Lane-Tahoe, Inc. v. Kindred Construction Company

536 P.2d 491, 91 Nev. 385, 73 A.L.R. 3d 1035, 1975 Nev. LEXIS 644
CourtNevada Supreme Court
DecidedJune 11, 1975
Docket7602, 7670
StatusPublished
Cited by18 cases

This text of 536 P.2d 491 (Lane-Tahoe, Inc. v. Kindred Construction Company) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lane-Tahoe, Inc. v. Kindred Construction Company, 536 P.2d 491, 91 Nev. 385, 73 A.L.R. 3d 1035, 1975 Nev. LEXIS 644 (Neb. 1975).

Opinions

[386]*386OPINION

By the Court,

Thompson, J.:

These consolidated appeals are from orders of the district court, entered in lien foreclosure proceedings, denying motions to compel the arbitration of disputes arising under construction 'Contracts.

[387]*387The appellant in each instance, Lane-Tahoe, Inc., as owner, entered into written contracts with respondents, McKenzie Construction, Inc., and Kindred Construction Co., respectively for land site preparation and for the construction of condominiums. Each contract contains provisions for the arbitration of claims and disputes arising thereunder. McKenzie and Kindred seek court foreclosure of lien claims timely filed. Lane-Tahoe sought unsuccessfully to stay court action and to compel arbitration in lieu thereof. These appeals followed. We first must resolve a motion to dismiss tendered by Kindred.

1. Kindred filed a statement of facts constituting its claim of lien [NRS 108.239] in a lien foreclosure action commenced by two of its subcontractors, Incline Glass and Cal-Vada Cabinet Company, against Lane-Tahoe. Since Lane-Tahoe’s contract with Kindred provided for the arbitration of disputes between them, Lane-Tahoe moved to stay court action and to compel arbitration. As noted, that motion was denied. We are asked to dismiss Lane-Tahoe’s appeal from the order denying arbitration because NRCP 54(b) provides that when multiple parties are involved, the court may direct the entry of final judgment “only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment.” The record contains no such express determination and direction. Whether Rule 54(b) has application to this case is the point to be decided.1

The motion to compel arbitration was offered pursuant to NRS 38.045 of the Uniform Arbitration Act. Section 1 thereof provides that “on application of a party showing an agreement described in NRS 38.035, and the opposing party’s refusal to arbitrate, the court shall order the parties to proceed with arbitration. . . And, section 4 thereof reads that “any action or proceeding involving an issue subject to arbitration shall be stayed if an order for arbitration or an application therefor has been made under this section. . . . When the application is made in such action or proceeding, the order for arbitration shall include such stay.” Finally, NRS 38.205 (1) (a) of the Act expressly provides that “an appeal may be taken from an order denying an application to compel arbitration made under NRS 38.045.”

A Rule 54(b) determination is not necessary if a statute or rule expressly authorizes an appeal. In DeLuca Importing [388]*388Co. v. Buckingham Corp., 90 Nev. 158, 520 P.2d 1365 (1974), we ruled that an appeal may be taken from an order denying a motion for an injunction, NRAP 3A(b) (2), without any express determination that there is no just reason for delay. See also: Bernhardt v. Polygraphic Company of America, 235 F.2d 209, 211 (2d Cir. 1956); Atlantic Richfield Co. v. Oil, Chemical & A. Wkrs. Int. U., 447 F.2d 945, 947 (7th Cir. 1971); Thompson v. Trent Maritime Company, Ltd., 343 F.2d 200, 204 (3rd Cir. 1965).

Kindred’s motion to dismiss is denied. We turn to consider the merits of the consolidated appeals.

2. The contractual provisions for arbitration are, in each instance, identical and, in relevant part, are quoted below.2 Moreover, each contract states that it “shall be governed by the law of the place where the Project is located.” The project is located in Washoe County, Nevada. Consequently, the arbitration provisions of the contracts are to be read in conjunction with the Uniform Arbitration Act of this state.

The underlying purpose of the Act is to preclude court intervention into the merits of disputes when arbitration has been provided for contractually. This is evident from a mere reading of the Act. A contract to submit controversies to arbitration, with certain exceptions, is valid, enforceable, and irrevocable. NRS 38.035. Any action o/ proceeding involving an issue subject to arbitration shall be stayed if an application therefor has been made. NRS 38.045(4). Subject to the specified exceptions of NRS 38.145 and 38.155, the court shall confirm [389]*389the award of the arbitrators. NRS 38.135. The whole tenor of the Act favors arbitration when the parties have agreed to that method of settling disputes between them. The respondents Kindred and McKenzie acknowledge this to be so. However, they each insist that the owner, Lane-Tahoe, waived its right to arbitration by failing to file written notice of its demand therefor within a reasonable time as required by the contract provision quoted in footnote 2, and the respondent McKenzie further urges that Lane-Tahoe’s motion to compel arbitration is barred by limitations. These contentions formed the basis for the district court orders denying arbitration.

Although Lane-Tahoe did not file a written demand for arbitration, neither did McKenzie nor Kindred. All had agreed, however, to settle their disputes in that manner. In view of that agreement, one of the contracting parties was obliged to initiate the arbitration process. Absent express language in the contract placing the initial burden on either party, that responsibility properly rests with the party seeking relief. Mamlin v. Susan Thomas, Incorporated, 490 S.W.2d 634, 639 (Civ.App. Tex. 1973); Nordenstrom v. Swedberg, 143 N.W.2d 848, 857 (N.D. 1966); Klein Coat Corp. v. Peretz, 153 N.Y.S.2d 92, 97 (Sp.Ct. 1956). He should not be free to litigate in the courts simply because his opponent did not demand arbitration. This is not to say that the opponent could not have initiated arbitration. We hold only that the burden to initiate arbitration is upon the party seeking relief and does not shift to the opponent absent a clear waiver of arbitration by the opponent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KORTE CONSTR. CO. VS. STATE, BD. OF REGENTS
2021 NV 37 (Nevada Supreme Court, 2021)
CVN Group, Inc. v. Delgado
95 S.W.3d 234 (Texas Supreme Court, 2002)
Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.
621 N.W.2d 502 (Nebraska Supreme Court, 2001)
In Re Bruce Terminix Co.
988 S.W.2d 702 (Texas Supreme Court, 1998)
Phillips v. Parker
794 P.2d 716 (Nevada Supreme Court, 1990)
Mountain Plains Constructors, Inc. v. Torrez
785 P.2d 928 (Supreme Court of Colorado, 1990)
Gold Coast Mall, Inc. v. Larmar Corp.
468 A.2d 91 (Court of Appeals of Maryland, 1983)
Continental Insurance v. Hull
654 P.2d 1024 (Nevada Supreme Court, 1982)
County of Clark v. Blanchard Construction Co.
653 P.2d 1217 (Nevada Supreme Court, 1982)
St. Paul Fire & Marine Insurance Co. v. Wright
629 P.2d 1202 (Nevada Supreme Court, 1981)
Voss v. City of Oklahoma City
1980 OK 148 (Supreme Court of Oklahoma, 1980)
Johnson v. Fireman's Fund Insurance Co.
272 N.W.2d 870 (Supreme Court of Iowa, 1978)
Exber, Inc. v. Sletten Construction Company
558 P.2d 517 (Nevada Supreme Court, 1976)
Lane-Tahoe, Inc. v. Kindred Construction Company
536 P.2d 491 (Nevada Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
536 P.2d 491, 91 Nev. 385, 73 A.L.R. 3d 1035, 1975 Nev. LEXIS 644, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lane-tahoe-inc-v-kindred-construction-company-nev-1975.