Prellwitz Construction

CourtCourt of Appeals of Kansas
DecidedJuly 2, 2020
Docket121470
StatusUnpublished

This text of Prellwitz Construction (Prellwitz Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prellwitz Construction, (kanctapp 2020).

Opinion

NOT DESIGNATED FOR PUBLICATION

No. 121,470

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

PRELLWITZ CONSTRUCTION, INC., Appellee,

v.

NIGEL JONES, KYLE CHANSLER, and DONALD KIMBALL, Appellants.

MEMORANDUM OPINION

Appeal from Shawnee District Court; TERESA L. WATSON, judge. Opinion filed July 2, 2020. Affirmed.

Trevor C. Wohlford and Will B. Wohlford, of Morris, Laing, Evans, Brock & Kennedy, Chtd., of Topeka, for appellants.

Bryan W. Smith, of Smith Law Firm, of Topeka, for appellee.

Before ARNOLD-BURGER, C.J., WARNER, J., and LAHEY, S.J.

PER CURIAM: Kyle Chansler, Nigel Jones, and Donald Kimball (the Owners) appeal from the judgment in a lawsuit brought against them by the general contractor, Prellwitz Construction, Inc. (PCI), hired to build their home. Following a bench trial, the district court found for the general contractor on its breach of contract claim and on the Owners' counterclaims, including a claim under the Kansas Consumer Protection Act (KCPA), K.S.A. 50-623 et seq. The Owners argue the district court erred by (1) not ordering the general contractor to bear the costs of defending a lien foreclosure claim a

1 subcontractor brought; (2) holding the Owners breached the contract; and (3) holding the Owners failed to prove their KCPA claims. Finding no error by the district court, we affirm.

FACTUAL AND PROCEDURAL BACKGROUND

In 2013, the Owners bought land in Shawnee County, intending to build a home there. Jones, who is an architect, designed the home and drew up plans with input from Chansler and Kimball. In July 2016, the Owners began meeting with George Coe, project manager for PCI, which is owned by general contractor Mark Prellwitz.

Coe provided an initial bid proposal to the Owners that included a list of allowances, which Coe said were "realistic or perhaps strong" estimates of costs for certain items or work required for construction of the home. The allowance for excavation costs was $10,000, but the parties later agreed to increase it to $12,500 based on additional work the Owners desired. The proposal required an initial payment of $55,000 due upon signing of the contract, with monthly draws after excavation began. Neither the proposal nor the eventual contract included a provision detailing the use of the $55,000 payment or requiring PCI to provide the Owners with an accounting of its use.

Prellwitz, Chansler, and Kimball signed the contract on September 29, 2016; Jones signed on October 5, 2016, and gave Prellwitz a check for $55,000. Prellwitz took the $55,000 payment, wrote himself a check for $25,000, wrote Coe a check for $25,000, and left $5,000 in the business account. The contract stated:

"The Owner shall pay the Contractor for the performance of the Contract, but subject to any additions or deductions provided by the parties, the sum of $529,558.00 which includes allowances, listed in Description of Materials, inclusive of the Contractor's fee.

2 Any Allowance items that go above the listed allowance will be paid to Builder. Any underages that may result in any allowance category will be refunded to Owner and will be documented by attached invoices."

The contract included several allowances "to pay for items for which the cost is unknown or under control of Owner," and it provided: "Cost of all changes and any overages of allowances shall be billed to the Owner at cost plus a 15% mark-up."

Construction was delayed while the Owners secured financing, but work began in January 2017. PCI subcontracted with RDR Excavating, Inc. (RDR) for the excavation phase of construction. Riley Rees, the owner of RDR, did not submit a bid before beginning work, nor did PCI ask him for one. PCI did not routinely request nor did Rees routinely provide bids on this type of excavation because there was no way to know what RDR might encounter when it began digging.

The property had a steep driveway from the road to the planned location of the house. The home site was also sloped, so RDR had to excavate a flat area by cutting through vegetation and topsoil to reach native soil that would adequately support the house's foundation. Because the native soil was mostly clay, which expands and contracts depending on moisture, Rees had to bring in select fill to create a pad strong enough to support the house. Wet and cold weather delayed and prolonged the excavation.

