Lindsey Masonry Co. v. Murray & Sons Construction Co.

390 P.3d 56, 53 Kan. App. 2d 505, 2017 WL 461213, 2017 Kan. App. LEXIS 14
CourtCourt of Appeals of Kansas
DecidedFebruary 3, 2017
Docket114812
StatusPublished
Cited by21 cases

This text of 390 P.3d 56 (Lindsey Masonry Co. v. Murray & Sons Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lindsey Masonry Co. v. Murray & Sons Construction Co., 390 P.3d 56, 53 Kan. App. 2d 505, 2017 WL 461213, 2017 Kan. App. LEXIS 14 (kanctapp 2017).

Opinions

Hill, J.:

This is an appeal by Murray & Sons Construction Company of the trial court’s holding that it had breached an implied-in-fact contract with Lindsey Masonry Company by not paying for all of die services performed. Along with the contract payments, the trial court awarded interest, costs, and attorney fees as authorized by the Kansas Fairness in Public Construction Contracts Act. Our review of the extensive record leads us to conclude that we must affirm the judgments of the trial court.

With no signed contracts, a general contractor and a masonry company work together on several public school projects.

The Blue Valley School District decided to build four buildings: the Blue Valley Elementary School #22, die . New Highlands Elementary School, Blue Valley Southwest High School Sports Field Buildout, and Blue Valley Middle School #10. Over a span of several months, the school district sought and received separate bids on each project. Murray & Sons bid on the projects as the general contractor and asked Lindsey Masomy to submit bids on the projects for the masonry work (labor only).

Blue Valley picked Murray as the general contractor on each of these projects and Lindsey became Murrays masonry subcontractor for all four buildings. A pattern of business then developed between the two companies as the work progressed. For each building project, Lindsey submitted to Murray a written proposal that [507]*507included the names of the parties, the identification of the project, the price, the scope of work, exclusions from the scope of work, and the identification of the plans, specifications, and drawings that applied to each.

Each of Lindseys proposals indicated that the parties would later sign an AIA Document A-401 Standard Form Agreement between Contractor and Sub-Contractor. (This form is supplied by The American Institute of Architects.) The proposals also contained language regarding the timing of payments and listed the percentage of retainage to be withheld.

After that, Murray would include the price from each of Lind-seys proposals in its bids to Blue Valley.

After Murray was awarded the contract on each project, it asked Lindsey to be the masonry subcontractor. Lindsey then sent Murray a schedule of values for each project. The schedule of values, essentially, is a price list that sets out each masonry task to be performed. Lindsey used the schedule of values when it prepared its pay applications to Murray and, in turn, Murray used the same schedule of values when it prepared its pay applications to Blue Valley.

After each successful bid on each project, Lindsey signed and sent an AIA form subcontract to Murray to sign. In return, Murray sent a signed AGC subcontract form to Lindsey for its signature. (This is a contract form supplied by the Associated General Contractors of Kansas, Inc.) Neither party signed the form contracts sent by the other company. As far as we can tell from this record, no written agreements were ever signed by both parties, except for some specific change orders signed in the midst of construction.

Nevertheless, Murray authorized Lindsey to begin work on each project and Lindsey did so. Lindsey periodically submitted pay applications to Murray and received periodic payments from Murray. As the buildings progressed, Murray submitted pay applications to the owner and received payments from Blue Valley. After payment, Lindsey would return partial hen waivers that reflected the amount of the payment.

Unfortunately, the working relationship between Murray and Lindsey deteriorated, and Lindsey walked off the Blue Valley #10 [508]*508job before completing the masonry work. Later, Lindsey filed a lawsuit seeking money from Murray. In its lawsuit, Lindsey claimed damages for money due on each of the projects, asserting alternative theories of recovery based on breach of contract, promissory estoppel, and quantum meruit. Murray denied liability and asserted counterclaims against Lindsey on each project.

The parties submitted the case to the judge.

At trial, both Lindsey and Murray agreed about the identity of the parties, the scope of work, and the original price, as modified by the fully executed change orders for each project. They did not agree on anything else.

In the end, the trial court found that the evidence failed to establish an express contract between the two companies. Instead, the court concluded that there was an implied-in-fact contract on each project for Lindsey to perform the masonry work described in the scope of work in exchange for the compensation set out in Lindseys proposal and schedule of values. The implied-in-fact contract contained no specific time for payment. The court made specific findings about each project. We list a brief summary of each.

Blue Valley #22

On the Blue Valley #22 project, the district court found that the parties agreed to a revised total compensation of $1,036,848 for the masonry work. Lindsey completed all of its work on the project, but received only $1,020,568 from Murray. The court found Murray in breach of contract for its failure to pay Lindsey the remaining balance of $15,916 and granted judgment in that amount.

The court denied Murrays counterclaim for $5,511 for the cost to repair a damaged portion of a roof. The court found that the parties’ conduct established an agreement that any changes in the work would be made by written change orders signed by both parties. Since Murray had submitted a change order for the roof repair and Lindsey had not signed it, Lindsey was not liable under the counterclaim. The district court awarded Lindsey interest, costs, and attorney fees under the Kansas Fairness in Public Construction Contract Act found at K.S.A. 16-1901 et seq. (not to be [509]*509confused with the Kansas Fairness in Private Construction Contract Act found at K.S.A. 16-1801 et seq.)

New Highlands

On the New Highlands project, the district court found that the parties agreed to a revised total compensation of $1,014,358. Lindsey completed its work, but $83,794 remained unpaid. The district court found Murray in breach of contract for failure to pay that amount.

The district court found Lindsey in breach of contract for not installing some steel rebar in the storm shelter walls on that project. Murray was entitled to recover $55,250 from Lindsey to remediate the rebar omission. In addition, Murray was entitled to recover $5,957 in damages to remediate some subsequent damage to the water proofing and a protection board.

The court set off Murrays damages against Lindsey’s damages, resulting in a net judgment of $22,587 awarded to Lindsey. In addition, the court awarded Lindsey interest, costs, and attorney fees under tire Act.

Sports Field Buildout

On the Sports Field Buildout project, the district court found that the parties agreed to a price of $123,590. The court found that $12,565 remained due to Lindsey and awarded judgment in that amount plus interest, costs, and attorney fees under the Act. The court denied Murrays counterclaim for $4,166 in damages for weather-related time extensions.

Blue Valley #10

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monarch Build v. DLH Holdings
567 P.3d 831 (Court of Appeals of Kansas, 2025)
Linlor v. Holman
D. Kansas, 2024
Johnson v. Creason
D. Kansas, 2023
Wesley Properties Management, Inc. v. Hill
Court of Appeals of Kansas, 2022
Ringel v. NueHealth
Court of Appeals of Kansas, 2021
Leavenworth County Bd. of Comm'rs v. Copeland
Court of Appeals of Kansas, 2020
Prellwitz Construction
Court of Appeals of Kansas, 2020
In re Estate of Ramsey
Court of Appeals of Kansas, 2020
Straightline HHD v. Smart E-Solutions
Court of Appeals of Kansas, 2020
Law Co. Building Associates v. Law
444 P.3d 376 (Court of Appeals of Kansas, 2019)
Law Company Building Associates v. Law
Court of Appeals of Kansas, 2019
Ramsey v. H&R Block Inc
W.D. Missouri, 2019

Cite This Page — Counsel Stack

Bluebook (online)
390 P.3d 56, 53 Kan. App. 2d 505, 2017 WL 461213, 2017 Kan. App. LEXIS 14, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lindsey-masonry-co-v-murray-sons-construction-co-kanctapp-2017.