Mountain Plains Constructors, Inc. v. Torrez

785 P.2d 928, 14 Brief Times Rptr. 123, 1990 Colo. LEXIS 75, 1990 WL 5450
CourtSupreme Court of Colorado
DecidedJanuary 29, 1990
Docket88SC487
StatusPublished
Cited by37 cases

This text of 785 P.2d 928 (Mountain Plains Constructors, Inc. v. Torrez) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mountain Plains Constructors, Inc. v. Torrez, 785 P.2d 928, 14 Brief Times Rptr. 123, 1990 Colo. LEXIS 75, 1990 WL 5450 (Colo. 1990).

Opinion

Justice ERICKSON

delivered the Opinion of the Court.

The court of appeals, in Mountain Plains Constructors, Inc. v. Torrez, No. 86CA1722 (Colo.App. Aug. 11, 1988), reversed the trial court’s order denying the respondents’, Vonne and Gilbert Torrez (the Torrezes), motion to dismiss and remanded with directions to dismiss. We accepted certiorari to determine whether the court of appeals erred in finding that the Torrezes did not waive a contractual arbitration provision and whether the proper procedure upon remand was to dismiss the case. We find that the court of appeals correctly held that the Torrezes were entitled to arbitration of the dispute, but that the proper remedy on remand is to stay the trial court proceeding pending arbitration. Accordingly, we affirm in part, reverse in part, and return this case to the court of appeals with directions to remand to the trial court with instructions to stay the proceeding pending the conclusion of the arbitration process.

Petitioner Mountain Plains Constructors, Inc. (Mountain Plains) contracted with the Torrezes, pursuant to a standard form agreement between owner and contractor, to construct a building to be used as a lounge. 1 As originally contemplated, the building was to hold five hundred persons. However, due to budgetary limitations, the parties modified the plans to provide for a building with an occupancy of four hundred *930 persons, and also reduced the capacity of the air conditioning system and the amount of insulation installed. Mountain Plains commenced work under the contract and a certificate of occupancy was issued by the City of Greeley on May 17, 1984. Following the issuance of the certificate of occupancy, the building was completed in June 1984.

In June 1984, a dispute arose between Mountain Plains and the Torrezes concerning payment of the remaining balance due on the contract. Mountain Plains mailed the Torrezes a notice of intent to file a mechanic’s lien on June 29, 1984. The Tor-rezes apparently did not respond to the notice and on October 23, 1984, Mountain Plains filed an action for breach of contract and foreclosure on the mechanic’s lien. From the time the dispute arose to the filing of the complaint, the parties negotiated in a fruitless attempt to reach a settlement.

On December 21, 1984, the Torrezes entered an appearance and moved to dismiss on the grounds that the dispute between the parties was subject to arbitration and the court was therefore without jurisdiction to proceed until arbitration was completed. 2 The trial court denied the motion, finding that the contract required the party asserting the right to arbitration to notify the other party and the American Arbitration Association within a reasonable time and that the Torrezes failed to comply with those contractual terms.

When the motion to dismiss was denied, the Torrezes filed an answer asserting, as an affirmative defense, that the trial court lacked jurisdiction over the action because the parties agreed to arbitrate any dispute arising out of the contract. The answer also contained a counterclaim for breach of contract and requested damages in the amount of $38,000. The arbitration issue was also raised by the Torrezes in the trial data certificate. Trial was to the court and judgment was entered in favor of Mountain Plains in the amount of $10,493.41 plus interest and attorney fees. The Torrezes raised the arbitration issue in a motion for a new trial and that motion was denied.

The Torrezes appealed. The court of appeals reversed the trial court’s order denying the motion to dismiss on the grounds that the trial court erroneously placed the burden to initiate arbitration on the Tor-rezes, and remanded with directions to dismiss the action.

The public policy of this state encourages the resolution of disputes through arbitration. Ezell v. Rocky Mountain Bean & Elevator Co., 76 Colo. 409, 412, 232 P. 680, 681 (1925); Christensen v. Flaregas Corp., 710 P.2d 6, 8 (Colo.App.1985). A valid and enforceable arbitration provision divests the courts of jurisdiction over all disputes that are to be arbitrated pending the conclusion of arbitration. Guthrie v. Barda, 188 Colo. 124, 126, 533 P.2d 487, 488 (1975). Submission of the dispute to arbitration is a condition precedent to the commencement of a suit on an issue covered by an arbitration agreement. Id.

