility for developing the Provo property into Alpine Brook. Development of the property then commenced. Mr. Stewart made a statement in a deposition suggesting that when he formed Enterprises, SDC transferred the property and made certain assignments to Enterprises, including an assignment of all rights and claims under the RB & G reports. The documents evidencing the development agreement, transfer of the property, and assignment are not a part of the record in this case.

¶4 In 1998, the Utah Geologic Survey, a division within the Department of Natural Resources, sent Provo City a letter expressing its concern that the RB & G reports did not adequately address the seriousness of the geologic faults on the property. Provo City responded to the Survey’s concerns by requiring Enterprises to expand setbacks within the Alpine Brook development to mitigate the risks associated with the faults. By the time Provo City mandated these changes, Enterprises had completed the design of certain portions of the development. The site *1002 revisions required by Provo City resulted in a loss of fourteen units, amounting to a claimed loss of over one million dollars. Delays in development, redesign, and attorney fees resulted in additional costs.

¶ 5 Petitioners claim that RB & G failed to notify SDC and Enterprises of the geologic condition of the site in the reports. In early February, SDC sued RB & G for breach of contract and negligence. SDC later amended its complaint to include Enterprises as a plaintiff. SDC and Enterprises sought to recover for the loss of the fourteen units as well as additional “administrative costs,” which included the costs of delay, redesign, and attorney fees. As discovery progressed, RB & G moved for summary judgment on SDC’s negligence claims and Enterprises’ breach of contract and negligence claims. The district court granted summary judgment against both SDC and Enterprises on their negligence claims, concluding that the economic loss rule barred any recovery in negligence. The court also granted summary judgment against Enterprises on its breach of contract claim. The court reasoned that Enterprises could not recover damages from RB & G because it could not stand in a better position than its assignor, SDC. The court explained that because RB & G had fully performed its contracts with SDC, the assignment only transferred SDC’s rights to pursue remedies for existing, not future, breaches of those contracts. Therefore, because the loss of the fourteen units occurred after the assignment, Enterprises could not recover those damages from RB & G because SDC never had the right to recover such damages. The court further concluded that the assignment did not establish privity between Enterprises and RB & G or otherwise entitle Enterprises to pursue its alleged damages.

¶ 6 A year later, RB & G moved for summary judgment on SDC’s remaining breach of contract claims, which sought recovery for the “administrative costs.” The district court granted summary judgment to RB & G because SDC had not supported its damage summary with evidence eligible for consideration by the court under Utah Rule of Civil Procedure 56(c) before the discovery period closed. The parties agreed not to appeal the second summary judgment of SDC’s breach of contract claims.

¶ 7 Petitioners appealed the first summary judgment and the case was transferred to the Utah Court of Appeals. Specifically, Petitioners argued that Enterprises could recover as an assignee of the RB & G reports for damages that occurred after the assignment and/or that SDC could recover in negligence. The court of appeals declined to address the merits of the appeal. Instead, the court of appeals held that because SDC’s contract damages were dismissed on summary judgment, Enterprises could not recover as an assignee because “ ‘an assignee gains nothing more, and acquires no greater interest than had his assignor....’” Sunridge Dev. Corp. v. RB & G Eng’g, Inc., 2008 UT App 29, ¶ 8, 177 P.3d 644 (quoting Aird Ins. Agency v. Zions First Nat’l Bank, 612 P.2d 341, 344 (Utah 1980)). The court of appeals reasoned that Enterprises was subject to SDC’s failure to timely present evidence of the damages at issue in the second summary judgment because “assignment merely allows the assignee to stand in the shoes of the assignor.” Id. ¶ 9. Judge Bench dissented. He reasoned that “[although an assignee’s damages are limited to those damages the assignor would have suffered, the assignee should not be required to depend upon the assignor to litigate on its behalf.” Id. ¶ 15 (Bench, J. dissenting). Judge Bench noted that a determination of Enterprises’ rights, if any, to pursue claims under the RB & G contracts needed to be addressed before analyzing any effect the second summary judgment might have had on Enterprises. Id.

¶ 8 We granted certiorari to determine whether the majority of the court of appeals’ panel erred in its assessment of the effect of the judgments rendered by the district court. We have jurisdiction pursuant to Utah Code section 78A-3-102(3)(a) (2008).

STANDARD OF REVIEW

¶ 9 On certiorari review, we review the decision of the court of appeals, not the decision of the district court. See Massey v. Griffiths, 2007 UT 10, ¶ 8, 152 P.3d 312.

*1003 ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2010 UT 6, 230 P.3d 1000, 649 Utah Adv. Rep. 28, 2010 Utah LEXIS 5, 2010 WL 391858, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunridge-development-corp-v-rb-g-engineering-inc-utah-2010.