Arrowhead Construction Co. v. Essex Corp.

662 P.2d 1195, 233 Kan. 241, 1983 Kan. LEXIS 305
CourtSupreme Court of Kansas
DecidedApril 29, 1983
Docket54,193
StatusPublished
Cited by31 cases

This text of 662 P.2d 1195 (Arrowhead Construction Co. v. Essex Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arrowhead Construction Co. v. Essex Corp., 662 P.2d 1195, 233 Kan. 241, 1983 Kan. LEXIS 305 (kan 1983).

Opinion

The opinion of the court was delivered by

Herd, J.:

This is an action for breach of contract. The appeal is from the trial court’s order granting judgment on the counterclaims of Frank Crotts and Glenn Henley.

A contract for the construction of a low-income housing project in Lakin is the issue from which this case arose. The original contract for the project was let to Essex Corporation as the general contractor on March 15, 1978. On March 23, 1978, Essex acquired a “Labor and Material Payment Bond” from Inland Insurance Company and Universal Surety Company.

Essex subcontracted the job to Heritage Construction Management Company. Pursuant to a contract dated April 21, 1978, Heritage subcontracted to Arrowhead Construction Company of Dodge City. Arrowhead then discussed a possible subcontract for some of the work with Frank Crotts and Glenn Henley. The existence of a firm contract between Crotts and Henley and Arrowhead is a matter of dispute and will be discussed in more detail later. Nevertheless, Crotts and Henley began work on the Lakin project on June 6, 1978, and completed a substantial portion of the work they set out to perform.

During the course of the construction project Heritage became concerned by the failure of Arrowhead to complete the job. As a result Heritage hired another contractor to finish the project. Arrowhead’s last day on the Lakin project was August 3, 1978. On August 15, 1978, Arrowhead filed a mechanics’ lien statement against the premises claiming a balance due from Heritage of $21,768.00. Crotts and Henley, in turn, filed a mechanics’ lien on August 30, 1978, claiming a balance due from Arrowhead of $6897.00.

On December 11, 1978, Arrowhead filed a petition in Kearny County District Court listing as defendants Essex, Universal, Inland, Heritage, the City of Lakin and Crotts and Henley. The petition alleged Heritage breached its contract by failing to pay money owing to Arrowhead. It also alleged Essex was liable for *243 Heritage’s debt as general contractor and that Universal and Inland were liable for the debt on the labor and material payment bond. Finally, it asked that the priority of Crotts and Henley’s lien be determined in the same action. Crotts and Henley filed their answer asking the court to determine the liability of Essex, Universal and Inland. In their counterclaim against Arrowhead they alleged the existence of a contract between the two parties pursuant to which Arrowhead would pay Crotts and Henley $8397.00. Crotts and Henley claimed they performed their part of the bargain but that Arrowhead had paid them only $1500.00. Finally, Crotts and Henley filed a cross-claim alleging Essex, as the general contractor, was liable for Arrowhead’s breach and that Universal and Inland were liable as sureties.

The other corporate defendants, Essex, Universal, Inland, and Heritage, were represented by John G. Sauer of Garden City. They filed their answer on February 9, 1979. With respect to Arrowhead’s petition they offered twelve defenses, including the ninth which alleged, “Plaintiff cannot recover upon the labor and material payment bond because it failed to comply with the notice requirements thereof.” In its counterclaim to Arrowhead’s petition these defendants alleged breach of contract by Arrowhead.

With regard to Crotts and Henley’s cross-claim these defendants offered nine defenses. Their fourth defense alleged, “Defendants Crotts and Henley cannot recover upon the labor and material payment bond because they failed to comply with the notice requirements thereof.” The seventh defense claimed, “Defendants Crotts and Henley cannot recover against any of these defendants because it lacks privity of contract with them.” The eighth defense asserted, “Defendants Crotts and Henley are not a proper claimant under the labor and material bond as they have no direct contract with the principal, Defendant Essex Corporation, or with the sub-contractor of the principal, defendant Heritage Construction Management Company.”

On April 30, 1979, the defendants Essex, Universal, Inland, and Heritage, filed a “Motion for Judgment on the Pleadings” asking the court to discharge the liens previously filed by Arrowhead and Crotts and Henley. In support of this motion the defendants alleged the labor and material payment bond ac *244 quired by Essex was a “statutory public works” bond pursuant to K.S.A. 60-1111 which authorizes the discharge of previously filed liens when such a bond is filed with the district court.

