Layne-Minnesota Co. v. Regents of the University of Minnesota

123 N.W.2d 371, 266 Minn. 284, 1963 Minn. LEXIS 735
CourtSupreme Court of Minnesota
DecidedAugust 16, 1963
Docket38,811
StatusPublished
Cited by99 cases

This text of 123 N.W.2d 371 (Layne-Minnesota Co. v. Regents of the University of Minnesota) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Layne-Minnesota Co. v. Regents of the University of Minnesota, 123 N.W.2d 371, 266 Minn. 284, 1963 Minn. LEXIS 735 (Mich. 1963).

Opinion

Rogosheske, Justice.

Appeal from an order denying plaintiff’s motion to compel arbitration under Minn. St. 572.09 of the Uniform Arbitration Act adopted by Minnesota in 1957. 1

*285 On March 9, 1961, plaintiff, a contractor, after acceptance of its bid, entered into a construction contract with the defendant to construct caisson foundations for two buildings to be erected on the west campus of the University of Minnesota.

“A caisson is a column of concrete and steel upon which the building rests. The contract called for a total of 56 caissons with varying diameters of 4, 5 or 6 feet. Each caisson extends from the ground surface to whatever depth was necessary to get an 8-inch penetration into bedrock which was approximately 25 feet below the surface. After excavation to bedrock was completed the holes were filled with concrete and reinforcing steel to form a set of reinforced concrete legs upon which the buildings would rest.” 2 Attached to the specifications, pursuant to which the plaintiff made its bid, were reports on preconstruction borings which had been conducted for defendant by the Minnesota Test Boring Company. These reports were provided for what value they might have to the contractor but were not guaranteed by defendant as accurate or indicative of all soils at the site. The contract included a modification clause and an arbitration clause hereafter quoted. During the course of the construction plaintiff encountered boulders, limestone slabs, and underground water in amounts and at locations not indicated by the plans and specifications. Plaintiff claims that a requested modification of the contract and a claim for additional compensation was made and denied. We are not informed whether this occurred before or after completion of the work. 3 Defendant does not deny that a request was made, but the particulars concerning the time, nature, and manner of the request, and of defendant’s denial, are not disclosed by the record. We assume that the request was denied and that plaintiff completed the work notwithstanding this controversy. 4 In any event, after a denial, *286 the plaintiff, on February 8, 1962, served a written request for arbitration of the claim for additional compensation because of unanticipated difficulties. Defendant refused this request on the ground that such claim was not a dispute intended to be referable to arbitration under the language of the arbitration clause of the contract, The controversy as to whether the claim of the contractor was a dispute subject to arbitration apparently continued and remained unresolved until April 24, 1962, on which date the defendant commenced a declaratory judgment action seeking a construction of the provisions of the contract relating to arbitration. Thereafter, pursuant to § 572.09(a) of the Uniform Arbitration Act, plaintiff made application for an order compelling arbitration and staying the declaratory judgment action until its motion to compel arbitration was heard and determined. Under § 572.09(d) of the act, the parties agreed to stay the action for declaratory judgment, and the plaintiff’s application was heard and denied. The court held that the dispute involved was not one within the meaning of section 1-23 of the contract. This appeal from the order denying an application to compel arbitration is expressly authorized by § 572.26, subd. 1(1), of the act.

The pertinent provisions of the contract are as follows:

“Section 1-16 Changes, Extras, Etc.
“* * * Should the Contractor find at any time during the progress of the work that in his judgment existing conditions demand or malee desirable or beneficial a modification in the requirements covering any particulars or items, it shall be his duty and he is required to promptly report in writing each such matter to the Supervising Engineer for his decision and instruction.”
*287 “Section 1-23 Disputes.
“If during progress of the work, any disputes, claims or questions arise between the owner and the contractor concerning the work, the architect/engineer shall be consulted and his decision shall be final. However, decision may -be submitted to arbitration.”
“Section 1-24 Arbitration.
“All disputes, claims or questions subject to arbitration under this contract shall be submitted to arbitration in accordance with the provisions, then obtaining of the Uniform Arbitration Act. Chapter 633, Laws of Minnesota, 1957, and this Agreement shall be specifically enforceable under the prevailing arbitration law, and judgment upon the award rendered may be entered in the court of the forum, state or federal, having jurisdiction. It is mutually agreed that the decision of the arbitrators shall be a condition precedent to any right of legal action that either party may have against the other.”

