§ 16-1904 — Retainage; release and withholding thereof; alternate security; failure to pay

Kansas·Ch. 16 CONTRACTS AND PROMISES·Art. 19 KANSAS FAIRNESS IN PUBLIC CONSTRUCTION CONTRACT ACT
(a)Retainage shall not exceed 5% of the value of the contract or subcontract unless the owner or contractor determines that a higher rate of retainage is required to ensure performance of the contract. Retainage, however, shall not exceed 10% of the value of the contract or subcontract.
(b)If the contractor or subcontractor has failed to meet the terms of the contract, is not performing according to schedule, shows poor workmanship or other issues, the owner may increase retainage up to 10%.
(c)An owner may withhold not more than 150% of the value of incomplete work, provided that the incomplete work is due to the fault of a contractor. Any amounts retained for incomplete work shall be paid within 45 days after completion of the work as a part of the regular payment cycle.
(d)A contrac

Free access — add to your briefcase to read the full text and ask questions with AI

Kansas § 16-1904 (Retainage; release and withholding thereof; alternate security; failure to pay) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lindsey Masonry Co. v. Murray & Sons Construction Co.
390 P.3d 56 (Court of Appeals of Kansas, 2017)
21 case citations
W & W Steel, LLC v. BSC Steel, Inc.
944 F. Supp. 2d 1066 (D. Kansas, 2013)
5 case citations

Legislative History

L. 2007, ch. 163, § 4; L. 2010, ch. 128, § 4; July 1.