Phelps Dodge Copper Products Corp. v. Alpha Construction Co.

455 P.2d 555, 203 Kan. 591, 1969 Kan. LEXIS 493
CourtSupreme Court of Kansas
DecidedJune 14, 1969
Docket45,364
StatusPublished
Cited by24 cases

This text of 455 P.2d 555 (Phelps Dodge Copper Products Corp. v. Alpha Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phelps Dodge Copper Products Corp. v. Alpha Construction Co., 455 P.2d 555, 203 Kan. 591, 1969 Kan. LEXIS 493 (kan 1969).

Opinion

The opinion of the court was delivered by

Fontron, J.:

This is an action by Phelps Dodge Copper Products Corporation, herein called plaintiff or Phelps Dodge, against the defendants, Alpha Construction Company and Fidelity and Casualty Company of New York, herein referred to as Alpha or defendants, to recover for copper products sold and delivered to Alpha in the total amount of $292,684.22.

The defendants filed an answer generally admitting the plaintiff’s allegations but cross claiming for damages resulting to Alpha from delays in delivery allegedly amounting to $184,416.08. Phelps Dodge eventually recovered judgment against both defendants for $136,392.71 plus interest in an amount of some $27,000, and the defendants have appealed. The real bone of contention in this lawsuit is over the interest allowed, as will become apparent later in this opinion.

The copper products supplied to Alpha were for its use on two REA telephone construction projects, one being in Kansas and tire other in Oklahoma. The materials were furnished at an agreed price and payment therefor was due 30 days from date of invoice. It was admitted by the defendants that the copper products were delivered from November, 1964 to October, 1965, and the last date of delivery was found by the trial court to be October 22,1965.

A motion for summary judgment was filed by Phelps Dodge, and in response thereto the trial court found that the total indebtedness due on account, as alleged in plaintiff’s petition, was not in dispute but was admitted by the defendants. Accordingly tire court ruled that the burden would rest on Alpha, when the case was tried, to go forward with the evidence on its setoff or counterclaim.

Pursuant to the court’s ruling Alpha proceeded, at time of trial, to introduce evidence supporting its claim for delay damages. Trial was terminated June 28, 1967, when the parties stipulated to the following effect: Alpha was to have judgment entered for $57,000 *593 on its claim for delay damages; judgment was to be entered for Phelps Dodge for $292,684.22 less Alpha’s $57,000 setoff; the question of whether Phelps Dodge was entitled to interest was reserved for submission to the court at a later date; and execution on plaintiff’s judgment was withheld pending receipt by Alpha of certain retainages due on its projects, to be paid on plaintiff’s judgment.

A few months later the matter of plaintiff’s right to recover interest was presented to the court, and on September 21, 1967, the court addressed the following letter to counsel for both sides:

“Gentlemen:
On the 6th day of September, 1967, the court heard argument as to the amount of interest due Phelps Dodge Copper Products Corporation from Alpha Construction Company.
After reading the briefs and studying the law, the court makes the following findings of fact and conclusions of law:
1. That the last delivery date to Alpha Construction was the 22d day of October, 1965.
2. That under the tenms of the orders, the net balance due was within 30 days, or on or before the 22d day of November, 1965.
3. That the balance due as of November 22d, 1965, was $292,684.22, and that said sum liquidated as of the last said date.
4. That interest is due plaintiff at the rate of 6 per cent per annum from said date on the said sum, less the amount of set-off said set-off being in the sum of $57,000. It is therefore the court’s conclusion that interest at the rate of 6 per cent annum is due plaintiff from defendant on the sum of $235,684.22, from the 22d day of November, 1965, until said sum is paid.
The court would appreciate a journal entry to this effect being drawn and submitted to counsel for signatures and sent to the court for signature and filing.
Sincerely,
/s/ A. B. Fletcher, Jr.
District Judge, Division 2”

Difficulty was encountered in preparing a satisfactory journal entry, and on November 17, 1967, Phelps Dodge filed a motion requesting the court to prepare and sign the order of judgment in the event disagreements of counsel could not be resolved. On December 6, 1967, a journal entry of judgment was filed with the clerk, signed by the court but not approved by counsel, reciting that judgment was entered for plaintiff on December 4, 1967, the judgment including interest from November 22, 1965, on the difference between the $292,684.22 due Phelps Dodge for merchandise sold and the $57,000 due Alpha for delay damages, with allowance being given for payments made by Alpha after June 28, 1967.

*594 Additional facts will come to light throughout the course of this opinion.