Essentially the question presented to the trial court and here is whether or not the parties intended by their contract to submit to arbitration a dispute arising over a claim for additional compensation occasioned by unanticipated difficulties in performing the work required by the contract.

As the question was submitted to the trial court and here, the arguments of the parties were primarily directed toward seeking a final judicial determination of whether the claim presents an issue referable to arbitration. We are urged, as was the trial court, to decide the question under the rules relating to the construction of contracts without reference to any specific provisions of the' Uniform Arbitration Act. This emphasis overlooks section 1-24 of the contract which makes the act an integral part of the contract, thereby requiring a consideration of those provisions of the act which were intended to apply and control a judicial determination of the very question presented.

One of the fundamental objectives of the act was to encourage and facilitate the arbitration of disputes by providing a speedy, informal, and relatively inexpensive procedure for resolving controversies arising out of commercial transactions, including the labor- *288 management field. The language of the act emphasizes an intention to change the common-law policy of judicial hostility toward arbitration to one favoring arbitration. Contrary to decisions found in many states, it specifically makes a written agreement to arbitrate effective whether relating to existing or future disputes. 5 By invoking the aid of courts, the legal rights of parties to such an agreement are protected. Summary procedures are provided to compel 6 or prevent 7 arbitration and to review awards with express provisions relating to judicial vacation, 8 modification, and correction of awards, 9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of: Jon Amberson
54 F.4th 240 (Fifth Circuit, 2022)
Gannett Fleming, Inc. v. Corman Const.
243 Md. App. 376 (Court of Special Appeals of Maryland, 2019)
Fernow v. Gould
835 N.W.2d 8 (Supreme Court of Minnesota, 2013)
Gale v. Rittenhouse
686 N.W.2d 50 (Court of Appeals of Minnesota, 2004)
Chicago Fire Fighters Union Local No. 2 v. City of Chicago
735 N.E.2d 108 (Appellate Court of Illinois, 2000)
Weaver v. State Farm Insurance Companies
609 N.W.2d 878 (Supreme Court of Minnesota, 2000)
Correll v. Distinctive Dental Services, P.A.
594 N.W.2d 222 (Court of Appeals of Minnesota, 1999)
Lenz v. Depositors Insurance Co.
561 N.W.2d 559 (Court of Appeals of Minnesota, 1997)
Shields v. Goldetsky
552 N.W.2d 226 (Supreme Court of Minnesota, 1996)
Allstate Insurance Co. v. Nodak Mutual Insurance Co.
540 N.W.2d 614 (North Dakota Supreme Court, 1995)
Mely v. State Farm Insurance Co.
530 N.W.2d 216 (Court of Appeals of Minnesota, 1995)
Copper Mountain, Inc. v. Poma of America, Inc.
890 P.2d 100 (Supreme Court of Colorado, 1995)
Amdahl v. Green Giant Co.
497 N.W.2d 319 (Court of Appeals of Minnesota, 1993)
Yale University v. Blumenthal
621 A.2d 1304 (Supreme Court of Connecticut, 1993)
Spaeth v. Warren
478 N.W.2d 319 (Court of Appeals of Minnesota, 1991)
Anderson v. Federated Mutual Insurance Co.
465 N.W.2d 68 (Court of Appeals of Minnesota, 1991)
Michael-Curry Companies v. Knutson Shareholders Liquidating Trust
449 N.W.2d 139 (Supreme Court of Minnesota, 1989)
Packer River Terminal, Inc. v. City of Minneapolis
445 N.W.2d 269 (Court of Appeals of Minnesota, 1989)
Preferred Financial Corp. v. Quality Homes, Inc.
439 N.W.2d 741 (Court of Appeals of Minnesota, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
123 N.W.2d 371, 266 Minn. 284, 1963 Minn. LEXIS 735, Counsel Stack Legal Research, https://law.counselstack.com/opinion/layne-minnesota-co-v-regents-of-the-university-of-minnesota-minn-1963.