Nordenstrom v. Swedberg

143 N.W.2d 848, 1966 N.D. LEXIS 162
CourtNorth Dakota Supreme Court
DecidedJune 30, 1966
Docket8308
StatusPublished
Cited by15 cases

This text of 143 N.W.2d 848 (Nordenstrom v. Swedberg) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nordenstrom v. Swedberg, 143 N.W.2d 848, 1966 N.D. LEXIS 162 (N.D. 1966).

Opinion

ERICKSTAD, Judge.

This is an appeal by the defendant, Milton Swedberg, doing business as Swedberg Construction Company, from a judgment of the District Court of Grand Forks County in favor of the plaintiff, Fred Norden-strom, and from an order of the District Court denying his motion for judgment notwithstanding the verdict or in the alternative for a new trial.

On May 7, 1959, Mr. Swedberg entered into a contract with the Franciscan Sisters of the Immaculate Conception, Little Falls, Minnesota, for the construction of a new addition to St. Gabriel’s Hospital and for the remodeling of the existing hospital building. He was the only general contractor involved in the project. On May 22, 1959, he entered into a subcontract with Mr. Nordenstrom. In the subcontract Mr. Nordenstrom promised to furnish and install all lathing and plastering as shown on the plans and listed in the specifications and addenda. Mr. Nordenstrom commenced his work on the project in November or December 1959. He was not personally present on the project but was represented by several foremen who directed his employees during the various stages of construction. Mr. Swedberg was represented at the construction site by Ray Wendt, his general superintendent, until Mr. Wendt became ill, and after that by Bill Otteson, whom he called his carpenter foreman.

On November 22, 1960, Mr. Norden-strom traveled to the construction site in response to a telephone call from his foreman or superintendent. He testified that when he arrived he found that his employees were being asked to do a considerable amount of work which was not included in his contract. He further testi *850 fied that after talking with Mr. Wendt, he was advised that Mr. Wendt would sign or approve any “extras” if Mr. Swedberg would give his approval. He testified that he then on the same day telephoned Mr. Swedberg and informed him that there was extra work not called for in his contract and that if he did not receive a letter from Mr. Swedberg “stating that these extra items would be paid for,” he would have to remove his crew the next morning. He said that Mr. Swedberg informed him that he would be paid for any extra work not called for in the contract and that a letter would be sent to him confirming this promise.

The letter received by Mr. Nordenstrom, admitted in evidence as plaintiff’s exhibit 2, reads as follows:

[Letterhead omitted]
November 23, 1960
Mr. Fred Nordenstrom
Plastering Contractor
2810 Belmont Road
Grand Forks, Minnesota [North Dakota]
Re: St. Gabriel’s Hospital
Little Falls, Minnesota
Dear Mr. Nordenstrom:
In regard to the above job, there will be some changes and some extras in your work that will be above and beyond the original contract. Any items which are not specifically called for on the plans and specifications will, of course; be an extra.
We wish that you could have your foreman keep track of these items and list them for us along with the bill so that we can keep our records straight and bill the owner properly.
Very sincerely yours,
SWEDBERG CONSTRUCTION COMPANY
By (signed) M. Swedberg_
Milton Swedberg

Mr. Nordenstrom’s crew continued to work on the project, and his foremen recorded work performed and materials used in doing what they considered to be extra work not included in Nordenstrom’s contract. These records were kept in the form of tickets which were signed by Nordenstrom’s foremen and submitted to Mr. Wendt or Mr. Otteson, who signed or initialed them. The tickets were then mailed to Mr. Nordenstrom. This procedure was followed until Mr. Nordenstrom completed his work on the hospital in May 1961.

Mr. Nordenstrom’s subcontract was for the sum of $48,000. He claimed that Mr. Swedberg owed him an additional $10,829.-68. This amount was for the extra work and materials which he believed he had expended on the project and was computed on the basis of the tickets he had received from his foremen. Mr. Swedberg claimed that he owed only $2,572.05. The jury, however, found that he owed $10,829.-68. Mr. Nordenstrom’s bill for extra work and materials arose solely from the remodeling of the existing hospital building.

*851 Mr. Nordenstrom began this action to recover the sum which he claimed was due for extra work on the hospital. Prior to the commencment of the trial, Mr. Swed-berg moved the trial court to dismiss the action and made motions for a directed verdict at the close of the plaintiff’s (Nordenstrom’s) case and at the close of all of the evidence. The court denied these motions. The jury returned a verdict for the amount claimed for the extra work. After the verdict had been returned, Mr. Swedberg made a motion for judgment notwithstanding the verdict or in the alternative for a new trial. The trial court denied the motion and ordered that judgment be entered in the amount of the verdict. Mr. Swedberg is appealing from the order denying his motion and from the judgment.

Mr. Swedberg has assigned eight specifications of error. We first consider specifications 2 and 6, which read as follows:

2. The Trial Court erred in denying the Defendant’s Motion to Dismiss made, filed and argued to the Court prior to the empaneling of the jury or the commencement of the trial of this matter; said Motion to Dismiss was based upon the failure of the Plaintiff to arbitrate the disputes between the parties pursuant to paragraph “d” of the Subcontract between the parties, pursuant to paragraph XI of the Subcontract between the parties, and pursuant to paragraph No. 7 of the general conditions of the Contract between the parties.
6. The Court erred in denying Defendant’s Motion for Judgment Notwithstanding the Verdict or in the Alternative for a New Trial.

In regard to specification 2, Mr. Swed-berg contends that the subcontract contained a provision which required the parties to submit their dispute to arbitration before commencing this action. In support of this contention he directs our attention to specific provisions of the subcontract which read as follows:

XI. To be bound to the Contractor by the terms of the contract with the owner, the general conditions, special conditions ' and specifications and addenda, and to conform to and comply with the drawings and specifications and addenda, to furnish such shop drawings or samples as may be required, and to assume toward the Contractor all the obligations and responsibilities that the Contractor assumes in and by the aforesaid documents toward the Owner, in so far as they are applicable to this particular subcontract.
D.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rollings v. Thermodyne Industries, Inc.
1996 OK 6 (Supreme Court of Oklahoma, 1996)
SHORTLAND v. Larson
364 N.W.2d 67 (North Dakota Supreme Court, 1985)
Gold Coast Mall, Inc. v. Larmar Corp.
468 A.2d 91 (Court of Appeals of Maryland, 1983)
Wagner Bros., Inc. v. City of Williston
335 N.W.2d 328 (North Dakota Supreme Court, 1983)
Lane-Tahoe, Inc. v. Kindred Construction Company
536 P.2d 491 (Nevada Supreme Court, 1975)
Bel Pre Medical Center, Inc. v. Frederick Contractors, Inc.
320 A.2d 558 (Court of Special Appeals of Maryland, 1974)
Rettig v. Taylor Public School District No. 3 Ex Rel. School Board
211 N.W.2d 743 (North Dakota Supreme Court, 1973)
First National Bank of Wibaux v. Dreher
202 N.W.2d 670 (North Dakota Supreme Court, 1972)
Bjerken v. Ames Sand and Gravel Company
189 N.W.2d 366 (North Dakota Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
143 N.W.2d 848, 1966 N.D. LEXIS 162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nordenstrom-v-swedberg-nd-1966.