Galion Iron Works & Mfg. Co. v. J. D. Adams Mfg. Co.

128 F.2d 411, 53 U.S.P.Q. (BNA) 611, 1942 U.S. App. LEXIS 3594
CourtCourt of Appeals for the Seventh Circuit
DecidedJune 1, 1942
Docket7900
StatusPublished
Cited by45 cases

This text of 128 F.2d 411 (Galion Iron Works & Mfg. Co. v. J. D. Adams Mfg. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Galion Iron Works & Mfg. Co. v. J. D. Adams Mfg. Co., 128 F.2d 411, 53 U.S.P.Q. (BNA) 611, 1942 U.S. App. LEXIS 3594 (7th Cir. 1942).

Opinion

LINDLEY, District Judge.

On February S, 1936, plaintiff and defendant entered into an agreement under which plaintiff granted defendant a license to manufacture motor graders embodying one or more claims of Winsor patent 2,-020,271. The present suit arose out of this contract and involves two separate claims; the first for royalties claimed to have become due after July 6, 1938, and the second for judgment upon an arbitrator’s award made in an ex parte proceeding by the arbitrator named in the contract.

Under the agreement, defendant agreed to pay royalties on graders sold by it after February 5, 1936. Section (d) provided that if in any suit the patent should be held invalid or not infringed, no royalties should be due until reversal, with respect to those graders manufactured by defendant substantially of “the same design and construction as that involved in the supposed litigation and within the scope of the claims involved.”

The subsequent suit of Gabon Iron Works & Mfg. Co. v. Beckwith Machine Co., D.C., 25 F.Supp. 73, affirmed 3 Cir., 105 F.2d 941, resulted, July 6, 1938, unfavorably to the Winsor patent. There a grader known as the Caterpillar Auto Patrol was held not to infringe Winsor. Consequently our question is whether defendant’s graders are substantially of the same design and construction as the Caterpillar Auto Patrol. The District Court *413 so held, and' the evidence supports the finding.

Both the Caterpillar products held not to infringe and defendant’s graders are power operated machines with a relatively long vehicle frame comprised of spaced, elongated, symmetrically arranged side members and cross members, with a power traction unit at the rear and a steering unit at or near the front end of the frame. Each has a grader blade adjustably mounted on the frame to operate on material along the path of travel. Each has a mechanism between the side members and the power unit to hold the implement in a fixed relation to the frame, independent of the steering wheel unit. In both the engine is supported at three spaced points upon the frame. Each has the operator’s station between the engine and the grader blade, except that in a few models of defendant’s graders it is located over and to the rear of the motor. And both place their engines over the axle except in a few models of defendant. These slight differences are of no importance. Gabon I. W. & M. Co. v. J. D. Adams Mfg. Co., 7 Cir., 105 F.2d 943.

In view of this substantial evidence supporting the finding of the trial court, it should be accepted by this court. Barbour v. George, 7 Cir., 84 F.2d 281, 282; Universal Gas Co. v. Central Illinois Public Service. Co., 7 Cir., 102 F.2d 164, 166. Moreover there is no substantial evidence to the contrary. Consequently, the decision in Gabon Iron Works & Mfg. Co. v. Beckwith Machine Co., D.C., 25 F.Supp. 73, having been unfavorable to the Winsor patent and the motor graders manufactured by defendant being of substantially the same design and construction as those involved in the unfavorable suit, defendant was justified under the contract in refusing to continue payment of royalties after July 6, 1938.

Under the second claim, plaintiff alleges that it is entitled to $28,179.63 awarded it by the arbitrator mentioned in the license contract.

Clause 4 of the contract, under which plaintiff claims relief, provided that the arbitrator should be vested with sole authority and power to receive, consider and decide upon any complaint presented by either party claiming a violation of the license contract with respect to prices, terms of sale, and payment of royalties. If the arbitrator should find that the contract had been violated in any of these respects, he was authorized to assess as “liquidated damages,” and “not as a penalty,” not less than 100 per cent nor more than 500 per cent of the total royalty payments payable.

In satisfaction of the judgment in the first Gabon Iron Works & Mfg. Co. v. J. D. Adams Mfg. Co. suit, supra, Adams paid Gabon $19,825, representing unpaid royalties, and costs of $300.25. Shortly after this, plaintiff asked the arbitrator named in the contract to ascertain the amount of its alleged liquidated damages suffered by reason of defendant’s refusal to pay royalties until compelled to do so under the judgment.