The defendants’ first contention is that the trial court erred in holding that the Phelps Dodge claim became liquidated as of November 22, 1965, and in allowing interest from that date on the balance, that is, on the difference between what was due Phelps Dodge and what was due Alpha. In support of this contention, Alpha argues that interest cannot be recovered on an unliquidated claim until the amount due thereon is ascertained, and that the amount ultimately due Phelps Dodge could not be ascertained until Alpha’s claim for delay damages was settled, both as to liability and as to amount.

On the other hand, Phelps Dodge contends that its claim against Alpha for merchandise sold and delivered toas liquidated on November 22, 1965, since the amount Alpha was to pay for the materials sold to it and the date of payment therefor were both definitely fixed by agreement of the parties. Such being so, Phelps Dodge maintains that only Alpha’s claim for damages remained unliquidated and that its unliquidated setoff for damages will not prevent the accrual of interest on the balance due on plaintiff’s liquidated claim.

As appears from the letter set out earlier in this opinion, the trial court accepted the view urged by Phelps Dodge, and in rendering judgment for Phelps Dodge included interest on the balance due on its account against Alpha, after deducting Alpha’s stipulated damages. In so doing we believe the court was correct.

There has been no dispute as to what Alpha owed Phelps Dodge for goods sold and delivered, nor as to terms of payment. The agreed price was admitted by Alpha in response to a request for admissions and the date of payment was established by invoice as 30 days after date. The pleadings established that materials were supplied by Phelps Dodge from November, 1964 to October, 1965, the trial court found, without objection, that the final delivery date was October 22, 1965. Thus payment was due November 22, 1965.

Under the undisputed facts there can be little doubt that plaintiff’s claim became liquidated as of November 22, 1965, thus entitling the plaintiff to interest. In the early case of Gas Co. v. Schliefer, 22 Kan. 468, this court held:

“An account showing the delivery of goods at a time stated, prima facie

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lindsey Masonry Co. v. Murray & Sons Construction Co.
390 P.3d 56 (Court of Appeals of Kansas, 2017)
First National Bank v. Sankey Motors, Inc.
204 P.3d 1167 (Court of Appeals of Kansas, 2009)
Owen Lumber Co. v. Chartrand
157 P.3d 1109 (Supreme Court of Kansas, 2007)
Kansas Mun. Gas Agency v. Vesta Energy Co., Inc.
843 F. Supp. 1401 (D. Kansas, 1994)
Burrowwood Associates, Inc. v. Safelite Glass Corp.
853 P.2d 1175 (Court of Appeals of Kansas, 1993)
Kilner v. State Farm Mutual Automobile Insurance
847 P.2d 1292 (Supreme Court of Kansas, 1993)
J. Walters Construction Co. v. Greystone South Partnership, L.P.
817 P.2d 201 (Court of Appeals of Kansas, 1991)
D.M. Ward Constr. Co v. Elec. Corp. of Kan. City
803 P.2d 593 (Court of Appeals of Kansas, 1990)
In Re Tax Protests of Midland Industries, Inc.
703 P.2d 840 (Supreme Court of Kansas, 1985)
Johnson v. General Motors Corp.
668 P.2d 139 (Supreme Court of Kansas, 1983)
Arrowhead Construction Co. v. Essex Corp.
662 P.2d 1195 (Supreme Court of Kansas, 1983)
Equity Investors, Inc. v. Academy Insurance Group, Inc.
625 P.2d 466 (Supreme Court of Kansas, 1981)
Fairway Builders, Inc. v. Malouf Towers Rental Co.
603 P.2d 513 (Court of Appeals of Arizona, 1979)
First National Bank v. Bankers Dispatch Corporation
562 P.2d 32 (Supreme Court of Kansas, 1977)
La Villa Fair v. Lewis Carpet Mills, Inc.
548 P.2d 825 (Supreme Court of Kansas, 1976)
In Re the Estate of Penn
531 P.2d 133 (Supreme Court of Kansas, 1975)
Garrett v. American Family Mutual Insurance Co.
520 S.W.2d 102 (Missouri Court of Appeals, 1974)
Westamerica Securities, Inc. v. Cornelius
520 P.2d 1262 (Supreme Court of Kansas, 1974)
Mentzer v. Mentzer
512 P.2d 320 (Supreme Court of Kansas, 1973)
Urban Renewal Agency v. Reed
508 P.2d 1227 (Supreme Court of Kansas, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
455 P.2d 555, 203 Kan. 591, 1969 Kan. LEXIS 493, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phelps-dodge-copper-products-corp-v-alpha-construction-co-kan-1969.