A couple of days before RDR finished the pad, Coe visited the job site and spoke with Rees, who told him the fill alone had cost over $20,000. RDR's bill to PCI for the excavation work, reflected on an invoice dated February 17, 2017, totaled $44,044.95. PCI included that amount in its bank draw request to the Owners dated March 6, 2017. Unhappy that the excavation cost was so much more than the allowance amount, the Owners did not pay.

3 On March 24, 2017, RDR filed a mechanic's lien against the property in the amount of $44,044.95. Three days later, the Owners emailed Prellwitz and Coe and said they would pay $25,000 to settle the excavation bill. Two days after that, Coe replied by email, stating RDR was willing to accept $30,000 as payment in full. On April 10, 2017, Kimball responded, stating he would not sign a draw request for $30,000 until he had a signed statement from Riley and Prellwitz acknowledging that the $30,000 would fully settle the invoice and they would seek no further payment.

The next day, Coe told the Owners that Prellwitz would bring a signed document to the bank when he picked up the checks, but the day after that, Kimball emailed Coe and stated he had spoken with Rees, who was reluctant to provide a signed statement. Although Rees was willing to release RDR's lien after he received the money, Kimball told Coe the Owners would not release the $30,000 without a signed and notarized lien release form given to them immediately upon receipt of the funds. The Owners' bank, Capital Federal (CapFed), issued a check to RDR dated April 18, 2017, but Rees did not pick up the check because he was angry about some comments the Owners had made. CapFed voided the check on April 19, 2017.

Meanwhile, PCI continued construction work on the house. PCI's June 7, 2017 request for a bank draw included invoices for $17,200 for windows; $1,572.03 for garage doors; and $1,898.34 for exterior paint. PCI sent the Owners an invoice dated June 28, 2017, that included invoices from Insulation and Drywall Contractors, Inc. in the amount of $43,792, as well as charges for nonpayment for the windows and exterior paint. PCI demanded payment on June 28, 2017, and, when the Owners did not pay, PCI stopped work on the house. The next day, PCI filed a lien against the property in the amount of $25,531.31, which included the 15% overage on the excavation allowance, the cost of the windows and the late fees for nonpayment of that bill, the cost of the garage doors, and the cost of the exterior paint.

4 On July 3, 2017, PCI and RDR filed suit seeking foreclosure of their liens, and PCI sued the Owners for breach of contract and unjust enrichment. On July 19, 2017, PCI filed a second lien against the property in the amount of $47,402.93, which included money owed for the insulation and drywall work, fees for nonpayment of the windows bill, and fees for nonpayment of the exterior paint bill. The Owners eventually paid for the paint and the drywall work.

Around July 20, 2017, Prellwitz sent a letter to each of the Owners' employers, stating he was in a contract dispute with the Owners, who owed him money.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

St. Francis Regional Medical Center, Inc. v. Weiss
869 P.2d 606 (Supreme Court of Kansas, 1994)
Manhattan Ice & Cold Storage, Inc. v. City of Manhattan
274 P.3d 609 (Supreme Court of Kansas, 2012)
Peterson v. Ferrell
349 P.3d 1269 (Supreme Court of Kansas, 2015)
Cresto v. Cresto
358 P.3d 831 (Supreme Court of Kansas, 2015)
Lindsey Masonry Co. v. Murray & Sons Construction Co.
390 P.3d 56 (Court of Appeals of Kansas, 2017)
Geer v. Eby
432 P.3d 1001 (Supreme Court of Kansas, 2019)
Lambert v. Peterson
439 P.3d 317 (Supreme Court of Kansas, 2019)
Jarvis v. Kansas Dept. of Revenue
442 P.3d 1054 (Court of Appeals of Kansas, 2019)
Unified School District No. 446 v. Sandoval
286 P.3d 542 (Supreme Court of Kansas, 2012)
Stechschulte v. Jennings
298 P.3d 1083 (Supreme Court of Kansas, 2013)
Via Christi Regional Medical Center, Inc. v. Reed
314 P.3d 852 (Supreme Court of Kansas, 2013)
State v. Williams
319 P.3d 528 (Supreme Court of Kansas, 2014)
State v. Godfrey
350 P.3d 1068 (Supreme Court of Kansas, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Prellwitz Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prellwitz-construction-kanctapp-2020.