D.M. Ward Constr. Co v. Elec. Corp. of Kan. City

803 P.2d 593, 15 Kan. App. 2d 114, 1990 Kan. App. LEXIS 950
CourtCourt of Appeals of Kansas
DecidedDecember 28, 1990
Docket64,824
StatusPublished
Cited by20 cases

This text of 803 P.2d 593 (D.M. Ward Constr. Co v. Elec. Corp. of Kan. City) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.M. Ward Constr. Co v. Elec. Corp. of Kan. City, 803 P.2d 593, 15 Kan. App. 2d 114, 1990 Kan. App. LEXIS 950 (kanctapp 1990).

Opinion

Wahl, J.:

This is a contract dispute between Electric Corporation of Kansas City (Electric Corp.) and D.M. Ward Construction Co., Inc. (Ward). Ward appeals the trial court’s judgment refusing to compel arbitration of this dispute and refusing to grant Ward a setoff from the judgment entered for Electric Corp.

In 1985, Ward, a general contractor, contracted with Distron, Inc., a division of Burger King Corporation, to build a warehouse-distribution center in Kansas City, Kansas. Ward selected Electric Corp. as the electrical contractor for the project, and the parties entered into a written subcontract on September 30, 1985. Ward supplied the American Institute of Architects standard form subcontract agreement that the parties used. The subcontract contained a provision stating: “All claims, disputes and other matters in question arising out of, or relating to, this subcontract . . . shall be decided by arbitration.”

The warehouse was to contain office space, storage space, and large drive-in refrigerator and freezer units which occupied ap *116 proximately 30 or 40 percent of the floor space of the warehouse. The refrigerated portions of the warehouse were to be cooled by a computerized ammonia cooling system, which included a sensitive ammonia detection system.

During construction, Electric Corp. was called upon to perform several tasks which were not included in the subcontract with Ward. Ward also requested Electric Corp. to install temperature control wiring for the ammonia system, believing such wiring to be part of Electric Corp.’s subcontract. Electric Corp. disputed this claim, arguing the only temperature control wiring it agreed to install was that relating to the heating and cooling systems for the office area. Electric Corp. believed the temperature control wiring for the ammonia system was the responsibility of the refrigeration contractor, Preston Refrigeration. Ward eventually hired another electrical contractor, Broadway Electrical Construction (Broadway), to install the ammonia system wiring.

Electric Corp. completed its work on the warehouse on January 14, 1987, but as of March 23, 1987, had not been paid the full contract price or for the extra work performed, so Electric Corp. filed a mechanic’s lien against the property. Ward made further payments to Electric Corp. after the lien was filed, but still owed Electric Corp. approximately $20,000 a year later. Electric Corp. brought suit against Ward and Burger King in March 1988 to collect the balance due. Ward filed an answer on April 11, 1988, but the answer did not mention the arbitration clause of the subcontract.

In December 1988, following discovery, the court set the matter for trial on January 10, 1989, then on December 21, 1988, reset trial for February 7, 1989. On January 3, 1989, Ward filed a motion to compel arbitration and stay the trial court’s proceedings pursuant to K.S.A. 5-402(a). The appearance docket indicates the trial court denied this motion on January 20, 1989, but no journal entry was filed.

Ward’s defenses at trial were that Electric Corp. had not adequately performed under the contract, that it did not promptly submit some of the bills for the extra work in a timely manner as required by the subcontract, and that Electric Corp.’s labor charges were unreasonable. Ward also claimed a setoff for *117 amounts paid to Broadway to complete the temperature control wiring for the ammonia system.

The trial court found the subcontract was ambiguous on whether Electric Corp. was required to install the ammonia system temperature control wiring and construed the contract strictly against Ward. The trial court also found Electric Corp.’s charges were reasonable and its billings were timely submitted, except for two items which were billed late. The trial court found, however, the late billing on these items did not prejudice Ward and thus allowed Electric Corp. to recover for them. The trial court entered judgment in favor of Electric Corp. for $23,932.46.

Ward filed a post-trial motion to alter or amend the judgment, alleging K.S.A. 5-402(a) required the trial court to compel arbitration when it was requested by Ward. Ward also argued that the trial court erred in not allowing a setoff based on the undisputed evidence at trial that the parties had a clear understanding of what the term “temperature control Wiring” meant. The trial court denied Ward’s motion in total and Ward timely appeals.

