Interwest Construction v. Palmer

886 P.2d 92, 1994 WL 677960
CourtCourt of Appeals of Utah
DecidedMarch 21, 1995
Docket930219-CA
StatusPublished
Cited by15 cases

This text of 886 P.2d 92 (Interwest Construction v. Palmer) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interwest Construction v. Palmer, 886 P.2d 92, 1994 WL 677960 (Utah Ct. App. 1995).

Opinions

OPINION

ORME, Associate Presiding Judge:

This appeal arises from a rather complicated, multi-party construction dispute. Thiokol Corporation appeals the judgment in favor of appellees Interwest Construction and A.H. Palmer & Sons.1 We affirm.

FACTS

All parties acknowledge that the trial court’s factual findings withstand challenge under the clearly erroneous standard. See Jacobs v. Hafen, 875 P.2d 559, 561 (Utah App.1994). We recite the facts accordingly.

[95]*95In the fall of 1988, Interwest agreed to construct a waste treatment facility for Thiokol. On December 1, 1988, Interwest subcontracted with Palmer to provide materials and perform the labor necessary for the construction of part of the treatment facility. Pursuant to the subcontract agreement, Palmer was to provide, among other things, three fiberglass waste-water storage tanks designated as T32, T33, and T34. On February 28, 1989, Palmer entered into a purchase order agreement with Fiberglass Structures, Inc., under which Fiberglass Structures agreed to manufacture and install the storage tanks.

Upon completion of the tanks on April 30, 1989, Thiokol tested the three storage tanks. During the trial test, -tank T34 ruptured. Following the failure of T34, Thiokol negotiated directly with Fiberglass Structures to determine the cause of the failure, replace the ruptured tank, and repair the remaining tanks in accordance with Thiokol’s original specifications. In an angry exchange of letters and professional opinions, Thiokol’s project engineer vehemently disagreed with Fiberglass Structures’ assessment of the tanks’ deficiencies and the proposed solution.2

On May 1, 1989, Thiokol inspected the waste treatment plant and notified Interwest that it considered the facility to be substantially complete, notwithstanding the rupture of T34 the previous day and the repairs to the tanks that would necessarily be required. Under Thiokol’s supervision, Fiberglass Structures replaced the failed tank and reinforced the existing tanks according to the design specifications suggested by Fiberglass Structures and approved by Thiokol. Thiok-ol tested and accepted the three tanks based on its determination that the tanks were built according to these plans and specifications. Interwest and Palmer were not directly involved in these negotiations or the ensuing remedial actions.

Thiokol began operating the waste treatment facility during the summer of 1989. Sometime after June 2, 1989, Thiokol modified the three tanks, changing the method of filling the tanks from the gravity feed system specified in Thiokol’s own plans and specifications to an overhead feed. On August 24, 1989, a Thiokol employee overfilled T33, resulting in the tank holding some 3,000 gallons in excess of its proper capacity. Had Thiokol not altered the method by which the tanks were filled, it would not have been possible to overfill the tanks.' In the early morning hours of August 24, tank T33 ruptured, spilling its liquid-waste contents. At the time the tank failed, Thiokol owed Interwest $200,000 under the contract. Of this amount, Inter-west owed Palmer $93,673.70. Thiokol withheld the balance due Interwest as compensation for the damages Thiokol alleged it suffered as a result of the tank’s failure, and Interwest, in turn, withheld payment from Palmer.

PROCEEDINGS BELOW

The posture of this case is unusual in that Interwest did not sue Thiokol for the amount due under the contract, nor did Thiokol sue Interwest for breach of warranty, negligence, or breach of contract. Instead, Interwest commenced this action by filing a complaint against Palmer for breach of contract, indemnity, negligence, and breach of warranty. Interwest also sought indemnification from Palmer for attorney fees, costs, and expenses incurred as a result of the tank failure.3 Interwest later filed an amended complaint adding Thiokol as a defendant, and in addition to restating its claim against Palmer, sought recovery from Thiokol under theories of breach of contract and unjust enrichment. Palmer filed a third-party complaint against Fiberglass Structures, which, in turn, filed a third-party complaint against Thiokol. Thiokol responded by bringing counterclaims and third-party complaints against Fiber[96]*96glass Structures and Palmer and a counterclaim against Interwest.

Before the trial court, Thiokol claimed In-terwest, Palmer, and Fiberglass Structures breached their contracts because the tanks were not manufactured in accordance with contract specifications, did not meet industry standards, and were defective in design and manufacture. Thiokol also claimed that In-terwest, Palmer, and Fiberglass Structures (1) breached numerous express warranties, as well as the implied warranties of fitness and merchantability, (2) negligently breached their duty of care, and (3) were strictly liable for designing, manufacturing, and supplying the defective tanks and creating a dangerous condition.

At trial, the cause of the tank’s failure was vehemently disputed. The trial court received documents and exhibits and heard substantial testimony concerning the issue of causation. After carefully evaluating the evidence,4 the court made the following findings:

Notwithstanding evidence to the contrary the Court finds that the tanks were built'pursuant to Thiokol’s design specifications. There is little question, however, that the tanks were under-designed, that they did not have sufficient hoop or tensile strength and likely may have eventually failed in any regard.
[[Image here]]
... Thiokol knew of the wall thickness or lack thereof and of the safety concerns and accepted tanks T32, T33 and T34 with said deficiencies. Whatever deficiencies there may have been were fully accepted by Thiokol.
[[Image here]]
The installation of pumps and an overhead method of filling the tanks allowed Thiokol to fill the tanks beyond their capacity. The Court finds that this was the most likely cause of the failure. The Court further finds that an overfilling of the tank would not have occurred had the gravity feed system remained in place....
The Court finds that the overfilling was most likely the cause of the failure which created an uplifting force on the tank which the tank was not designed to withstand.

Having found that the tanks were built according to Thiokol’s own specifications, that Thiokol accepted the tanks knowing they were structurally deficient, and that tank T33 failed because Thiokol unilaterally modified the tank, thereby making it possible for one of its own employees to overfill the tank and subject it to pressure which it was not designed to withstand, the trial court ruled against Thiokol and awarded Interwest the $200,000 it was due under the contract. Likewise, Interwest was ordered to pay Palmer the $93,673.70 owed for the work it performed. In accordance with this judgment, the court dismissed Thiokol’s claims with prejudice. Thiokol appeals.

BREACH OF CONTRACT

Thiokol does not challenge the trial court’s factual findings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Welty v. Retirement Board
2017 UT App 26 (Court of Appeals of Utah, 2017)
Salt Lake City Corp. v. Erm-West, Inc.
984 F. Supp. 2d 1156 (D. Utah, 2013)
ASC Utah, Inc. v. Wolf Mountain Resorts, L.C.
2010 UT 65 (Utah Supreme Court, 2010)
In Re Estate of Flake
2003 UT 17 (Utah Supreme Court, 2003)
Fisher Sand & Gravel Co. v. South Dakota
1997 SD 8 (South Dakota Supreme Court, 1997)
Consolidated Realty Group v. Sizzling Platter, Inc.
930 P.2d 268 (Court of Appeals of Utah, 1996)
Cortez v. University Mall Shopping Center
941 F. Supp. 1096 (D. Utah, 1996)
Sullivan v. Vernay Products, Inc
91 F.3d 242 (First Circuit, 1996)
Interwest Construction v. Palmer
923 P.2d 1350 (Utah Supreme Court, 1996)
Allred v. Brown
893 P.2d 1087 (Court of Appeals of Utah, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
886 P.2d 92, 1994 WL 677960, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interwest-construction-v-palmer-utahctapp-1995.