The arbitrator found plaintiff’s expenses in the suit to be $25,218.11 plus accrued interest on unpaid royalties of $1,925 and $103.65 costs, a total of $28,179.63, and awarded this amount to plaintiff as actual liquidated damages in the form of additional royalties. Defendant refused to participate in the arbitration and claimed that the award was of no effect. The District Court sustained defendant’s contention.

Assuming the binding effect of the agreement to arbitrate, plaintiff did not see fit originally to avail itself of that remedy. Rather it brought suit. A right to arbitration arising out of mutual agreement, like any other contractual right, may be waived, amended or altered. The Belize, D.C., 25 F.Supp. 663, appeal dismissed 2 Cir., 101 F.2d 1005; Radiator Specialty Co. v. Cannon Mills, Inc., 4 Cir., 97 F.2d 318, 117 A.L.R. 299; La Nacional Platanera v. North American F. & S. S. Corp., 5 Cir., 84 F.2d 881. Commencement of a suit in court rather than reliance upon-arbitration, with answer by the opposing party upon the merits, is a waiver of the right to arbitrate by both parties. The Belize, D.C., 25 F.Supp. 663; McKenna Process Co. v. Blatchford Corp., 304 Ill.App. 101, 25 N.E.2d 916. The plaintiff brought suit to recover unpaid royalties which defendant claimed it did not owe. It had a clear right to have the dispute arbitrated. This right was abandoned by suit; in that abandonment defendant acquiesced by answer on the merits. Plaintiff Could have sought arbitration but it exercised its option of bringing suit. By its election, it waived its right to arbitration.

By the contract the arbitrator was granted sole authority and power to deter *414 mine any complaint involving violation of the contract by either party with respect to prices, terms and conditions of sale and payment of royalties. His decision was to be final and'binding upon the parties. The language used is of such breadth as to include any controversy with respect to every subject mentioned, including payment of royalties. This, under the law of both Indiana and Ohio, apparently, was a binding covenant. Miller v. Blockberger, 111 Ohio St. 798, 146 N.E. 206; Jones v. Stevens, 112 Ohio St. 43, 146 N.E. 894; Carpenter v. Lockhart, 1 Ind. 434; Beiser v. Kerr, 107 Ind.App. 1, 20 N.E.2d 666. Under the contract the right to ask for arbitration came into existence whenever there was a controversy between the parties as to payment of royalties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bharat B. Patel v. BancorpSouth Bank
187 So. 3d 1060 (Court of Appeals of Mississippi, 2016)
H.R., Inc. v. Vissepó & Diez Construction Corp.
190 P.R. 597 (Supreme Court of Puerto Rico, 2014)
Design Benefit Plans, Inc. v. Enright
940 F. Supp. 200 (N.D. Illinois, 1996)
Buy-Rite Costume Jewelry, Inc. v. Albin
676 F. Supp. 433 (D. Rhode Island, 1988)
Knorr Brake Corp. v. Harbil, Inc.
556 F. Supp. 489 (N.D. Illinois, 1983)
Charles J. Frank, Inc. v. Associated Jewish Charities of Baltimore, Inc.
450 A.2d 1304 (Court of Appeals of Maryland, 1982)
James Julian, Inc. v. Raytheon Service Co.
424 A.2d 665 (Court of Chancery of Delaware, 1980)
Midwest Window Systems, Inc. v. Amcor Industries, Inc.
630 F.2d 535 (Seventh Circuit, 1980)
McNall v. Farmers Insurance Group
392 N.E.2d 520 (Indiana Court of Appeals, 1979)
United Nuclear Corp. v. General Atomic Co.
597 P.2d 290 (New Mexico Supreme Court, 1979)
Standard Roofing Co. v. John G. Johnson & Sons Construction Co.
376 N.E.2d 610 (Ohio Court of Appeals, 1977)
International Brotherhood of Teamsters, Local 959 v. King
572 P.2d 1168 (Alaska Supreme Court, 1977)
Lane-Tahoe, Inc. v. Kindred Construction Company
536 P.2d 491 (Nevada Supreme Court, 1975)
John David Yench v. Ted P. Stockmar
483 F.2d 820 (Tenth Circuit, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
128 F.2d 411, 53 U.S.P.Q. (BNA) 611, 1942 U.S. App. LEXIS 3594, Counsel Stack Legal Research, https://law.counselstack.com/opinion/galion-iron-works-mfg-co-v-j-d-adams-mfg-co-ca7-1942.