On appeal, Ward argues the trial court erred in refusing to compel arbitration becáuse: (1) the subcontract requires arbitration of all disputes; (2) K.S.A. 5-402(a) requires the trial court to compel arbitration when requested by a party; (3) arbitration agreements are statutorily recognized and their enforceability sup-' ported by Kansas case law; and (4) Ward did not waive its right to arbitration. Electric Corp. contends Ward’s tardy attempt to compel arbitration was barred by waiver, estoppel, or laches.

Waiver is “an intentional renunciation of a claim or right and exists only where there has been some absolute action or inaction inconsistent with that claim or right.” Proctor Trust Co. v. Neihart, 130 Kan. 698, 705, 288 Pac. 574 (1930). Waiver of a contract right “ ‘implies a voluntary and intentional renunciation of it, and some positive act or positive inaction inconsistent with .the contract right is necessary to create a waiver. [Citations omitted. ]’” 130 Kan. at 705. See Rice v. Hillenburg, 13 Kan. App. 2d 155, 161, 766 P.2d 182 (1988), rev. denied 244 Kan. 738 (1989).

There is no journal entry in the record denying Ward’s motion to compel arbitration. However, the trial court explained its reason for denying the motion in its decision denying Ward’s post- *118 trial motion to alter or amend the judgment. The journal entry provides:

“[T]he court originally denied the defendant’s request for arbitration, due to the fact that the trial was set to commence on February 2, 1989, and the motion to compel arbitration was not filed and brought to the attention of the court until January 3, 1989. The court found at that time that provisions for arbitration are generally included in contracts so that matters might be settled in shorter periods of time, and to grant arbitration in this case would have the effect of actually delaying the process of adjudication of the dispute. The court finds no sufficient reason to disturb that prior ruling on this issue.”

K.S.A. 5-402(a) clearly requires a trial judge to stay court proceedings and compel arbitration when the parties have entered into a binding agreement to arbitrate disputes. In this respect, Kansas law is virtually identical to the provisions of the Federal Arbitration Act. See 9 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Torbol
Court of Appeals of Kansas, 2018
In re Marriage of Sinks
Court of Appeals of Kansas, 2016
Portfolio Recovery Associates, LLC v. Dixon
366 P.3d 245 (Court of Appeals of Kansas, 2016)
Pla-Fit Franchise v Patricko et al.
2013 DNH 109 (D. New Hampshire, 2014)
American Federation of State v. City of Albuquerque
2013 NMCA 049 (New Mexico Court of Appeals, 2013)
AFSCME v. City of Albuquerque
2013 NMCA 49 (New Mexico Court of Appeals, 2012)
Colgan Air, Inc. v. Raytheon Aircraft Co.
404 F. Supp. 2d 893 (E.D. Virginia, 2005)
Jones-Williams Construction Co. v. Town & Country Property, L.L.C.
923 So. 2d 321 (Court of Civil Appeals of Alabama, 2005)
Hales v. ProEquities, Inc.
885 So. 2d 100 (Supreme Court of Alabama, 2003)
In Re Marriage of Brotherton
59 P.3d 1025 (Court of Appeals of Kansas, 2002)
Scott Addison Const. Inc. v. Lauderdale County School System
789 So. 2d 771 (Mississippi Supreme Court, 2001)
Liberty Builders, Inc. v. Horton Ex Rel. Estate of Horton
521 S.E.2d 749 (Court of Appeals of South Carolina, 1999)
Malarky Enterprises v. Healthcare Technology, Ltd.
962 F. Supp. 1427 (D. Kansas, 1997)
Beeson v. Erickson
917 P.2d 901 (Court of Appeals of Kansas, 1996)
Interwest Construction v. Palmer
886 P.2d 92 (Court of Appeals of Utah, 1995)
In Re Doe
866 P.2d 1069 (Court of Appeals of Kansas, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
803 P.2d 593, 15 Kan. App. 2d 114, 1990 Kan. App. LEXIS 950, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dm-ward-constr-co-v-elec-corp-of-kan-city-kanctapp-1990.