Amdahl v. Green Giant Co.

497 N.W.2d 319, 1993 Minn. App. LEXIS 260, 1993 WL 69700
CourtCourt of Appeals of Minnesota
DecidedMarch 16, 1993
DocketC2-92-1611, C8-92-1709
StatusPublished
Cited by9 cases

This text of 497 N.W.2d 319 (Amdahl v. Green Giant Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amdahl v. Green Giant Co., 497 N.W.2d 319, 1993 Minn. App. LEXIS 260, 1993 WL 69700 (Mich. Ct. App. 1993).

Opinion

OPINION

RANDALL, Judge.

Respondents Don Amdahl, Harold Berg-strom, and Thomas Miller commenced this action in Meeker County District Court against appellant Green Giant Company seeking recovery of losses arising out of vegetable acreage contracts entered into with appellant Green Giant Company. In their complaint, respondents allege violations of the Minnesota Securities Act (Count I) and breach of contract (Count II). Appellant Green Giant challenges the trial court’s order denying its motion to compel arbitration of the breach of contract claim. Green Giant also challenges summary judg *320 ment in favor of respondents on the breach of contract claim. By order of this court, the separate appeals have been consolidated. We reverse.

FACTS

Green Giant purchases large quantities of raw vegetables from farmers/growers for processing and marketing. The claims of respondents arise out of their entry into vegetable acreage contracts with Green Giant in 1981 and their participation in the 1981 “Green Line Futures Program” (futures program). The profits or losses to the growers who opted to participate in the futures program (rather than the “fixed compensation contracts”) were tied to the price of field corn futures contracts as reflected on the Chicago Board of Trade. Under the standardized fixed compensation contracts, the growers were to be paid for their crops in two roughly equal installments, known as the “Schedule A” payment and the “Schedule B” payment. However, each of the contracts between the growers and Green Giant provides, “If the Green Line [Futures] Program is exercised the Schedule ‘B’ payment will be adjusted as appropriate.”

Each grower received his Schedule A payment from Green Giant in the fall of 1981. The amount of the Schedule B payment, due in June of 1982, would be determined by defined commodity futures prices.

During the 1981-82 crop year, the price of field corn declined resulting in substantial losses to the growers participating in the futures program. Many of the growers participating in the futures program received less money than they would have received if they had chosen the fixed-price alternative. For many of the growers participating in the futures program, the price ultimately due to them under their contracts was less than the amount of their Schedule A payments.

Green Giant sought to recover from the growers their losses in excess of the Schedule B payment, claiming that it was entitled to recover all or a part of the schedule A payments as well. Green Giant (1) deducted the losses from growers’ Schedule B payments; (2) demanded and received from growers payments alleged to be due and owing; or (3) initiated arbitration against the growers.

In 1983, six growers, Frank Marshall, Louis Hedlund, Richard Thorp, Kenneth Berggren, Fred Behnke, and Oliver Berg-strom, commenced an action in federal district court in Minnesota (the Marshall action). The complaint in the Marshall action alleged, among other things, violations of the Minnesota Securities Act and breach of contract based upon Green Giant’s efforts to recover amounts from the growers in excess of their Schedule B payments.

Each of the 1981 contracts at issue contained the following arbitration clause:

ARBITRATION: Any controversy or claim arising out of or relating to this contract shall be settled by arbitration in the City of Glencoe in accordance with the Rules of the American Arbitration Association. It is agreed that the decisions of the Arbitrator shall be final and binding upon both parties.

Upon motion by Green Giant, the federal district court stayed all further proceedings in the Marshall action and ordered the Marshall plaintiffs and Green Giant to arbitrate the breach of contract claim.

The parties then arbitrated the contract claim of Louis Hedlund (the Hedlund arbitration). The arbitrator ruled in favor of Hedlund, interpreting the contract as precluding Green Giant from recovering sums from Hedlund in excess of the Schedule B payment.

Upon motion by the Marshall plaintiffs, Marshall, Hedlund, Thorp, Berggren, Behnke, and Bergstrom, the federal district court confirmed the arbitrator’s award in favor of Hedlund and against Green Giant. The six growers also moved the federal court for summary judgment on their breach of contract claim based upon the collateral estoppel effect of the Hedlund award. The court denied the growers’ motion, concluding that whether “the issues decided in Hedlund’s arbitration are identical to those between the defendant and the *321 remaining plaintiffs ” is a dispute which falls within the scope of the arbitration agreement. (Emphasis added.)

In the second arbitration (the Berggren arbitration), the arbitrator consolidated the disputes between Green Giant and the five remaining named plaintiffs, Berggren, Marshall, Bergstrom, Thorp, and Behnke. Ruling in favor of the plaintiffs, the arbitrator concluded the Hedlund arbitration award controlled this (the Berggren) arbitration and collaterally estopped Green Giant.

Returning to federal district court, the Marshall plaintiffs moved for confirmation of the Berggren arbitration award, class certification, and entry of final judgment. Green Giant moved to vacate the arbitration award. Noting that the arbitrator correctly laid out the applicable law on the issue of collateral estoppel and then applied it, the district court confirmed the Berg-gren arbitration award. Although the court confirmed the Berggren award and ordered final judgment in favor of the Marshall plaintiffs, it denied plaintiffs’ motion for class certification on jurisdictional grounds.

The growers and Green Giant both appealed various rulings to the Eighth Circuit Court of Appeals. That court affirmed the district court’s confirmation of the Berg-gren arbitration award (granting collateral estoppel effect to the Hedlund arbitration). Marshall v. Green Giant Co., 942 F.2d 539, 550 (8th Cir.1991). The court also affirmed the district court’s denial of the Marshall plaintiffs’ motion for class certification. Id. at 549-50. On remand, the federal district court entered judgment in favor of the growers and dismissed the remaining state law claims for lack of federal jurisdiction.

This action was subsequently filed against Green Giant in Meeker County District Court by respondent growers Amdahl, Bergstrom, and Miller. Respondents, who were not involved in the Marshall action, alleged violation of the Minnesota Securities Act (Count I) and breach of contract (Count II). Respondents moved for class certification and for summary judgment on both counts. Green Giant moved to compel arbitration of both counts I and II and to stay the trial court proceedings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schultz v. GGNSC St. Paul Lake Ridge LLC
310 F. Supp. 3d 985 (D. Maine, 2018)
Cargill, Inc. v. Jorgenson Farms
719 N.W.2d 226 (Court of Appeals of Minnesota, 2006)
Community Partners Designs, Inc. v. City of Lonsdale
697 N.W.2d 629 (Court of Appeals of Minnesota, 2005)
State Farm Mutual Automobile Insurance Co. v. Cincinnati Insurance Co.
651 N.W.2d 542 (Court of Appeals of Minnesota, 2002)
CHURCHILL ENVIR. PARTNERS v. Ernst & Young
643 N.W.2d 333 (Court of Appeals of Minnesota, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
497 N.W.2d 319, 1993 Minn. App. LEXIS 260, 1993 WL 69700, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amdahl-v-green-giant-co-minnctapp-1993.