County of Clark v. Blanchard Construction Co.

653 P.2d 1217, 98 Nev. 488, 1982 Nev. LEXIS 511
CourtNevada Supreme Court
DecidedNovember 30, 1982
Docket13549
StatusPublished
Cited by62 cases

This text of 653 P.2d 1217 (County of Clark v. Blanchard Construction Co.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Clark v. Blanchard Construction Co., 653 P.2d 1217, 98 Nev. 488, 1982 Nev. LEXIS 511 (Neb. 1982).

Opinion

*489 OPINION

Per Curiam:

In May of 1977, Blanchard Construction Company entered into a contract with the County of Clark to build a fire station. *490 Shortly thereafter, Blanchard entered into a subcontract with Empire Electric, Inc., to provide and install electrical equipment. Both contracts contained arbitration provisions.

Sq’metime during the following September, a dispute arose concerning responsibility for supplying certain fire alarm equipment. Empire claimed that the County was obliged to supply the equipment, and the County claimed that responsibility for the equipment lay with Empire. Blanchard, as general contractor, supplied the equipment and backcharged Empire for it.

The dispute had ensued for nearly a year when Empire filed a complaint against Blanchard in district court. The complaint requested relief in the amount of $4,909.38. Of that amount, $4,025.00 represented the backcharge stemming from the dispute between Empire and Clark County. The remaining $884.38 was an unrelated charge against Blanchard for services rendered by Empire. Blanchard answered the complaint and further sought indemnity by filing a third-party complaint against the County.

In the summer of 1979, approximately one year after the filing of suit, Empire and Blanchard moved the district court to compel arbitration. The court ordered arbitration. 1

The arbitration panel found that Empire was entitled to the total amount of $4,909.38 and that Blanchard should be indemnified by Clark County for the amount of $4,025.00. Blanchard and Empire petitioned the district court for confirmation of the arbitration award and for the sum of $2,500.00 each in attorney’s fees. The district court confirmed the award and ordered that Blanchard and Empire each receive $1,750.00 in attorney’s fees. The court also awarded interest on the total amount of $4,909.38.

Clark County appeals from the judgment affirming the arbitration award and ordering payment of attorney’s fees. Blanchard appeals that portion of the judgment awarding prejudgment interest on the $884.38 which it owed Empire.

Waiver of the Right to Arbitrate

Clark County objects to the order confirming the arbitration award on the ground that Blanchard had waived its right to arbitrate the dispute. The County asserts two primary bases for finding waiver. The first is "that Blanchard waited approximately nine months following the filing of Empire’s complaint before moving for arbitration. The second is that Blanchard *491 waived its right to arbitrate by actively participating in litigation. Blanchard assertedly engaged in active litigation by filing an answer to Empire’s complaint, by filing a third-party complaint against Clark County and by responding to interrogatories propounded by Empire.

We begin with recognition of our state’s policy strongly favoring arbitration where the parties have previously agreed to that method of dispute resolution. See Exber, Inc. v. Sletten Constr. Co., 92 Nev. 721, 558 P.2d 517 (1976); Lane-Tahoe, Inc. v. Kindred Constr. Co., 91 Nev. 385, 536 P.2d 491 (1975). In view of that policy, we believe that waiver should “not be lightly inferred.” Carcich v. Rederi A/B Nordie, 389 F.2d 692 (2d Cir. 1968).

Clark County relies on a line of cases holding that answering to the merits of a claim constitutes waiver of the right to arbitrate. We have carefully read these authorities and reject the view that any participation in litigation is inconsistent with arbitration and therefore tantamount to waiver. 2

The central issue in determining waiver of the right to arbitrate is not whether the moving party’s actions have been consistent with arbitration, but rather, whether prejudice would occur to the party opposing arbitration. See, e.g., Carolina Throwing Co. v. S & E Novelty Corp., 442 F.2d 329 (4th Cir. 1971); Carcich v. Rederi A/B Nordie, supra; see also Doers v. Golden Gate Bridge, Etc., 588 P.2d 1261 (Cal. 1979). In the immediate case, Clark County was unable to show any prejudice which had resulted from the compelled arbitration. Cf. Keating v. Superior Court of Alameda County, 645 P.2d 1192, 1205 (Cal. 1982) (the presence or absence of prejudice is significant). Moreover, Clark County was unable to establish that the delay in seeking arbitration was unreasonable or that Blanchard in any way engaged in wilful misconduct or acted in bad faith. In fact, Blanchard’s role was somewhat passive since it was caught in the middle of a dispute between the County and Empire. Under these circumstances, we cannot say that Blanchard waived its right to arbitrate.

The Award of Attorney’s Fees

Clark County next objects to the district court order awarding attorney’s fees to Blanchard and Empire.

*492 We agree with the County that NRS 18.010, the general statute governing the award of attorney’s fees, may not be applied to justify an award in this situation. The statute appears to contemplate the award of attorney’s fees following a “trial or special proceeding.” 3 The award of costs and disbursements incurred during arbitration is controlled by the specific provisions of the Uniform Arbitration Act.

There are two applicable provisions in the Uniform Arbitration Act. The first section, NRS 38.125, specifically excludes the award of attorney’s fees in the absence of an express agreement to the contrary among the parties. 4

The second applicable section, NRS 38.165, permits the court to award expenses incurred in seeking an order confirming, modifying or correcting an arbitration award. “Costs of the application and of the proceedings subsequent thereto, and disbursements may be awarded by the court.” We interpret this provision to mean that the court is permitted to award attorney’s fees only for the effort expended in this case in obtaining an order confirming the arbitration award and not for any efforts expended prior to that time. See Stein v. Feldmann,

Related

KORTE CONSTR. CO. VS. STATE, BD. OF REGENTS
2021 NV 37 (Nevada Supreme Court, 2021)
Sunlight Tr. Vs. Ying-Man
Nevada Supreme Court, 2019
Chen v. Bank of America, N.A.
Nevada Supreme Court, 2019
Steve Case Traditional Ira LLC v. Bank of Am., N.A.
430 P.3d 532 (Nevada Supreme Court, 2018)
U.S. Home Corp. v. Medina C/W 64604
Nevada Supreme Court, 2018
PRINCIPAL INVESTMENTS, INC. VS. HARRISON
2016 NV 2 (Nevada Supreme Court, 2016)
TALLMAN VS. DIST. CT. (CPS SECURITY (USA), INC.)
2015 NV 71 (Nevada Supreme Court, 2015)
MIKA VS. DIST. CT. (CPS SECURITY (USA), INC.)
2015 NV 71 (Nevada Supreme Court, 2015)
Fraternal Order of Police, Montgomery County Lodge 35 v. Montgomery County
88 A.3d 887 (Court of Special Appeals of Maryland, 2014)
Grease Spot, Inc. v. Harnes
226 P.3d 524 (Idaho Supreme Court, 2010)
Edwards v. Emperor's Garden Restaurant
130 P.3d 1280 (Nevada Supreme Court, 2006)
Kahn v. Morse & Mowbray
117 P.3d 227 (Nevada Supreme Court, 2005)
Alison Group, Inc. v. Ericson
181 S.W.3d 670 (Court of Appeals of Tennessee, 2005)
Nevada Gold & Casinos, Inc. v. American Heritage, Inc.
110 P.3d 481 (Nevada Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
653 P.2d 1217, 98 Nev. 488, 1982 Nev. LEXIS 511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-clark-v-blanchard-construction-co-nev-1982.