In this case, the trial court found that the Torrezes failed to assert their right to arbitration within a reasonable time after the dispute arose, and imposed the burden to initiate arbitration on the Torrezes. The general rule is that the party asserting a claim has the burden to initiate arbitration. See Gold Coast Mall, Inc. v. Larmar Corp., 298 Md. 96, 107, 468 A.2d 91, 98 (1983); Lane-Tahoe, Inc. v. Kindred Constr. Co., 91 Nev. 385, 389, 536 P.2d 491, 494 (1975). Since the Torrezes were not obligated to initiate arbitration, they were not required to notify Mountain Plains and the American Arbitration Association as a condition precedent to asserting their right to arbitration.

Mountain Plains contends that the Torrezes waived their right to arbitration by failing to appeal the trial court’s denial of their motion to dismiss and proceeding to final judgment. A denial of a motion to compel arbitration is an appealable order. *931 Section 13-22-221, 6A C.R.S. (1986). 3 However, since section 13-22-221(l)(a) is permissive and not mandatory, an order denying a motion to compel arbitration may also be appealed after final judgment. See In re Northwestern Mut. Life Ins. Co., 703 P.2d 1314, 1317 (Colo.App.1985) (order appointing receiver appealable pursuant to rule, but party could still appeal order upon entry of final judgment). See also 9 J. Moore, B. Ward, and J. Lucas, Moore’s Federal Practice ¶ 110.18 (2d ed. 1989).

A party may waive its right to arbitration by taking actions that are inconsistent with an arbitration provision. Cordillera Corp. v. Heard, 200 Colo. 72, 75, 612 P.2d 92, 94 (1980). However, in this case, the arbitration issue was reserved in the Torrezes’ answer, trial data certificate and motion for new trial and Mountain Plains was therefore on notice of the Torrezes’ objection. Under these circumstances, the Torrezes did not waive their right to arbitration by failing to appeal the denial of their motion to dismiss pursuant to section 13-22-221.

When an order compelling arbitration is issued pursuant to section 13-22-204, 6A C.R.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JPMorgan v. Graham
Colorado Court of Appeals, 2025
Tug Hill Marcellus LLC v. BKV Chelsea LLC
2021 COA 17 (Colorado Court of Appeals, 2021)
Linzy v. Conifer Care Communities
2020 COA 88 (Colorado Court of Appeals, 2020)
Meardon v. Freedom Life Insurance
2018 COA 32 (Colorado Court of Appeals, 2018)
Sure-Shock Electric, Inc. v. Diamond Lofts Venture, LLC
259 P.3d 546 (Colorado Court of Appeals, 2011)
Estate of Keenan v. Colorado State Bank
252 P.3d 539 (Colorado Court of Appeals, 2011)
Ferla v. Infinity Development Associates, LLC
107 P.3d 1006 (Colorado Court of Appeals, 2004)
EAGLE RIDGE CONDOMINIUM ASS'N. v. Metropolitan Builders, Inc.
98 P.3d 915 (Colorado Court of Appeals, 2004)
CVN Group, Inc. v. Delgado
95 S.W.3d 234 (Texas Supreme Court, 2002)
Rains v. Foundation Health Systems Life & Health
23 P.3d 1249 (Colorado Court of Appeals, 2001)
Waldman v. Old Republic National Title Insurance Co.
12 P.3d 835 (Colorado Court of Appeals, 2000)
In Re the Marriage of Popack
998 P.2d 464 (Colorado Court of Appeals, 2000)
Camelot Investments, LLC v. LANDesign, LLC
973 P.2d 1279 (Colorado Court of Appeals, 1999)
Peterman v. State Farm Mutual Automobile Insurance Co.
961 P.2d 487 (Supreme Court of Colorado, 1998)
In Re Bruce Terminix Co.
988 S.W.2d 702 (Texas Supreme Court, 1998)
Peterman v. STATE FARM MUT. AUTO. INS.
948 P.2d 63 (Colorado Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
785 P.2d 928, 14 Brief Times Rptr. 123, 1990 Colo. LEXIS 75, 1990 WL 5450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mountain-plains-constructors-inc-v-torrez-colo-1990.