On May 7, 1979, the district court issued an “Order Granting Judgment on the Pleadings.” The court found the bond complied with K.S.A. 60-1111 as a public works bond and as such discharged the liens previously filed by Crotts and Henley and Arrowhead.

The May 7 order was the result of a compromise between the parties pursuant to which, on July 9, 1979, attorney Sauer filed “amendments” to the defendants’ answers to the claims of Arrowhead and Crotts and Henley. The defendants admitted Arrowhead had complied with the notice requirements of the labor and material payment bond, thereby abandoning their ninth defense.

With regard to the claims of Crotts and Henley the defendants’ answer was amended to admit the allegations Essex was liable as general contractor in the absence of payment by its subcontractors and that Crotts and Henley had fully complied with the notice requirements of the labor and material payment bond. Accordingly, the defendants abandoned their defenses against Crotts and Henley dealing with privity and the notice requirements of the bond.

Armed with these admissions Crotts and Henley filed their own motion for judgment on the pleadings July 3, 1980, alleging Arrowhead had admitted the allegations in their counterclaims by failing to answer. On August 13, 1980, the trial court held: “[T]he only factual controversy as to the amount due the defendants Crotts and Henley and the quality of their work is a question as to whether or not a certain overhang was built incorrectly . . . .” The court further found “this small controversy is separable from the other controversies involved in the case . . .” and ordered it tried as a separate matter.

Previously, on October 18, 1979, attorney Sauer withdrew from the case and left the practice of law for another occupation. It was not until shortly before the court’s order on August 13, 1980, severing the trial that defendants’ present counsel, Mr. Kenneth Peirce, entered the case.

A year later on September 11, 1981, a pretrial conference was held. At that time the trial of Crotts and Henley’s claim was set *245 for September 22, 1981. The other issues were tentatively set for trial January 12, 1982. With regard to the claims of Crotts and Henley the court further stated in part:

“[I]f Crotts and Henley are successful in their claim for monies due and owing from Arrowhead, said sums shall be paid by Universal Surety Company and/or Inland Insurance Company. The Court finds as its basis for such ruling:
“1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Doe v. M.J.
508 P.3d 368 (Supreme Court of Kansas, 2022)
John Doe v. M.J.
482 P.3d 596 (Court of Appeals of Kansas, 2021)
Miller Trust v. Cox
Court of Appeals of Kansas, 2020
Law Co. Building Associates v. Law
444 P.3d 376 (Court of Appeals of Kansas, 2019)
Law Company Building Associates v. Law
Court of Appeals of Kansas, 2019
Lindsey Masonry Co. v. Murray & Sons Construction Co.
390 P.3d 56 (Court of Appeals of Kansas, 2017)
City of Hiawatha v. Rural Water Dist. No. 2
Court of Appeals of Kansas, 2015
Navair, Inc. v. IFR Americas, Inc.
519 F.3d 1131 (Tenth Circuit, 2008)
NEA-Coffeyville v. Unified School District No. 445
996 P.2d 821 (Supreme Court of Kansas, 2000)
Dimension Graphics, Inc. v. Liebowitz
994 P.2d 658 (Court of Appeals of Kansas, 1999)
Offices Togolais Des Phosphates v. Mulberry Phosphates, Inc.
62 F. Supp. 2d 1316 (M.D. Florida, 1999)
Amoco Production Co. v. Hugoton Energy Corp.
11 F. Supp. 2d 1270 (D. Kansas, 1998)
Miller v. Botwin
899 P.2d 1004 (Supreme Court of Kansas, 1995)
United States Fidelity & Guaranty Co. v. Burress
844 F. Supp. 1475 (D. Kansas, 1994)
Island Directory Co. v. Iva's Kinimaka Enterprises, Inc.
859 P.2d 935 (Hawaii Intermediate Court of Appeals, 1993)
J. Walters Construction Co. v. Greystone South Partnership, L.P.
817 P.2d 201 (Court of Appeals of Kansas, 1991)
Shade v. Wheatcraft Industries, Inc.
809 P.2d 538 (Supreme Court of Kansas, 1991)
Kansas Workers Compensation Fund v. W. F. Anderson Co.
798 P.2d 949 (Court of Appeals of Kansas, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
662 P.2d 1195, 233 Kan. 241, 1983 Kan. LEXIS 305, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arrowhead-construction-co-v-essex-corp-kan-1983.